LAW.coLAW.co

BAKER v. WEAVER

Supreme Court of Georgia1898-04-13
104 Ga. 228

Summary

Holding. The court affirmed the trial judge's order requiring Baker to lower his dam, holding that a court of equity has the authority to order property to remain in status quo pending final hearing and may compel obedience to its orders through contempt proceedings, and that Baker's unilateral action to flood the land in response to the court's partial denial of his injunction request constituted a clear violation of the court's authority.

Baker owned a mill and mill-pond and sought an injunction against Weaver to prevent him from clearing trees and undergrowth along the pond's banks and from digging ditches that would alter water flow into the pond. The trial judge granted a partial injunction protecting the trees and undergrowth but refused to restrain Weaver from cultivating land he had already cleared. Dissatisfied with this outcome, Baker raised his dam to block water flow and flood Weaver's cleared land, effectively taking matters into his own hands to prevent Weaver's cultivation.

Weaver then sought a contempt citation against Baker, and the trial court ordered Baker to lower his dam within eleven days to restore the conditions that existed when the earlier injunction was issued. Baker appealed, arguing that the order to lower the dam constituted an impermissible mandatory injunction. The appellate court rejected this argument, finding that Baker's decision to manipulate his dam after losing part of his injunction request amounted to a violation of the court's order and a contempt of court.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether a court of equity may order restoration of property to its prior condition to preserve the status quo pending final hearing
  • Whether an order to lower a dam is a prohibited mandatory injunction or a permissible status quo preservation measure
  • Whether a party's self-help measures taken in response to an unfavorable partial injunction decision constitute contempt of court

Procedural posture

Baker appealed from the trial court's contempt order requiring him to lower his dam after the court had previously granted a partial injunction in his favor and refused to restrain Weaver from cultivating cleared land.

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

Simmons, C. J.

Baker owned a mill and mill-pond. Weaver claimed to own the land on the sides of the pond. He was cultivating part of this land, and undertook to clear away the trees and undergrowth near the banks of the pond. Baker claimed title to the land on one side of the pond, and claimed that the trees and undergrowth on the other sidewere appurtenances to his mill property. He filed an equitable petition seeking to enjoin Weaver from cultivating the land already cleared, cutting or clearing the trees and undergrowth on the banks of the pond, and digging ditches which would empty surface-water into his pond and fill it in. On the hearing the judge granted an injunction restraining Weaver from cutting the trees and undergrowth on the banks of the pond and from digging any ditches which would empty into the pond, but refused to enjoin him from cultivating the land which he had already cleared. The evidence was conflicting as to the rights of the parties; and this court, according to numerous decisions, will not undertake to control the discretion of the trial judge in granting or refusing an injunction in such a case.

It appears that, after the refusal of the trial judge to restrain Weaver from cultivating the cleared land, Baker took the matter into his own hands by raising and building up his dam so as to stop the flow of the water and back it up-stream in such manner as to overflow the land cleared by Weaver, and thus prevent its cultivation. Weaver applied to the court for a rule nisi calling upon Baker to show cause why he should not be attached for contempt. At the hearing of this rule nisi the above facts appeared. The court ordered Baker, within eleven days, to lower the dam to the height at which it had stood at tlie time of the previous order. Baker excepted to this order aud brought the case here. The ground urged in the argument here was, that this was a mandatory injunction and that the court was without authority to pass it. We do not agree with counsel for plaintiff in error in this view of the case. While it is true that the judge can not, in this State, grant a mandatory injunction at a preliminary hearing, it is likewise true that he has full power in an equity case to order the property to remain in statu quo until the hearing. It would be a source of regret to hold that where a court of equity has acquired jurisdiction of the parties and the property, it can not compel obedience to its orders and-preserve the rights of all parties until the final hearing. Baker applied to the court for relief. The court granted it in part and refused it in part. The court thereby said to him: “I will restrain Weaver from cutting the trees and undergrowth, so as to protect you until final hearing of the case; but you have not made out such a title to the cleared land as would authorize me to restrain him from entering upon and cultivating it, and I therefore refuse this part of your prayer.” Baker, by his subsequent conduct, replied: “You refuse to restrain Weaver from cultivating this land, but I will take the matter into my own hands and effect my purpose by flooding the land.” This, in our opinion, was clearly a violation of the order of court and was a contempt. The court had full power to order him to lower the dam so as to restore the status which had existed at the time the injunction was refused, and, if he refused or failed to obey this order, to attach him for contempt. Johnson v. Hall, 83 Ga. 281.

Judgment affirmed.

All concurring, except Cobb, J., absent.