LAW.coLAW.co

MARYLAND PUBLIC SERVICE COMMISSION and New Jersey Board of Public Utilities, Petitioners v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent American Municipal Power, Inc., et al., Intervenors

United States Court of Appeals for the District of Columbia Circuit2011-02-08No. No. 09-1296
632 F.3d 1283

Summary

Holding. The petition for review is denied because the Federal Energy Regulatory Commission adequately explained that the Reliability Pricing Model rates were just and reasonable, supported by substantial evidence including analysis from expert consultants, market monitors, and independent reviewing groups showing no market power abuse and legitimate reasons for price increases.

The Maryland Public Service Commission and New Jersey Board of Public Utilities challenged electricity rates established under a new pricing model adopted by the Federal Energy Regulatory Commission. The new Reliability Pricing Model was designed to encourage investment in electrical generation capacity by replacing an older pricing structure that the Commission found inadequate. The state regulators argued that the higher rates resulted from suppliers exercising market power during auctions held before a three-year advance-bidding period could take effect.

The Commission had implemented three safeguards against market power abuse, including requiring suppliers to offer available capacity, substituting proxy bids where market power was identified, and establishing auctions three years in advance of delivery to allow new competitors to enter the market. For interim deliveries before this long-lag auction system became fully operational, the Commission permitted shorter-lag auctions. The Commission concluded that price increases were not attributable to market manipulation but rather reflected legitimate transmission constraints that the old model had ignored, and that the new rates would spur necessary investment in generation capacity.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether new electricity rates under the Reliability Pricing Model were just and reasonable
  • Whether suppliers exercised market power to artificially inflate prices during interim auction periods
  • Appropriate standard of review for FERC rate design decisions
  • Whether transmission constraints justified higher rates in certain regions

Procedural posture

State regulatory commissions petitioned for review of FERC orders approving the Reliability Pricing Model and the resulting electricity rates.

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

Opinion PER CURIAM.

PER CURIAM:

Petitioners, the Maryland Public Service Commission and the New Jersey Board of Public Utilities, challenge higher electricity rates that were the result of a new pricing model the Federal Energy Regulatory Commission adopted to encourage increased investment in capacity. We deny the petition for review because the Commission adequately explained why the new rates were just and reasonable.

Respondent-Intervenor PJM Interconnection, LLC, (“PJM”) is the regional transmission organization for thirteen mid-Atlantic states and the District of Columbia. Among its duties, PJM is responsible for preventing interruptions to the delivery of electricity in that region by ensuring that its system has sufficient generating capacity. In August 2005, PJM filed a proposal to replace its old pricing model with what it called the Reliability Pricing Model (RPM), arguing that the old model did not sufficiently encourage investment in electrical capacity. FERC agreed, and adopted the RPM with some modifications. See PJM Interconnection, L.L.C., 115 FERC ¶ 61,079 (2006) (finding preexisting pricing model to be unjust and unreasonable); PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 (2006) (approving, with conditions, the RPM); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318 (2007) (clarifying nature and extent of order approving the RPM). Petitioners argue that the RPM allowed suppliers of electric capacity to exercise their market power to set artificially inflated prices in auctions held before May 2008.

The Commission anticipated concerns about the suppliers’ market power and adopted three measures to mitigate this market power. First, the Commission oversees the availability of physical capacity and, as a general matter, requires that suppliers offer all available capacity at RPM auctions. Second, where the Commission determines that a supplier has market power, it requires PJM to substitute a proxy bid, determined by a formula that the RPM provides, in the place of the supplier’s actual offer. This pushes high bids down to more competitive levels. And third, what is most relevant to this petition, the RPM encourages the entry of new suppliers into the market with auctions that set rates three years in advance of delivery. For example, the May 2008 auction set the rate for the delivery year beginning in May 2011. This lag time allows competition from new suppliers that lack the capacity to deliver electricity now but could develop that capacity within three years of winning a bid.

Of course, the protection of the three-year lag would not be available for the sale of electricity that needed to be delivered before May 2011, and the Commission allowed auctions for those deliveries to proceed under the RPM with a shorter lag. Petitioners claim that this shorter lag time allowed suppliers to exercise market power to artificially inflate prices in those auctions. They fault the Commission for failing to determine whether the challenged rates were just and reasonable, and for relying instead on the conclusion that the provisions of the RPM were followed.

But the Commission did determine that the rates were just and reasonable. It reviewed analytical reports from expert consultants retained by the states, PJM’s Market Monitor (who reviewed the auctions and specifically addressed the issue of market power), and an independent consulting group hired by PJM. Only then did it conclude that there was no reason to believe that market power was being exercised. The Commission found instead that prices went up in some areas because the RPM accounted for transmission constraints that increased the costs of delivering electricity to those areas. The old pricing model, by contrast, had assumed that capacity created anywhere within PJM’s territory could readily be transmitted to any other point in that territory, an assumption that created artificially low prices for areas facing transmission constraints. The Commission recognized that the price hikes petitioners challenge would encourage much needed long-term investment in energy capacity. And there is substantial evidence the Commission was right. The PJM’s independent report found that the RPM spurred an unprecedented amount of potential new resources — including approximately 33,000 MW of new generation projects — and that reliability had been increased to meet the PJM’s target levels.

Given this evidence, we conclude that the Commission had a substantial basis on which to conclude that the RPM was an appropriate tool for increasing reliability in electricity markets, that the RPM did precisely what it was intended to do, even during the transition period before the three-year lag could take effect, and that the price hikes in its wake were attributable to legitimate causes, not the suppliers’ exercise of market power. See, e.g., FPL Energy Maine Hydro LLC v. FERC, 287

F.3d 1151, 1160 (D.C.Cir.2002) (stating that the Commission’s factual findings are conclusive if supported by substantial evidence, which “requires more than a scintilla, but can be satisfied by something less than a preponderance of the evidence”). As we have stated before, “[b]ecause issues of rate design are fairly technical and, insofar as they are not technical, involve policy judgments that lie at the core of the regulatory mission, our review of whether a particular rate design is just and reasonable is highly deferential.” Pub. Utils. Comm’n v. FERC, 254 F.3d 250, 254 (D.C.Cir.2001) (internal quotation marks omitted). Accordingly, we uphold the Commission’s orders under the arbitrary and capricious standard. See, e.g., Sithe/Independence Power Partners v. FERC, 165 F.3d 944, 948 (D.C.Cir.1999).

For the foregoing reasons, the petition for review is

Denied.

. As a preliminary matter, the Commission contends that under our decision in Blumenthal v. FERC, 552 F.3d 875 (D.C.Cir.2009), it is not enough for a petitioner to show that the challenged rates are not just and reasonable; the petitioner must also propose rates that are. See id. at 885. But the language cited by the Commission was unnecessary to our holding and inaccurate insofar as it implied that a challenge to rates must propose alternative rates that are just and reasonable. As the Federal Power Act clearly provides, “[wjhenever the Commission, after a hearing held upon its own motion or upon complaint, shall find that any rate ... [under its jurisdiction] is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate ... tobe thereafter observed and in force, and shall fix the same by order.” 16 U.S.C. § 824e(a) (emphasis added); see also Tenn. Gas Pipeline Co. v. FERC, 860 F.2d 446, 454 (D.C.Cir.1988) (“Once [FERC determines a rate is unjust], the Commission is required to reach a further determination: the just and reasonable rate to be fixed in place of either an unlawful proposed or existing rate.”). It is the Commission’s job — not the petitioners — to find a just and reasonable rate.