LAW.coLAW.co

Lexington Print Works vs. Inhabitants of Canton & others

Massachusetts Supreme Judicial Court1898-06-22
171 Mass. 414

Summary

Holding. The court retained jurisdiction in equity and reversed the lower court's dismissal, holding that the plaintiff may recover all damages sustained up to the filing of the bill through this equitable action, rather than being limited to the statutory condemnation remedy, because the plaintiff was entitled to relief when the bill was filed and the original defect was subsequently cured by the defendants' own action.

Lexington Print Works brought an equity bill against the Inhabitants of Canton and water commissioners after the company's initial challenge to a water-taking certificate succeeded. The defendants subsequently filed a corrected certificate in 1897 that cured the defect in the original certificate by specifying the quantity of water being taken. The defendants argued that any damages claim, including those arising from the period before the corrected certificate was filed, must be pursued through the statutory condemnation remedy rather than in the equity suit. The plaintiff contended it was entitled to have all damages assessed in the pending bill.

The court held that although the defendants had authority to take the water and eventually complied with statutory requirements, the plaintiff was entitled to equitable relief at the time it filed the bill, when the original certificate was still defective. Because the defect was subsequently cured through defendant's own action while the suit was pending, the court retained jurisdiction in equity to assess damages for the unlawful interference that occurred before the valid taking. The court distinguished this situation from cases where the plaintiff failed to act promptly or where the plaintiff should have pursued the statutory condemnation remedy from the outset.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether a party entitled to equitable relief when filing a bill loses that remedy if the defendant cures the defect during litigation
  • Whether the statutory condemnation remedy is the exclusive remedy once a valid taking certificate is filed
  • Proper forum for assessing damages from a defective taking that is later validated

Procedural posture

The case returned to court following a prior decision voiding the original water-taking certificate, with the defendants having since filed a corrected certificate and raising the question of whether damages must be assessed under the statutory condemnation procedure or may be determined in the pending equity suit.

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

Morton, J.

After the former decision in this case, reported 167 Mass. 341, in which it was held that the taking under the instrument filed in the registry of deeds on October 12,1894, by the water commissioners was void, the commissioners filed another certificate on March 30, 1897, in which the quantity taken was stated as half a million gallons daily, being the amount specified in the vote of the town. The plaintiff does not contest the legality of this last certificate, or of the taking thereunder. The defendants have filed a supplemental answer setting it up, and contends that for all damages caused by taking half a million gallons daily, as well before as after the filing of the last certificate, the plaintiff’s remedy is by petition in the manner prescribed in the acts authorizing the taking, which is the same as that where land is taken for the laying out of highways. St. 1885, c. 95, § 4. St. 1886, c. 168. The plaintiff contends that it is entitled to have all the damages which it sustained up to the time of bringing this bill assessed in this suit. These contentions present the principal, if not the only question in the case.

It is to be assumed that the defendants intended to proceed in accordance with the acts authorizing them to take the water for public uses. The plaintiff does not indeed controvert this. The only defect in the condemnatory proceedings was that the certificate omitted to state the quantity of water taken.

It is clear that after the filing of the last certificate the plaintiff could not have maintained an action of tort for the diversion of the amount named in it prior to the time of such filing. Moore v. Boston, 8 Cush. 274. Spaulding v. Arlington, 126 Mass. 492. Lewis v. Boston, 130 Mass. 339. It is also clear that after an actual taking, and before the filing of a certificate, the plaintiff could have maintained a petition for the assessment of its damages which would have included past and future damages. Moore v. Boston, ubi supra. Still further, it is clear that, if no certificate had been filed, or if the defendants had chosen to rely upon an insufficient one, the plaintiff would have been entitled to an injunction restraining the diversion, or to maintain an action of tort for the damages caused thereby. Wamesit Power Co. v. Allen, 120 Mass. 352. Lund v. New Bedford, 121 Mass. 286. Warren v. Spencer Water Co. 143 Mass. 9. Hollingsworth & Vose Co. v. Foxborough Water Supply District, 165 Mass. 186.

This case, however, is unlike any of those thus described, and more nearly resembles that of Woodbury v. Marblehead Water Co. 145 Mass. 509. When the bill was filed, the plaintiff was entitled to relief under it. Since the filing of the bill, the defect in the original certificate filed by the defendants has been cured. The plaintiff therefore no longer has any just ground for the issuing of an injunction to restrain the diversion of the water. But, speaking generally, jurisdiction in equity is fixed if the plaintiff is entitled to relief at the time of the bringing of the bill, and the court will retain the bill and administer a remedy in damages if that is appropriate, where the plaintiff loses his right pendente lite to purely equitable relief without fault on his part through some action on the part of the defendant. Milkman v. Ordway, 106 Mass. 232. Woodbury v. Marblehead Water Co. 145 Mass. 509. Brande v. Grace, 154 Mass. 210. Case v. Minot, 158 Mass. 577, 588, 589.

The defendants contend that this doctrine is not applicable to this case, and that the cases of Moore v. Boston, Lewis v. Boston, and Spaulding v. Arlington, ubi supra, are inconsistent with it. It is true that the statutes which authorize the taking provide a method for the assessment of damages. But we think that this does not take away any remedy which the plaintiff may have for what turns out to be a wrongful interference with his rights, though done under a supposed statutory authority, provided he seasonably avails himself of such remedy. If, after a defectivo taking has been cured by a valid taking, or if, after a taking valid in all respects except that the certificate was not filed within the proper time, the party aggrieved by such taking brings a petition, in the manner provided by statute, for the recovery of his damages, it well may be held that all damages to which he is entitled should be assessed in such proceedings. Such are the cases of Lewis v. Boston and Spaulding v. Arlington. So also, if, after an actual taking, the party aggrieved thereby files a petition for the assessment of his damages, it well may be held that the defendant should not be permitted to defeat his right to recover, because it had not filed, after the taking, within the time fixed, the certificate required. Such is the case of Moore v. Boston. But we find no reason, either in these cases or in the nature of the condemnatory proceedings, for holding that a party who has seasonably brought his bill to prevent an interference with his rights, which is unlawful because the defendant has failed to comply with statutory requirements in regard to the taking, should be compelled, because the defect is subsequently cured, to have his damages for such unlawful interference assessed under the statute which authorizes the taking. It is argued that the rule of damages might be different in such a case from what it would be under the statute, but we do not find it necessary to decide that now.

The result is, that a majority of the court think that the case should stand for hearing in regard to all damages which the plaintiff has sustained down to the filing of the bill.

So ordered.