Holding. The judgment is reversed. The plaintiff, having established prescriptive and estoppel-based rights to drainage across the defendant's land, is entitled to injunctive relief to prevent obstruction of the old drainage ditch when the defendant failed to complete the agreed tile drainage system; the defendant is not entitled to judgment against the plaintiff for the plaintiff's share of the construction costs of an uncompleted drainage system.

The plaintiff and defendant, who owned adjacent quarters of land, had long maintained a cooperative drainage system where water from the plaintiff's property flowed through an open ditch across the defendant's land. In 1910, they agreed to replace this open ditch with tile drains, with the plaintiff contributing to the costs. The defendant failed to construct the tile drains according to the agreement, leaving gaps of 18–20 feet on the main drain and 6–8 rods on the branch drain. The plaintiff alleged the defendant also filled in or obstructed the old ditch to prevent water flow. The trial court found the plaintiff entitled to have the tile drains extended to the agreed endpoints but also awarded the defendant judgment for the plaintiff's share of construction costs and disbursements.

On appeal, the court found that the plaintiff had acquired a prescriptive right and an estoppel-based right to drainage across the defendant's property through decades of use and cooperation. Because the defendant failed to complete the tile drainage system as promised, the plaintiff was entitled to continue using the old ditch. The court determined that specific performance of the parol agreement to build the tile system could not be enforced, and therefore the plaintiff should not be required to pay for an incomplete drainage system. The defendant's judgment for costs and disbursements was improper.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether the plaintiff acquired prescriptive and estoppel-based rights to drainage across adjacent property
  • Whether specific performance could be enforced for a parol agreement to construct tile drainage
  • Whether the defendant obstructed the plaintiff's pre-existing drainage rights by failing to complete the new system
  • Whether the plaintiff must pay for construction costs when the agreed drainage system was not completed as promised

Procedural posture

The plaintiff appealed from a judgment that granted the plaintiff the right to have tile drains extended to agreed points but also awarded the defendant judgment for the plaintiff's share of construction costs and disbursements.

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

Dibell, C.

This action was brought to compel the defendant to abate and remove the obstruction to the flow of water through a drain upon his land, and for damages. By the judgment entered it was determined that the plaintiff was entitled to have certain tile drains upon the land of the defendant extended to his land; that the defendant was entitled to have a certain tile drain on the plaintiff’s land extended to his land; that the defendant was entitled to judgment against the plaintiff for certain sums which the plaintiff had agreed to pay as a part of the cost of construction of the tile drains on defendant’s land; and that the defendant have judgment for his disbursements. The plaintiff appeals from the judgment.

1. The plaintiff owns the southwest quarter and the defendant owns the northwest quarter of a section of land in Waseca county. There is a slough covering a portion of the two quarters into which the surface waters drain, the lowest portion of which is very near the quarter line between the two, perhaps a little south of it. For many years, and as far back as 1877, a ditch ran from plaintiff’s land into the slough, and out of the slough through the defendant’s land was a drain to the north and east through a natural watercourse. The plaintiff did work in keeping the ditch through the defendant’s quarter in condition for taking care of the waters which came into the slough, he and the defendant co-operating in maintaining a ditch for the drainage of their lands, and forall these years there was no trouble or controversy. The plaintiff had a prescriptive right to drainage across the defendant’s quarter. Baldwin v. Fisher, 110 Minn. 186, 124 N. W. 1094, and cases cited. Tie also had the right of drainage by estoppel within the doctrine of Munsch v. Stelter, 109 Minn. 403, 124 N. W. 14, 25 L.R.A.(N.S.) 727, 134 Am. St. 785.

In June, 1910, the plaintiff and the defendant agreed to substitute a system of tile drainage for the open drainage, the plaintiff to pay a part of the cost of it. The main tile drain was to start at the low part of the slough at the quarter line following the old ditch to the north and east off the defendant’s land. From this main drain a branch drain was to run south to the quarter line at a point some distance easterly of the starting point of the main drain. The court states in its memorandum, and the evidence supports it, though it is not specifically found, that a tile drain was to extend easterly along the quarter line from the point of its intersection with the branch ditch. To this point of intersection the plaintiff was to extend a tile drain which was upon his quarter.

The tile drain was not constructed by the defendant as agreed. The main drain did not reach the quarter line by some 18 or 20 feet. The branch drain did not reach the quarter line by some six or eight rods. The plaintiff claims that the defendant filled in and obstructed the old ditch at the 18 or 20 foot space mentioned. The court found that he did not. Upon a careful review of the evidence we think that it must be held that he did. There was throughout an unconcealed purpose on the part of the defendant to prevent the plaintiff making beneficial use of the tile drainage. Although the court found to the contrary, and while not particularly important here, the evidence is quite cogent that the defendant ploughed his land to the east along the quarter line to prevent the surface waters coming from the plaintiff’s land.

2. If the defendant failed to construct the substituted tile drainage the plaintiff was entitled to the use of the old ditch; and if the defendant filled in the southerly 18 or 20 feet of it, or otherwise obstructed the plaintiff’s right to the flow of water through it, the plaintiff was entitled to injunctive relief. Baldwin v. Fisher, supra; Munsch v. Stelter, supra; Mueller v. Fruen, 36 Minn. 273, 30 N. W. 886.

3. The court found that the plaintiff was entitled to have the main ditch and the branch ditch extended to the agreed points. We are not able to see that specific performance could be enforced of this parol agreement to construct a tile drainage system to take the place of the open drainage. Robinson v. Luther, 134 Iowa, 463, 109 N. W. 775. The case was not an action for specific performance, nor was it tried as such, nor was relief by way of specific performance given. If it were an action for specific performance, the plaintiff was the prevailing party, and was entitled to disbursements, and the judgment was wrong in giving them to the defendant; and the defendant was not entitled to judgment against the plaintiff for his agreed portion of the cost of construction of the drain so long as it remained uncompleted.

Judgment reversed.