LAW.coLAW.co

Oscar J. Gagnon vs. Herbert Ainsworth & another

Massachusetts Supreme Judicial Court1933-06-29
283 Mass. 488

Summary

Holding. The appeal is remanded to allow the plaintiff to amend the first count of the declaration to conform to the proof presented at trial; if amended within thirty days, judgment shall be entered for the plaintiff on the auditor's report for the amended count, and judgment is affirmed for the plaintiff on the second count; if the plaintiff does not file a motion to amend, judgment is entered for the defendants on the first count.

A contractor sued to recover the unpaid balance on a house construction contract and for extra labor and materials. The defendants argued the original contract was illegal because it specified a nine-inch foundation wall width that violated the city building code. The court rejected this defense, finding that the building code contained no specific requirement for cinder block foundations (the material used), so the original contract terms were not unlawful. The defendants also claimed the contractor performed defectively, pointing to damaged window and door jambs. The auditor found the contractor substantially performed the work and deducted $63 for defects from the claimed $500 balance.

The court affirmed the auditor's finding on the extra work count but remanded the main contract count for amendment. Under Massachusetts law, recovery on a building contract typically requires complete performance, but the court found the evidence was fairly tried and the defects were minor. The contractor was given the opportunity to amend the pleadings to frame the claim as quantum meruit (recovery for the reasonable value of work performed), which would allow recovery despite incomplete performance.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether an original contract specifying non-code-compliant foundation dimensions is illegal when the building code contains no specific requirement for the material used
  • Whether a contractor who substantially performed a building contract despite minor defects may recover the contract balance
  • Application of the complete performance rule versus quantum meruit recovery in building contracts

Procedural posture

The defendants appealed from a Superior Court judgment entered on an auditor's report finding for the plaintiff on both counts of the declaration.

Authorities cited

No cited authorities resolved to law.co cases yet.

Opinion

majority opinion

Donahue, J.

The plaintiff, who made a written contract with the defendants for the erection of a house on their land in Fall River, has brought suit seeking to recover under the first count of the declaration the unpaid balance of the contract price and under the second count for extra labor and materials furnished. The case was heard by an auditor whose findings of fact were, by the terms of the order of reference, made final. Manning v. Woodlawn Cemetery Corp. 239 Mass. 5, 9. Merrimac Chemical Co. v. Moore, 279 Mass. 147. The auditor found for the plaintiff on each count of the declaration and a judge of the Superior Court ordered the entry of judgment for the plaintiff on the auditor’s report, from which order the defendants have appealed.

1. The contract provided that the walls of the building should be constructed of cinder blocks and that the width of the foundation walls should be nine inches. After work on the foundation had begun the inspector of buildings of the city ordered the plaintiff to increase the width of the foundation walls to twelve inches. The parties thereupon discussed the cost of constructing the foundation walls with a width of twelve inches and the defendants agreed to pay the plaintiff a fair charge for the extra work and ma terial required by the change. The foundation walls built by the plaintiff were twelve inches wide. The building when constructed was inspected and approved by the inspector of buildings. The building code of the city of Fall River provides that the width of foundations of buildings constructed of wood shall be sixteen inches and of buildings constructed of brick eighteen inches. It contains no provision as to the width of the foundations of buildings constructed of cinder blocks, which material the auditor found was heavier- than wood and lighter than brick. The defendants contend that the plaintiff cannot recover because the contract called for a width of foundation wall which was illegal. While acts prohibited and penalized by building laws are illegal and a contract for the performance of such acts is not enforceable, Eastern Expanded Metal Co. v. Webb Granite & Construction Co. 195 Mass. 356, no such case is here presented. A building law “being penal in nature and in derogation of common right, is not to be enlarged beyond its plain import, and as a general rule is strictly construed.” Commonwealth, v. Hayden, 211 Mass. 296, 297. We cannot write into the building code a provision which its framers did not see fit to put there. The contract, upon which the first count of the declaration is based, was not an illegal contract.

2. The first count of the declaration alleges that the plaintiff performed the written contract and that he is entitled to receive $500 which was the unpaid balance of the contract price. The defendants’ amended answer contains a general denial and, among others, the allegation that the plaintiff “failed to construct said house in a good and workmanlike manner.” The auditor found that “window and door jambs have spread, due to improper workmanship,” that there should be allowances made of $53 on that account and $10 for repairing ceilings, and that the plaintiff is entitled to recover $437 on the first count. The rule in this Commonwealth, which has been consistently followed, is that there can be no recovery on a count based solely on a building contract unless complete performance is proved. Cutter v. Arlington Construction Co. 268 Mass. 88, 92, and cases cited. In this case we do not think that the rule requires a new trial as to the facts although it does make necessary the amendment of the first count of the declaration in order to permit recovery by the plaintiff thereon. The report shows that the defendants were permitted to offer evidence of improper workmanship becoming manifest after the house was completed and accepted by the defendants. There is nothing to indicate that any limitation was put upon the introduction of evidence of improper workmanship or materials or that the finding of the auditor on the first count does not fairly represent the balance of the amount of net benefits received by the defendants from the plaintiff under the written contract. The facts found by the auditor show no lack of good faith on the part of the plaintiff or intentional departure by him from the terms of the contract. There was substantial although not complete performance. The issues raised if the first count were in the form of a quantum, meruit seem to us to have been fully and fairly tried. (Pizer v. Hunt, 253 Mass. 321, 331. Bucholz v. Green Bros. Co. 272 Mass. 49, 55.) It appears to us that the plaintiff should be given the opportunity to present a motion to amend the first count in the declaration so that the pleadings may conform to the proof. The plaintiff is given leave within thirty days after the date of the rescript to file in the Superior Court a motion for an appropriate amendment to the first count of the declaration so that it may conform to the proof; if such motion is filed, judgment for the plaintiff is to be entered on the auditor’s report on such amended first count; if such motion is not filed, judgment is to be entered for the defendants on the first count of the declaration. In any event judgment on the auditor’s report is to be entered for the plaintiff on the second count of the declaration.

So ordered.