F.W. Sims, Inc., Appellant, v. T. Moriarty & Son, Inc., et al., Respondents, et al., Defendants

New York Supreme Court, Appellate Division1999-10-21
265 A.D.2d 234696 N.Y.S.2d 453

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

—Judgment, Supreme Court, New York County (Martin Evans, J.H.O.), entered September 2, 1998, after a nonjury trial, which, to the extent appealed from, limited plaintiffs recovery of delay damages to the principal sum of $4,095, unanimously affirmed, without costs.

We agree with the trial court that “total cost” method of calculating construction delay damages (see, Fehlhaber Corp. & Horn Constr. Co. v State of New York, 69 AD2d 362, 368) was inapplicable under the particular circumstances of this case, and that plaintiff did not otherwise sufficiently prove delay-caused labor costs by non-speculative evidence (see, Mid-State Precast Sys. v Corbetta Constr. Co., 202 AD2d 702, 704, lv dismissed 84 NY2d 923, 86 NY2d 855). We have considered plaintiffs remaining arguments and find them unavailing. Concur — Sullivan, J. P., Nardelli, Tom, Mazzarelli and Friedman, JJ.