LAW.coLAW.co

World Energy LLC v. Air Products and Chemicals, Inc.

2026-07-06

Authorities cited

Opinion

majority opinion

IN THE COURT OF CHANCERY OF THE STATE OF DELAWARE

WORLD ENERGY, LLC, WORLD ENERGY )

LOS ANGELES, LLC, ALTAIR )

PARAMOUNT, LLC, and PARAMOUNT )

PIPELINE, LLC, )

)

Plaintiffs, )

v. ) C.A. No. 2025-0912-MTZ

)

AIR PRODUCTS AND CHEMICALS, INC., )

and AIR PRODUCTS MANUFACTURING )

LLC, )

)

Defendants. )

MEMORANDUM OPINION

Date Submitted: January 16, 2026

Date Decided: July 6, 2026

Lauren Dunkle Fortunato, Jason W. Rigby, Alyssa T. Atkisson McKeever, YOUNG CONAWAY STARGATT & TAYLOR, LLP, Wilmington, Delaware; Matthew G.

Mrkonic, Tucker R. Hunter, HONIGMAN LLP, Detroit, Michigan, Attorneys for Plaintiffs.

John L. Reed, Michael A. Carbonara, Jr., DLA PIPER LLP (US), Wilmington, Delaware; Steven M. Rosato, DLA PIPER LLP (US), New York, New York,

Attorneys for Defendants.

ZURN, Vice Chancellor.

Two major players in the alternative fuel industry teamed up to convert a gas

refinery to make renewable jet fuel. As in many ventures, one side was to do the

work, and the other side was to help pay for it. The payor did not pay, so the worker

did not work. The payor came to this Court seeking a mandatory injunction requiring

the worker to make repairs to the refinery. I denied the requested relief from the

bench, and promised a written explanation.1 This opinion provides that explanation,

and grants the defendants’ motion to dismiss.

I. BACKGROUND2

Plaintiffs World Energy, LLC (“WE LLC”), World Energy Los Angeles, LLC

(“WELA”), AltAir Paramount, LLC (“AltAir”), and Paramount Pipeline, LLC

(“Paramount Pipeline,” and together with WE LLC, WELA, and Alt Air, “World

Energy”) operate biodiesel manufacturing plants throughout the United States.3

World Energy is a pioneer in the production of sustainable aviation fuel.4 AltAir

owns and operates the Paramount, California-based fuel refinery at the center of this

1

D.I. 36; D.I. 37.

2

I draw the following facts from the Verified Complaint, and the documents attached to or integral to it. See Wal-Mart Stores, Inc. v. AIG Life Ins. Co., 860 A.2d 312, 320 (Del. 2004). Citations in the form “Carbonara Aff.” refer to the affidavit of Michael A. Carbonara, Jr., available at D.I. 24. Citations in the form of “Hr’g Tr. —” refer to the transcript for the oral argument on the motions, available at D.I. 38. 3

D.I. 1 [hereinafter “Compl.”] ¶ 46.

4

Id. ¶ 62.

2

action (the “Paramount Facility”).5 In March 2018, World Energy acquired AltAir

and the Paramount Facility with the aim of converting it from a petroleum refinery

into “one of the most innovative and largest [sustainable] fuel refineries in the

world.”6

World Energy needed a hydrogen supplier for the Paramount Facility. 7 In

2019, it entered into a supply agreement with defendant Air Products and Chemicals,

Inc. (“APC,” and together with defendant Air Products Manufacturing LLC “Air

Products”), a global industrial gases supplier and leader in energy transition.8

World Energy and Air Products saw additional opportunity to develop the

Paramount Facility together.9 In March 2020, AltAir and Air Products entered into

an agreement by which Air Products would “optimize existing Paramount Facility

operations” on what would be called “Plant A,” and “design, engineer, and construct

certain expansions” on what would be called “Plant B.”10 The project got off to a

rough start, with delays and cost overruns continuing well into 2023.11 World

5

Id. ¶¶ 48–52.

6

Id.

7

Id. ¶¶ 55–57.

8

Id. ¶¶ 47, 58–61, Ex. 10.

9

Compl. ¶¶ 62–66.

10

Id. ¶¶ 69, 70, Ex. 3.

11

Compl. ¶¶ 79–92.

3

Energy alleges Air Products had overstated its expertise, and blames Air Products

for those issues.12

Yet World Energy opted to entrust Air Products with more responsibility. In

early 2023, the parties began exploring a path for World Energy to sell the Plant A

assets and “hand over daily operations” at the Paramount Facility to Air Products.13

On November 14, the parties executed a suite of agreements to that effect.14 The

Master Project Agreement and the Credit Agreement are central to this action.

A. The Master Project Agreement And Credit Agreement

The Master Project Agreement amended and restated the 2020 agreement in

its entirety.15 Air Products would perform optimization and expansion work on Plant

A and Plant B.16 Air Products was also required to “use commercially reasonable

efforts to cooperate with World Energy, as reasonably requested by World Energy,”

to “assist World Energy to secure working capital finance.”17

World Energy would help pay for Air Products’ work through two monthly

payments: (1) a monthly operating fee (the “MOF”), consisting of Air Products’

12

Id.

13

Id. ¶¶ 93–94.

14

Id. ¶¶ 94–98.

15

Compl. Ex. 1 [hereinafter “Master Project Agreement”] at 1.

16

Id. §§ 2.1–2.2.

17

Id. § 32.15.

4

“actual out-of-pocket costs and expenses”; and (2) a monthly fixed fee (the “MFF”),

representing a fixed “rate of return of 4.5% on the asset acquisition cost and other

capitalized costs.”18 Both payment obligations began accruing as soon as Air

Products began its work on Plant A.19 Both payments were due within thirty days

of receiving an invoice at the beginning of each month.20 World Energy was entitled

to dispute invoiced amounts in good faith within one year of the invoice date, but

had to pay any undisputed amount within thirty days of the invoice.21 While World

Energy could “dispute proposed adjustments and calculations,” it could not

“otherwise challenge the obligation to pay the MFF.”22 In the event of a dispute,

World Energy was required to “set forth the basis for its dispute” and provide

“supporting documentation with respect to the amount disputed.” 23

The monthly payments were material to the Master Project Agreement.

Section 8.2(B) expressly conditioned Air Products’ performance on timely payments

of all undisputed MOF and MFF invoice amounts.24 If World Energy failed to pay

18

Compl. ¶ 103; Master Project Agreement §§ 8.1, 9.2, 9.3, 9.5, Attachment B, Attachment K.

19

Master Project Agreement §§ 9.3, 9.5.

20

Id. § 8.1.

21

Id. § 8.2(A).

22

Id.

23

Id.

24

Id. § 8.2(B).

5

those undisputed amounts within fifteen days of their due date, Air Products was

entitled to suspend performance upon providing forty-five days’ written notice.25

And if World Energy failed to remedy a missed MFF payment within ninety days of

receiving that written notice, it would be deemed in “Material Breach.”26

Under Section 18.1(B), “[i]f a non-breaching Party believes that the other

Party is in Material Breach,” it must “promptly notify the other Party in writing, and

in reasonable detail, of the substance of, and basis for, its belief that a Material

Breach . . . has occurred.”27 If a Material Breach remained unremedied throughout

the applicable notice and cure period, the non-breaching party could then

“immediately terminate” the Master Project Agreement upon providing a

termination notice.28 Under Section 18.2, the parties must also provide written

notice of, and an opportunity to cure, any “Ordinary Breach.”29

Under the Credit Agreement, Air Products also agreed to loan World Energy

up to $270 million.30 The principal amount was split up into two tranches: $180

25

Id.

26

Id. §§ 18.1(A)–(i).

27

Id. § 18.1(B).

28

Id.

29

Id. § 18.2.

30

See Compl. Ex. 6 [hereinafter “Credit Agreement”].

6

million upon closing of the Credit Agreement and $90 million in January 2024.31

World Energy received the loan in full.32

The interest rate on the loan “[p]rior to the Plant B Commencement Date” was

set at 15%.33 Interest payments were due on the last day of each calendar month.34

Nonpayment, coupled with a failure to remedy the default within three business

days, constituted an “Event of Default.”35 Per Section 8, upon an Event of Default,

Air Products was entitled to terminate its commitments and “declare the Loans then

outstanding to be due and payable in whole,” with the aggregate principal, accrued

interest, and other fees “automatically [] due and payable, without presentment,

demand, protest or other notice of any kind.”36

31

Id. §§ 2.1(a)–(b).

32

See Carbonara Aff. Ex. B [hereinafter “Forbearance Agreement”] § 1.02(b) (“As of July 2, 2024, (i) the aggregate principal amount of Loans outstanding under the Credit Agreement was not less than $270,000,000 (which amount does not include fees, expenses, interest, or other amounts chargeable or otherwise reimbursable under the Loan Documents) . . . .”).

33

Credit Agreement §§ 1.1, 2.10(a).

34

Id. §§ 1.1, 2.10(c).

35

Id. § 8(b).

36

Id. § 8.

7

B. World Energy Defaults; The Parties Execute a Forbearance

Agreement.

World Energy defaulted immediately and repeatedly. The parties

memorialized that reality in a Forbearance Agreement dated July 10, 2024.37 World

Energy “acknowledge[d] and agree[d]” that it had breached its payment obligations

under both the Master Project Agreement and the Credit Agreement since November

2023, and that it would likely remain in default through September 2024.38 As of

July 2024, World Energy’s missed payments totaled nearly $19 million.39 World

Energy also acknowledged that Air Products had “fully and timely performed all of

[its] obligations and duties under the Agreements . . . and ha[d] acted reasonably and

in good faith under the circumstances.”40

“In reliance upon” those acknowledgements, Air Products agreed to “forbear

from exercising any rights or remedies that it may have against [World Energy] or

[its] respective assets and properties, in each case solely as a result of the occurrence

of the Specified Defaults,” until September 30, 2024.41

37

See Forbearance Agreement.

38

Id. §§ 1.01(b)–(c).

39

Id. §§ 1.02(b), (d).

40

Id. § 1.03.

41

Id. §§ 2.01, 2.03(g).

8

C. Activist Investors Target Air Products, And The Parties Execute The

Second Amendment To The Credit Agreement.

In mid-2024, Air Products became the target of activist investor campaigns.42

One campaign assailed the World Energy project as “Exhibit A” of Air Products’

mismanagement.43 Air Products focused on monetizing that project.44 It pushed for

an amendment to the Credit Agreement that would change certain provisions

governing the disposition and distribution of assets.45 According to the Complaint,

Air Products threatened to “stop working with World Energy to obtain working

capital financing,”46 and promised to provide another forbearance agreement if

World Energy executed the Second Amendment.47

The parties executed the Second Amendment to the Credit Agreement on

September 30, 2024.48 It recites that “the Borrower [i.e., AltAir] has requested that

[Air Products] amend certain provisions of the Credit Agreement.”49 The parties did

not enter into another forbearance agreement.50

42

Compl. ¶ 144; see also id. Ex. 9.

43

Compl. ¶ 165.

44

Id. ¶ 146.

45

Id. ¶¶ 147–50; Carbonara Aff. Ex. C.

46

Compl. ¶¶ 151–53.

47

Id. ¶ 156.

48

Id. ¶ 154; Carbonara Aff. Ex. C.

49

Carbonara Aff. Ex. C at 1.

50

Compl. ¶ 156.

9

D. World Energy Continues To Default; Air Products Exercises Its

Remedies.

World Energy remained in default after the forbearance period. Between

October 2024 and February 2025, Air Products sent World Energy nine default

notices pursuant to the Master Project Agreement, and six default notices pursuant

to the Credit Agreement.51 The Master Project Agreement notices explained that

World Energy had not provided any grounds to dispute the invoiced amounts, that

Air Products was entitled to suspend performance after forty-five days, and that Air

Products was entitled to terminate the Master Project Agreement after ninety.52 The

Credit Agreement notices explained that Air Products “expressly reserve[d] the

right” to exercise any and all remedies available under the Credit Agreement “at any

time.”53

In late January 2025, a new slate of directors was elected to Air Products’

board.54 The new leadership commanded a shift away from energy transition

projects.55 In early February, Air Products told World Energy it was not going

forward with the Plant A optimization work.56 On February 24, Air Products

51

See Carbonara Aff. Exs. G–U.

52

Carbonara Aff. Exs. G–O.

53

Carbonara Aff. Exs. P–U.

54

Compl. ¶ 163.

55

Id. ¶¶ 163–69.

56

Id. ¶¶ 170–72.

10

publicly announced the termination of three energy transition projects, including the

World Energy project.57 The same day, Air Products sent World Energy written

notice that it was terminating the Master Project Agreement, effective

immediately.58 The termination notice explained that World Energy’s MFF defaults

constituted “a Material Breach under Section 18.1(A)(i),” and entitled Air Products

to terminate the Master Project Agreement under Section 18.1(B)(i).59

Later that week, the parties elected to move forward with a planned “February

2025 turnaround” so that Air Products could “hand back the keys” to World

Energy.60 World Energy claims Air Products promised as part of that turnaround

work to repair the “12-D Rack,” a “support rack that holds up utility lines” necessary

for Plant A’s operations.61 Air Products and its subcontractor “completed the

necessary pre-work for the 12-D Rack repair,” including the removal of external

bracing and scaffolding.62 But Air Products did not complete the repair.63 The 12-57

Id. ¶ 167.

58

Id. ¶ 173; see Carbonara Aff. Ex. V.

59

Carbonara Aff. Ex. V at 1.

60

Compl. ¶ 176–77.

61

Id. ¶¶ 178, 179.

62

Id. ¶ 186.

63

Id. ¶ 187.

11

D Rack sits unusable, rendering the Paramount Facility’s only “continuously-active”

environmental remediation system inoperable.64

On March 26, over a month after Air Products’ termination notice, World

Energy sent two letters challenging the termination.65 The first claimed the “sole

purported ground” for termination—the MFF payments—was invalid because the

payments were “the subject of a good faith dispute by World Energy and therefore

[we]re not due.”66 It also claimed Air Products, not World Energy, “Materially

Breached the [Master Project Agreement] and, through its own wrongful conduct,

prevented World Energy from being able to pay the [MFF].”67 The letter demanded

that “Air Products immediately withdraw its repudiation and improper termination

of the [Master Project Agreement] and confirm in writing that it will comply with

all of its contractual obligations.”68

World Energy also sent Air Products a formal notice of breach of the Master

Project Agreement.69 The notice advised of: (1) a material breach of Section 2.1(D)

by failing to complete and fund, and then by repudiating, the Paramount Facility

64

Id. ¶¶ 190–91.

65

Compl. ¶ 193, Ex. 12; Carbonara Aff. Ex. X.

66

Carbonara Aff. Ex. X at 2.

67

Id.

68

Id. at 3–4.

69

See Compl. Ex. 12.

12

expansion project; (2) an ordinary breach of Sections 2.2, 2.3, 4.1, and 16.1 by failing

to comply with “specific obligations related to the [w]ork”; and (3) an ordinary

breach of Section 32.15 by failing to assist World Energy in securing working

capital, as reasonably requested.70 The notice repeated World Energy’s demand that

Air Products immediately withdraw termination and perform.71

Air Products responded on March 31.72 It raised World Energy’s failure to

meet its financial commitments, properly dispute the MFF invoiced amounts, or

provide notice of any breach prior to termination.73 It maintained the termination

was valid because “[f]or some time, Air Products has been the only party performing

under the [Master Project] Agreement.”74 That same day, Air Products also sent

written notice that it was accelerating all amounts due under the Credit Agreement.75

Air Products demanded immediate payment of $313,568,095.01.76 World Energy

refused to pay.77

70

Id.

71

Id. at 4.

72

See Carbonara Aff. Ex. Y.

73

Id.

74

Id. at 4.

75

See Carbonara Aff. Ex. Z.

76

Id. at 2.

77

Compl. ¶ 175.

13

E. Air Products Files Suit In New York.

On April 29, Air Products filed a motion for summary judgment in lieu of

complaint against World Energy in New York state court.78 The motion sought a

$312 million judgment under a guaranty agreement (the “Guaranty”), in which WE

LLC irrevocably and unconditionally guaranteed all payments owed by AltAir under

the Credit Agreement.79 Both the Credit Agreement and the Guaranty contain New

York forum selection and choice of law provisions.80

On September 19, 2025, the New York court granted the motion in its

entirety.81 Relevant here, the court rejected World Energy’s argument that “the

applicable interest rate was 4.5%, not 15%” under the Credit Agreement.82

Specifically, it concluded “the Credit Agreement unambiguously sets the

‘Applicable Rate’ at 15% and permits modifications only through a signed

writing.”83

78

Id. ¶ 203.

79

Id. ¶ 204; see Carbonara Aff. Ex. A [hereinafter “Guaranty”] § 1.

80

Credit Agreement § 10.9; Guaranty § 13.9.

81

See Air Prods. & Chems., Inc. v. World Energy, LLC, 2025 WL 2682969, at *4 (N.Y. Sup. Ct. Sept. 19, 2025).

82

Id. at *3.

83

Id.

14

World Energy appealed. On April 9, 2026, the Appellate Division affirmed

the judgment below.84 On May 11, World Energy moved for leave to further appeal

the judgment to the Court of Appeals of the State of New York.85

F. This Litigation

On August 8, 2025, World Energy filed a Verified Complaint (the

“Complaint”), along with a motion for preliminary injunction.86 Counts I and II are

breach of contract claims seeking specific performance of the Master Project

Agreement. Both counts also seek preliminary and permanent injunctive relief

requiring Air Products to “restore and maintain the status quo operations of the

Paramount facility,” with a focus on restoring the 12-D Rack to operation.87

Count III alleges a breach of the implied covenant of good faith and fair

dealing. Count IV alleges mutual mistake and seeks reformation of the Credit

Agreement, particularly its 15% interest rate before the Plant B Commencement

Date. Count V alleges Air Products fraudulently induced World Energy into

executing the Second Amendment. Count VI seeks a declaration that World Energy

has not breached any of its agreements with Air Products, that Air Products’ default

84

D.I. 40; D.I. 41; see Air Prods. & Chems., Inc. v. World Energy, LLC, 256 N.Y.S.3d 17 (N.Y. App. Div. 2026).

85

D.I. 41.

86

D.I. 1.

87

Compl. ¶¶ 226, 235.

15

and termination notices are invalid, and that Air Products is not entitled to relief for

World Energy’s breaches. Count VII asserts a claim for promissory and equitable

estoppel.

Air Products moved to dismiss the Complaint on September 2, 2025. 88 The

parties briefed the motion for preliminary injunction and motion to dismiss by

November 18.89 I heard oral argument on January 16, 2026.90 I denied the motion

for preliminary injunction from the bench, with a promise to provide a subsequent

explanation, and took the motion to dismiss under advisement the same day.91

II. ANALYSIS

World Energy seeks relief for breach of contract, including a mandatory

injunction requiring Air Products to fix the 12-D Rack and perform other work at

the Paramount Facility.92 To obtain that extraordinary and final relief, World Energy

must state a claim for breach of contract, then prevail on its merits as a matter of law

on undisputed facts.93 World Energy has done neither. Air Products properly

88

D.I. 16.

89

D.I. 17; D.I. 19; D.I. 24; D.I. 27; D.I. 29.

90

D.I. 37; see Hr’g Tr.

91

D.I. 36; D.I. 37.

92

See Compl. at Prayer for Relief.

93

See Alpha Nat. Res., Inc. v. Cliff’s Nat. Res., Inc., 2008 WL 4951060, at *2 (Del. Ch. Nov. 6, 2008) (“[Granting a mandatory injunction] requires, in addition, a showing that the petitioner is entitled as a matter of law to the relief it seeks based on undisputed facts.”); C & J Energy Servs., Inc. v. City of Miami Gen. Empls., 107 A.3d 1049, 1053–54 (Del. Ch.

16

terminated the Master Project Agreement after World Energy repeatedly breached

it. World Energy’s breaches were unjustified and unexcused. World Energy has not

pled a claim for breach of contract that can support mandatory injunctive relief.

A. Merits

The pleading standards under Delaware law are “minimal.”94 On a motion to

dismiss under Rule 12(b)(6), the Court must “accept all well-pleaded factual

allegations in the complaint as true, accept even vague allegations in the complaint

as well-pleaded if they provide the defendant notice of the claim, [and] draw all

reasonable inferences in favor of the plaintiff.”95 The Court will grant a Rule

12(b)(6) motion if the “plaintiff could not recover under any reasonably conceivable

set of circumstances susceptible of proof.”96 The Court need not “accept as true

conclusory allegations without specific supporting factual allegations.”97 The Court

2014) (“To issue a mandatory injunction requiring a party to take affirmative action . . . the Court of Chancery must either hold a trial and make findings of fact, or base an injunction solely on undisputed facts.”).

94

Cent. Mortg. Co. v. Morgan Stanley Mortg. Cap. Hldgs. LLC, 27 A.3d 531, 536 (Del. 2011).

95

Id.

96

Id.

97

In re Gen. Motors (Hughes) S’holder Litig., 897 A.2d 162, 168 (Del. 2006) (internal quotation marks and citations omitted).

17

is not “required to accept every strained interpretation of the allegations proposed

by the plaintiff.”98

1. Breach of Contract

The elements of a claim for breach of contract are familiar: “(i) a contractual

obligation, (ii) a breach of that obligation by the defendant, and (iii) a causally

related injury that warrants a remedy, such as damages or in an appropriate case,

specific performance.”99 No path to recovery is available unless the plaintiff

“demonstrate[s] that it substantially complied with all of the provisions of the

contract.”100

World Energy did not substantially comply with its obligations under the

Master Project Agreement. World Energy’s primary obligation was to pay the MOF

98

Malpiede v. Townson, 780 A.2d 1075, 1083 (Del. 2001).

99

AB Stable VIII LLC v. MAPS Hotels & Resorts One LLC, 2020 WL 7024929, at *47 (Del. Ch. Nov. 30, 2020), aff’d, 268 A.3d 198 (Del. 2021).

100

Preferred Inv. Servs., Inc. v. T & H Bail Bonds, Inc., 2013 WL 3934992, at *10 (Del. Ch. July 24, 2013) (citing Commonwealth Constr. Co. v. Cornerstone Fellowship Baptist Church, Inc., 2006 WL 2567916, at *19 (Del. Super. Aug. 31, 2006)), aff’d sub nom. Preferred Inv. Servs., Inc. v. T & H Bail Bond, Inc., 108 A.3d 1225 (Del. 2015); see AQSR India Private, Ltd. v. Bureau Veritas Hldgs., Inc., 2009 WL 1707910, at *7 (Del. Ch. June 16, 2009) (“It is a basic principle of contract law, however, that to be entitled to specific performance, which is an equitable remedy that rests in the discretion of the court, the party seeking specific performance must have substantially performed under the contract herself.” (citations omitted)); CLP Toxicology, Inc. v. Casla Bio Hldgs. LLC, 2021 WL 2588905, at *12 (Del. Ch. June 14, 2021) (“To recover for damages, the plaintiff must demonstrate that he substantially complied with all provisions of the contract.” (citing Shah v. Am. Sols., Inc., 2012 WL 1413593, at *2 (Del. Super. Mar. 8, 2012)).

18

and MFF.101 World Energy repeatedly failed to do so. By its own “free[] and

voluntar[y]” acknowledgement in the Forbearance Agreement, World Energy

breached the Master Project Agreement by “fail[ing] to pay in full the MFF

payments due April 10, 2024, May 1, 2024, May 31, 2024, and July 1, 2024.”102

And in that same agreement, World Energy warned of anticipated future breaches.103

That warning came true; the record shows World Energy continued to breach its

payment obligations every month between October 2024 and February 2025.104

World Energy does not plead, and the record does not suggest, that it cured those

breaches at any point.

World Energy responds by invoking the prevention doctrine, arguing its

nonperformance is excused because Air Products engaged in conduct that prevented

it from making timely payments: specifically, that Air Products did not do the work

necessary to make the Paramount Facility profitable.105 It is well settled that “the

failure of a plaintiff to have performed his own obligation will be excused if he was

101

Master Project Agreement §§ 8.1, 9.2, 9.3, 9.5.

102

Forbearance Agreement §§ 1.01(b)(ii), 3.01.

103

Id. § 1.01(c)(i).

104

Carbonara Aff. Exs. G–O.

105

See D.I. 27 at 11–12 (“[I]f Air Products had fulfilled its obligations to optimize and operate the facility’s production operations, it is undisputed that those operations would have generated millions of dollars of free cash flow . . . .”).

19

prevented by the other party from performing his obligation.”106 “[T]he doctrine is

based on the long-established principle of law that a party should not be able to take

advantage of its own wrongful act.”107 For the doctrine to apply, World Energy must

show that Air Products’ conduct “contributed materially” to World Energy’s

defaults.108 But if the defaults would have occurred “regardless of the lack of

cooperation, the failure of performance did not contribute materially . . . and the rule

does not apply.”109

For defaults before September 30, 2024, the Forbearance Agreement is fatal

to World Energy’s argument.110 There, World Energy acknowledged that Air

106

Wells v. Lee Builders, Inc., 99 A.2d 620, 621 (Del. 1953) (citations omitted); see also WaveDivision Hldgs., LLC v. Millennium Digital Media Sys., L.L.C., 2010 WL 3706624, at *14 (Del. Ch. Sept. 17, 2010) (“It is an established principle of contract law that ‘[w]here a party’s breach by nonperformance contributes materially to the non-occurrence of a condition of one of his duties, the non-occurrence is excused.’” (quoting Restatement (Second) of Contracts § 245 (1981))); Mobile Commc’ns Corp. of Am. v. MCI Commc’ns Corp., 1985 WL 11574, at *4 (Del. Ch. Aug. 27, 1985) (“[A] party may not escape contractual liability by reliance upon the failure of a condition precedent where the party wrongfully prevented performance of that condition precedent.”).

107

13 Richard A. Lord, Williston on Contracts § 39:6 (4th ed. 2024).

108

See Snow Phipps Gp., LLC v. KCAKE Acq., Inc., 2021 WL 1714202, at *52 (Del. Ch. Apr. 30, 2021).

109

In re Anthem-Cigna Merger Litig., 2020 WL 5106556, at *90 (Del. Ch. Aug. 31, 2020) (internal quotation marks omitted) (quoting Restatement (Second) of Contracts § 245 cmt. b (1981)).

110

The Forbearance Agreement is governed by New York law. See Forbearance Agreement § 6.03. World Energy asserts that under New York law, the Forbearance Agreement’s “admission of liability” does not bar its claims or defenses. D.I. 34; see Berkshire Bank v. Fawer, 130 N.Y.S.3d 666, 666 (N.Y. App. Div. 2020). That does not mean the fact of the Forbearance Agreement and its contractual acknowledgements are

20

Products “fully and timely performed all of [its] obligations and duties under the

Agreements . . . and ha[d] acted reasonably and in good faith under the

circumstances.”111 That unambiguous language forecloses the conclusion that Air

Products interfered wrongfully or in bad faith with World Energy’s ability to pay.

Wells v. Lee Builders, Inc. is instructive.112 There, a buyer sought specific

performance of a land sale contract, even though he was required to move a house

off the parcel before closing and had not done so.113 The buyer argued his

nonperformance should be excused because the sellers had prevented the buyer from

moving the house.114 The Delaware Supreme Court concluded any prevention of the

buyer’s performance by the seller “was made immaterial by” an intervening

agreement.115 The agreement contained a “recital of fact” that “certain unforeseen

difficulties have caused unavoidable delays in the fulfillment by both the sellers and

the buyer of their respective obligations.”116 Its effect “was to wipe out . . . any

action on [the sellers’] part which tended to prevent performance by the plaintiff of

irrelevant to this Court’s analysis of a claim for breach of a contract governed by Delaware law.

111

Forbearance Agreement § 1.03.

112

99 A.2d 620, 621–25 (Del. 1953).

113

Id. at 621.

114

Id.

115

Id. at 622.

116

Id.

21

its obligation.”117 Here, as in Wells, the Forbearance Agreement “wipe[s] out” any

alleged breach or bad faith conduct by Air Products that would excuse World

Energy’s nonperformance.118 And World Energy is “precluded” by its own factual

recitals “from contending to the contrary.”119

That leaves Air Products’ conduct after September 30, 2024, until Air

Products terminated the Master Project Agreement.120 World Energy’s primary

argument is that Air Products “starve[d] World Energy of revenue that [it] needed”

to make its monthly payments, and then, having breached the contract itself,

improperly repudiated its obligations.121

First, it contends Air Products breached by failing to complete the “2024 Plant

A Expansion Shutdown”—which is how the Master Project Agreement labels the

overall Plant A expansion work—by the end of 2024.122 But nothing in the contract

mandates that deadline. World Energy relies entirely on the “2024” in the defined

term to infer a December 31, 2024 deadline. But the Master Project Agreement

explicitly states “that Air Products is not providing any schedule guarantee for the

117

Id.

118

Id.

119

Id.

120

See D.I. 34 at 3 (arguing “World Energy’s requested relief is entirely supported by Air Products’ post-[forbearance] conduct”).

121

D.I. 27 at 11.

122

Id. at 8–9.

22

completion of the Work or any component thereof in th[e] Agreement or

otherwise.”123 That specific language controls.124

More fundamentally, World Energy’s payment obligations were not tied to

the fruits of Air Products’ work.125 The obligations arose as soon as World Energy

began working on Plant A, without regard to any operational milestones.126 If the

123

Master Project Agreement § 2.2(B). The 2024 Plant A Expansion Shutdown is a component of Air Products’ “Work.” The Master Project Agreement defines “Work” to include the “Construction . . . of the Plant A Expansion Assets.” Id. § 1.1. The term “Construction” is defined to “includ[e] the completion of the 2024 Plant A Expansion Shutdown.” Id.; see also Compl. ¶ 101.

124

See DCV Hldgs., Inc. v. ConAgra, Inc., 889 A.2d 954, 961 (Del. 2005)

(“Specific language in a contract controls over general language, and where specific and general provisions conflict, the specific provision ordinarily qualifies the meaning of the general one.” (citations omitted)).

125

See, e.g., Desktop Metal, Inc. v. Nano Dimension Ltd., 2025 WL 904521, at *37 (Del. Ch. Mar. 24, 2025) (finding the prevention doctrine applicable where a party to a merger agreement “delay[ed] CFIUS approval in breach of the Merger Agreement”); Murphy Marine Servs. of Del., Inc. v. GT USA Wilm., LLC, 2022 WL 4296495, at *12 (Del. Ch. Sept. 19, 2022) (“If GT’s performance was conditioned upon KPMG issuing a formal valuation, GT was obliged not to interfere with the exercise of KPMG’s discretion in reaching that valuation[.]”).

126

See Master Project Agreement §§ 9.2 (“The MFF shall be determined as follows, irrespective of the amount of Products produced by the Expansion Assets . . . .”); see id. §§ 9.3(A), 9.5 (providing that the MOF and MFF payments shall commence “on the Plant A Commencement Date”).

The Master Project Agreement excused MFF payments in two scenarios: (1) upon the occurrence of a “MFF Deferral Event” which, by definition, must “occur[] after the completion of the 2024 Plant A Expansion Shutdown”; and (2) upon a “Material Breach” by Air Products, followed by its failure to cure the breach within sixty days of receiving a default notice. Master Project Agreement §§ 1.1, 18.1(A)(iii). Neither scenario applied to World Energy. The first did not apply because the 2024 Plant A Expansion Shutdown had not yet been completed. The second did not apply because World Energy did not provide Air Products notice or an opportunity to cure any purported breaches, as required by Section 18.1(A)(iii).

23

parties intended for World Energy to owe payments only after Plant A’s expansion

work was complete or only after the work yielded a certain level of cash flow, they

could have said so in the contract.127 They did not. They agreed to monthly

payments untethered to performance or profit. And World Energy defaulted the very

first month any such payment was owed.128

From there, World Energy argues Air Products breached its obligation to

assist with working capital financing.129 That contention is not supported by the

Complaint or the record. World Energy does not plead or identify a single instance

after the forbearance period where it “requested,” but failed to receive, Air Products’

assistance in securing capital.130

127

World Energy alleges the parties had discussed and understood “that World Energy’s payment obligations would only kick in after Air Products completed the Plant A optimization work, thereby creating the value and additional cash flow necessary for World Energy to make interest payments.” Compl. ¶ 130; see also id. ¶¶ 9, 95. That is not what the contract says. See Master Project Agreement §§ 9.2, 9.3, 9.5. “It is well-established that ‘[if] a contract is unambiguous, extrinsic evidence may not be used to interpret the intent of the parties, to vary the terms of the contract or to create an ambiguity.’” ITG Brands, LLC v. Reynolds Am., Inc., 2019 WL 4593495, at *12 (Del. Ch. Sept. 23, 2019) (quoting Eagle Indus., Inc. v. DeVilbiss Health Care, Inc., 702 A.2d 1228, 1232 (Del. 1997)).

128

Forbearance Agreement §§ 1.01(b)(i)–(ii).

129

D.I. 27 at 11.

130

Master Project Agreement § 32.15 (Air Products shall use commercially reasonable efforts to cooperate with World Energy, as reasonably requested by World Energy, in order to assist World Energy to secure working capital finance, subject to the limitations and restrictions set forth in the New Credit Facility and this Agreement.”).

24

World Energy’s next argument to avoid the consequences of its breaches

relates to the contractual mechanics of termination. Section 8.2(B) of the Master

Project Agreement provides that “except with respect to payments that are the

subject of good faith disputes[,]” Air Products was entitled to suspend performance

if a default remained unremedied for fifteen days after the payment due date, subject

to forty-five days’ written notice.131 Air Products sent five written “Notice[s] of

Potential Air Products Suspension” for every missed MFF payment between October

2024 and February 2025.132 Each of those missed payments, and failure to cure

within ninety days, put World Energy in “Material Breach.”133 Under Section

18.1(B)(i), Air Products was then entitled to “immediately terminate” the Master

Project Agreement upon providing a termination notice.134 It did so on February 24,

2025.135

World Energy presses that none of the missed MFF payments triggered a

termination right because they were never “due” in the first place: World Energy

contends they were “the subject of a good faith dispute.”136 Not so. The contract

131

Id. § 8.2(B).

132

See Carbonara Aff. Exs. G, H, J, L, N.

133

Master Project Agreement § 18.1(A)(i).

134

Id. § 18.1(B)(i).

135

Carbonara Aff. Ex. V.

136

See Carbonara Aff. Ex. X at 3.

25

permits World Energy to challenge only “proposed adjustments and calculations,”

and not “the obligation to pay the MFF” itself.137 To raise that challenge, it must

offer “supporting documentation with respect to the amount disputed.”138 And it

must pay any “non-disputed” amounts on time, pending resolution of the purported

dispute.139 World Energy did not follow those procedures before termination. World

Energy did not make any cognizable challenge as to “proposed adjustments and

calculations,” backed up by supporting documentation, and certainly did not identify

and pay any undisputed amount.140 A bare assertion at this point that the payments

“[we]re not ‘due’” because of “a good faith dispute” does no work for World

Energy.141 Air Products was entitled to suspend performance and terminate the

Master Project Agreement.142

Air Products’ performance under the Master Project Agreement was

unambiguously conditioned on receiving monthly payments from World Energy.143

137

Master Project Agreement § 8.2(A).

138

Id.

Id. (“World Energy will pay the non-disputed invoice by the original due date . . . and 139

may withhold payment of the disputed invoice amount pending resolution.”). 140

Id.

141

Carbonara Aff. Ex. X at 3. World Energy is correct that under Section 8.2(A), it was entitled to dispute an invoice “within the period of one year of the date of the invoice.” Master Project Agreement § 8.2(A).

142

See Master Project Agreement §§ 8.2(B), 18.1(B)(i).

143

Id. § 8.2(B).

26

World Energy failed to make those payments. And it failed to plead any

circumstances excusing its defaults. Counts I and II are dismissed.

It follows that Count VI, which seeks a declaration that World Energy has not

breached any of the relevant agreements and is entitled to have Air Products’

termination withdrawn, fails as well. Count VI is dismissed.

2. Breach Of The Implied Covenant

Count III asserts a claim for breach of the implied covenant of good faith and

fair dealing. The implied covenant “inheres in every contract and requires a party

in a contractual relationship to refrain from arbitrary or unreasonable conduct which

has the effect of preventing the other party . . . from receiving the fruits of the

bargain.144 “To state a claim for breach of the implied covenant, [a plaintiff] ‘must

allege a specific implied contractual obligation, a breach of that obligation by the

defendant, and resulting damage to the plaintiff.’”145 “General allegations of bad

faith conduct are not sufficient.”146

144

Kuroda v. SPJS Hldgs., L.L.C., 971 A.2d 872, 888 (Del. Ch. 2009) (internal quotation marks omitted) (quoting Dunlap v. State Farm Fire & Cas. Co., 878 A.2d 434, 442 (Del. 2005)); see also Nemec v. Shrader, 991 A.2d 1120, 1126 (Del. 2010) (“We will only imply contract terms when the party asserting the implied covenant proves that the other party has acted arbitrarily or unreasonably, thereby frustrating the fruits of the bargain that the asserting party reasonably expected.” (citation omitted)).

145

Wiggs v. Summit Midstream P’rs, LLC, 2013 WL 1286180, at *9 (Del. Ch. Mar. 28, 2013) (quoting Cantor Fitzgerald, L.P. v. Cantor, 1998 WL 842316, at *1 (Del. Ch. Nov. 10, 1998)).

146

Kuroda, 971 A.2d at 888.

27

The implied covenant’s “gap-filling power is a limited and extraordinary

remedy,” and wielding it is a “cautious enterprise.”147 It “cannot be invoked to

override express provisions of a contract”148 or “contradict[] a clear exercise of an

express contractual right.”149 It cannot be used to “create a free-floating duty

unattached to the underlying legal documents.”150 As such, a party invoking the

implied covenant must plead a “gap” in the relevant agreement.151 That gap must

reflect “developments that could not be anticipated, not developments that the parties

simply failed to consider” at the time of contracting.152 There is no gap to fill “when

the contract addresses the conduct at issue.”153

147

Johnson & Johnson v. Fortis Advisors LLC, 352 A.3d 229, 254 (Del. 2026) (internal quotation marks omitted) (citing Nemec, 991 A.2d at 1125, 1128, and then Oxbow Carbon & Mins. Hldgs., Inc. v. Crestview-Oxbow Acq., LLC, 202 A.3d 482, 507 (Del. 2019)). 148

Kuroda, 971 A.2d at 888.

149

Nemec, 991 A.2d at 1127.

150

Dunlap, 878 A.2d 434, 441 (Del. 2005) (alterations, footnote, and internal quotation marks omitted) (compiling sources and quoting Glenfed Fin. Corp., Com. Fin. Div. v. Penick Corp., 647 A.2d 852, 858 (N.J. Super. Ct. App. Div. 1994)).

151

See Johnson & Johnson, 352 A.3d at 256 (“The covenant applies only where there is a genuine contractual gap about a truly unanticipated development . . . .” (citations omitted)); Allen v. El Paso Pipeline GP Co., L.L.C., 113 A.3d 167, 183 (Del. Ch. 2014) (“When presented with an implied covenant claim, a court first must engage in the process of contract construction to determine whether there is a gap that needs to be filled.” (citation omitted)).

152

Nemec, 991 A.2d at 1126 (citing Dunlap, 878 A.2d at 441).

153

Nationwide Emerging Managers, LLC v. Northpointe Hldgs., LLC, 112 A.3d 878, 896 (Del. 2015) (citing Dunlap, 878 A.2d at 441).

28

World Energy claims Air Products frustrated the parties’ bargain by exiting

the Paramount Facility expansion project “for commercial reasons unrelated to

World Energy’s performance” and manufacturing “pretextual grounds to

terminate.”154 But the Master Project Agreement tells the parties exactly when and

how they could terminate: upon a material breach by the other party, with no

limitations.155 World Energy’s uncured defaults triggered Air Products’ right to

walk away from the relationship, no matter its true motive. “The time to demand

restrictions on an express contractual right was during negotiations—not years later

through the implied covenant,” after that right was validly triggered.156 Draping the

contractual consequences of World Energy’s nonpayment in “general allegations of

bad faith” does not invoke the implied covenant.157 World Energy fails to state a

claim for its breach. Count III is dismissed.

3. Estoppel

In Count VII, World Energy asserts a single claim for both promissory and

equitable estoppel.158 It alleges that after terminating the Master Project Agreement,

154

D.I. 27 at 37; see also Compl. ¶¶ 17, 24, 237–40.

155

Master Project Agreement § 18.1.

156

Glaxo Gp. Ltd. v. DRIT LP, 248 A.3d 911, 920 (Del. 2021) (citing Nemec, 991 A.2d at 1126).

157

Kuroda, 971 A.2d at 888.

158

Compl. ¶¶ 262–69.

29

Air Products promised—and began preparing—to complete “necessary repairs to

the 12-D Rack,” including by “preparing the site and removing bracing and

scaffolding.”159

“[P]romissory estoppel is fundamentally a narrow doctrine, designed to

protect the legitimate expectations of parties rendered vulnerable by the very

processing of attempting to form commercial relationships.”160 To plead a

promissory estoppel claim, the plaintiff must allege that:

(1) a promise was made; (2) it was the reasonable expectation of the

promisor to induce action or forbearance on the part of the promisee;

(3) the promisee reasonably relied on the promise and took action to his

detriment; and (4) such promise is binding because injustice can be

avoided only be enforcement of the promise.161

At oral argument, World Energy explained that the 12-D Rack repairs are

“part and parcel” of Air Products’ “obligations to fund and complete the work and

to maintain the plant under the [Master Project Agreement].”162 But as our Supreme

Court noted in SIGA Technologies, Inc. v. PharmAthene, Inc., promissory estoppel

is inapplicable “where a fully integrated, enforceable contract governs the promise

159

Id. ¶¶ 263, 264.

160

Ramone v. Lang, 2006 WL 905347, at *14 (Del. Ch. Apr. 3, 2006).

161

Grunstein v. Silva, 2009 WL 4698541, at *7 (Del. Ch. Dec. 8, 2009) (citing Pharmathene, Inc. v. SIGA Techs., Inc., 2008 WL 151855, at *17 (Del. Ch. Jan. 16, 2008), and then citing Lord v. Souder, 748 A.2d 393, 399 (Del. 2000))).

162

Hr’g Tr. 11–12.

30

at issue.”163 World Energy cannot rely on promissory estoppel to revive a promise

that was covered by, and thus died with, the Master Project Agreement.164

The question is therefore whether World Energy has pled Air Products made

a cognizable promise about the 12-D Rack after it terminated the Master Project

Agreement. Promissory estoppel requires “a real promise, not just mere expressions

of expectation, opinion, or assumption.”165 The promise must be “reasonably

definite and certain.”166 World Energy has fallen short of pleading a definite

promise.

World Energy alleges that after Air Products terminated the Master Project

Agreement, “[b]oth parties planned and agreed that Air Products would permanently

repair the 12-D Rack during [a] February 2025 turnaround.”167 It further alleges Air

completed “pre-work” for the repairs, and that “[t]hroughout [] daily

communications, Air Products consistently communicated that they were moving

forward with the 12-D Rack and other repairs.”168 Those allegations do not amount

163

67 A.3d 330, 348 (Del. 2013) (citing Chrysler Corp. (Del.) v. Chaplake Hldgs., Ltd., 822 A.2d 1024, 1033–34 (Del. 2003)).

164

See Master Project Agreement §§ 2.1, 32.6.

165

James Cable, LLC v. Millennium Digit. Media Sys., L.L.C., 2009 WL 1638634, at *5 (Del. Ch. June 11, 2009) (internal quotation marks omitted) (quoting Addy v. Piedmonte, 2009 WL 707641, at *22 (Del. Ch. Mar. 18, 2009)).

166

Id. (citing Cont’l Ins. Co. v. Rutledge & Co. Inc., 750 A.2d 1219, 1233 (Del. Ch. 2000)). 167

Compl. ¶ 181.

168

Id. ¶¶ 185, 186.

31

to a real promise. “[D]aily conversations” between onsite teams about “moving

forward” with certain repairs cannot be reasonably interpreted as a definite

promise.169 World Energy does not plead “when the promise was made, to whom it

was made, or any other specifics.”170 It does not indicate Air Products would

complete the 12-D Rack repairs on “any particular terms.”171 World Energy’s failure

to plead a real promise is fatal to its promissory estoppel claim.172

World Energy’s equitable estoppel theory fares no better. To state a claim

for equitable estoppel, a plaintiff must allege:

(1) conduct by the party to be estopped that amounts to a false

representation, concealment of material facts, or that is calculated to

convey an impression different from, and inconsistent with that which

the party subsequently attempts to assert, (2) knowledge, actual or

constructive, of the real facts and the other party's lack of knowledge

and the means of discovering the truth, (3) the intention or expectation

that the conduct shall be acted upon by, or influence, the other party

and good faith reliance by the other, and (4) action or forbearance by

the other party amounting to a change of status to his detriment.173

169

Id. ¶ 185.

170

James Cable, 2009 WL 1638634, at *5.

171

Hyetts Corner, LLC v. New Castle Cnty., 2021 WL 4166703, at *9 (Del. Ch. Sept. 14, 2021).

172

See Metro. Convoy Corp. v. Chrysler Corp., 208 A.2d 519, 521 (Del. 1965). 173

Olson v. Halvorsen, 2009 WL 1317148, at *11 (Del. Ch. May 13, 2009) (internal quotation marks omitted) (quoting Cornerstone Brands, Inc. v. O’Steen, 2006 WL 2788414, at *3 n.12 (Del. Ch. Sept. 20, 2006)), aff’d, 986 A.2d 1150 (Del. 2009).

32

A party’s “reliance must be both reasonable and justified under the circumstances.

Thus, the standards for establishing the elements of equitable estoppel are stringent;

the doctrine is applied cautiously and only to prevent manifest injustice.”174

World Energy has not pled circumstances that support justifiable reliance on

any purported representations about the 12-D Rack repairs. When the 2025 February

turnaround allegedly began, World Energy was well aware of Air Products’s exit

from the Paramount Facility project. It knew Air Products suspended performance

in early February, sent a formal termination notice later that month, and publicly

announced the termination.175 The termination notice referenced the impending

“demobilization and winding-down” of Air Products’ work, and explained Air

Products was walking away because it was not getting paid.176 Even if World Energy

questioned the termination’s validity, it could not have reasonably relied on informal

onsite communications and “pre-work” on a job Air Products had just called off.177

Count VII is dismissed.

174

Pilot Point Owners Ass’n v. Bonk, 2008 WL 401127, at *2 (Del. Ch. Feb. 13, 2008) (footnote omitted) (citing Progressive Int’l Corp. v. E.I. Du Pont de Nemours & Co., 2002 WL 1558382, at *6 (Del. Ch. July 9, 2002)).

175

Compl. ¶¶ 170–74.

176

Carbonara Aff. Ex. V at 1.

177

Compl. ¶ 186.

33

4. Mutual Mistake And Reformation

Count IV asserts a mistake claim seeking reformation of the Credit

Agreement.178 Specifically, it seeks a reformation that would swap the Credit

Agreement’s unambiguous 15% interest rate179 with a 4.5% rate used in the Master

178

See Compl. ¶¶ 241–49.

The parties dispute whether I need to address this claim at all. In the fall of 2025, a New York court found World Energy liable for breach of the Guaranty and awarded Air Products damages in the amount of $343,014,718.45, representing what World Energy owed under the Credit Agreement. Air Prods. & Chems., Inc., 2025 WL 2682969, at *1. The judgment was unanimously affirmed on appeal. Air Prods. & Chems., Inc., 256 N.Y.S.3d at 17. Air Products argues these decisions are dispositive of World Energy’s reformation claim. See D.I. 40.

But as World Energy observes, the New York action “involved only a single claim relating to a single contract: [Air Products’] claim against [WE LLC] to enforce payment obligations under the parties’ Guaranty.” D.I. 41 at 2. While the trial court concluded the applicable interest rate on those payment obligations was 15%, it did not address the narrow issue of whether World Energy is entitled to the equitable remedy of reformation on mutual mistake grounds. So I have considered that claim.

The Credit Agreement contains a New York choice of law provision. See Credit Agreement § 10.9. “Delaware courts will generally honor a contractually-designated choice of law provision so long as the jurisdiction selected bears some material relationship to the transaction.” J.S. Alberici Constr. Co., Inc. v. Mid-W. Conveyor Co., Inc., 750 A.2d 518, 520 (Del. 2000) (citing Annan v. Wilm. Tr. Co., 559 A.2d 1289, 1293 (Del. 1989)). But in litigating this claim, the parties have relied solely on Delaware law. See D.I. 24 at 50–53; D.I. 27 at 38–41; D.I. 29 at 28–32.

It does not appear the choice of law would change the analysis or outcome. In both Delaware and New York, to state a reformation claim based on mutual mistake, the proponent must plead with particularity “exactly what was really agreed upon between the parties.” 11 King Ctr. Corp. v. City of Middletown, 982 N.Y.S.2d 504, 505–06 (N.Y. App. Div. 2014) (internal quotations omitted) (quoting George Backer Mgmt. Corp. v. Acme Quilting Co., Inc., 413 N.Y.S.2d 135, 139 (N.Y. Ct. App. 1978)); see also Hilgreen v. Pollard Excavating, Inc., 146 N.Y.S.3d 323, 325–26 (N.Y. App. Div. 2021); Cerberus Int’l, Ltd. v. Apollo Mgmt., L.P., 794 A.2d 1141, 1152–53 (Del. 2002). I take the parties’ lead and evaluate World Energy’s claim under Delaware law.

179

See Credit Agreement § 1.1 (defining “Applicable Rate” as “15.0% per annum”).

34

Project Agreement in connection with the MFF.180 It alleges the failure to reflect a

4.5% interest rate in the Credit Agreement was an “obvious error.”181

Reformation is a narrow equitable remedy. It is “not an equitable license for

the Court to write a new contract at the invitation of a party who is unsatisfied with

his or her side of the bargain; rather, it permits the Court to reform a written contract

that was intended to memorialize, but fails to comport with, the parties’ prior

agreement.”182 “The Court may reform a contract ‘only when the contract does not

represent the parties’ intent because of fraud, mutual mistake or, in exceptional

circumstances, a unilateral mistake coupled with the other parties’ knowing

silence.’”183

World Energy advances a mutual mistake theory. That theory imposes a

heavy burden. A plaintiff alleging mutual mistake “must show that both parties were

mistaken as to a material portion of the written agreement.”184 To survive a motion

to dismiss, the plaintiff must allege: (1) the parties reached a definite agreement

180

Compl. ¶¶ 245–46, 249.

181

Id. ¶ 248.

182

In re TIBCO Software Inc. S’holders Litig., 2015 WL 6155894, at *13 (Del. Ch. Oct. 20, 2015); see also Collins v. Burke, 418 A.2d 999, 1002–03 (Del. 1980); In re Est. of Justison, 2005 WL 217035, at *10 (Del. Ch. Jan. 21, 2005).

183

Great-W. Inv’rs LP v. Thomas H. Lee P’rs, L.P., 2011 WL 284992, at *11 (Del. Ch. Jan. 14, 2011) (quoting James River-Pennington Inc. v. CRSS Cap., Inc., 1995 WL 106554, at *7 (Del. Ch. Mar. 6, 1995)).

184

Cerberus Int’l, 794 A.2d at 1151–52 (citing Collins, 418 A.2d at 1002).

35

before executing the final contract; (2) the final contract failed to incorporate the

terms of the agreement; (3) the parties’ mutually mistaken belief reflected the

parties’ true agreement; and (4) the precise mistake the parties made.185 “The

requirements are cumulative, and each one must be pled with particularity.”186

The claim fails at the first step: pleading a definite prior agreement.

“Reformation requires the existence of a specific prior contractual understanding

that conflicts with the terms of the written agreement.”187 While that prior

understanding “need not constitute a complete contract in and of itself,”188 it must

be sufficiently definite to specify for the Court “exactly what terms to insert in the

contract.”189 World Energy alludes to an oral agreement between the parties about

charging a 4.5% interest rate on the Credit Agreement loan until Air Products

completed its Plant A optimization work.190 As pled, that agreement is far from

definite.

185

Great-W. Inv’rs LP, 2011 WL 284992, at *11 (citing Joyce v. RCN Corp., 2003 WL 21517864, at *4 (Del. Ch. July 1, 2003)).

186

AECOM v. SCCI Nat’l Hldgs., Inc., 2023 WL 6294985, at *6 (Del. Ch. Sept. 27, 2023) (citing Cerberus Int’l, 794 A.2d at 1153); see Ct. Ch. R. 9(b) (“In alleging fraud or mistake, a party must state with particularity the circumstances constituting fraud or mistake.”). 187

ASB Allegiance Real Est. Fund v. Scion Breckenridge Managing Member, LLC, 2012 WL 1869416, at *13 (Del. Ch. May 16, 2012).

188

Cerberus Int’l, 794 A.2d at 1152 (citations omitted).

189

Collins, 418 A.2d at 1002 (citations omitted).

190

Compl. ¶ 121.

36

First, World Energy relies on the loan’s structuring history. It argues the

Credit Agreement’s $270 million loan arose out of a $300 million loan bifurcated

into two components for tax reasons: a $30 million sale-leaseback under the Master

Project Agreement and a $270 million loan under the Credit Agreement.191 The $30

million sale-leaseback applied a 4.5% “rate of return.”192 World Energy thus

contends the parties “obvious[ly]” intended to apply that 4.5% rate across both

agreements.193 That argument is unpersuasive. The structuring history explains why

the parties divided World Energy’s financing obligations into two instruments. It

does not “demonstrate[e] that the parties came to a ‘real agreement’” on charging

the same interest rate under both instruments.194

From there, World Energy points to statements by Air Products executives

after the parties executed the Credit Agreement.195 When World Energy allegedly

broached the interest rate issue to Air Products, one executive explained the 15%

interest rate “may be a mistake.”196 Another explained that rate “did not sound

191

Id. ¶¶ 95–96.

192

Id. ¶ 103a; Master Project Agreement at Attachment B.

193

Compl. ¶ 248.

194

MetCap Securities LLC v. Pearl Senior Care, Inc., 2007 WL 1498989, at *9 (Del. Ch. May 16, 2007).

195

See Davis v. C.J. Harris, Inc., 1962 WL 69607, at *3 (Del. Ch. Oct. 10, 1962) (“Subsequent events or representations are of no consequence in determining whether or not a mutual mistake existed when the contract was executed.” (citation omitted)). 196

Compl. ¶ 123a.

37

right.”197 Still another suggested “World Energy should hold off on making interest

payments” at all until the Paramount Facility achieved sufficient production

levels.198 These statements are not only vague, but also inconsistent. They offer no

“definitive, clear and particular agreement” about a 4.5% interest rate for the Court

to reference in reforming the Credit Agreement.199

And World Energy itself agreed the 15% interest rate was not a mistake. In

the Forbearance Agreement, executed eight months after the Credit Agreement,

World Energy unconditionally acknowledged the Credit Agreement “is legal, valid,

binding, and enforceable . . . in accordance with its terms.”200 And it acknowledged

that under those terms, it owed no less than $18,460,000 in overdue interest

payments.201 Those acknowledgements undermine any theory of mistake here.

Count IV is dismissed.

5. Fraud

Count V asserts a claim for fraud, alleging Air Products promised “a

reasonable cure or forbearance agreement” if World Energy executed the Second

197

Id. ¶ 123b.

198

Id. ¶ 126; see also id. ¶ 127 (alleging that “[f]ollowing the February 2024 meeting, both parties understood and agreed that World Energy would not pay interest until the Plant A expansion work was completed and until a third-party working capital provider was installed”).

199

AECOM, 2023 WL 6294985, at *8.

200

Forbearance Agreement § 1.02(a).

201

Id. § 1.02(b)(ii).

38

Amendment to the Credit Agreement.202 To survive a motion to dismiss on a claim

for fraud, a plaintiff must plead:

(1) a false representation, usually one of fact; (2) the defendant’s

knowledge or belief that the representation was false, or was made with

reckless indifference to the truth; (3) an intent to induce the plaintiff to

act or to refrain from acting; (4) the plaintiff’s action or inaction taken

in justifiable reliance upon the representation; and (5) damage to the

plaintiff as a result of such reliance.203

Under Court of Chancery Rule 9(b), “[i]n alleging fraud or mistake, a party must

state with particularity the circumstances constituting fraud or mistake.”204 To

satisfy Rule 9(b), a plaintiff must allege: “(1) the time, place, and contents of the

false representation; (2) the identity of the person making the representation; and (3)

what the person intended to gain by making the representations.”205

World Energy’s fraud claim is not premised on false representations of fact.

Instead, it is premised on an allegedly false promise—i.e., to “enter into a separate

cure or forbearance agreement” if World Energy agreed to execute the Second

202

Compl. ¶ 253.

203

See Hauspie v. Stonington P’rs, Inc., 945 A.2d 584, 586 (Del. 2008).

204

Ct. Ch. R. 9(b).

205

Abry P’rs V, L.P. v. F & W Acq. LLC, 891 A.2d at 1050 (citing H-M Wexford LLC v. Encorp, Inc., 832 A.2d 129, 145 (Del. Ch. 2003)).

39

Amendment.206 World Energy’s fraud allegations “are thus best considered through

the lens of ‘promissory fraud.’”207

“This Court looks with particular disfavor at allegations of fraud when the

underlying utterances take the form of unfulfilled promises of future

performance.”208 That is because usually, “statements which are merely promissory

in nature and expressions as to what will happen in the future are not actionable as

fraud.”209 A claim of promissory fraud thus entails “a heightened burden to plead

‘particularized facts that allow the Court to infer that, at the time the promise was

made, the speaker had no intention of keeping it.’”210 That is, the plaintiff “must

plead specific facts that lead to a reasonable inference that the promissor had no

intention of performing at the time the promise was made.”211 “[A] party’s failure

to keep a promise does not prove the promise was false when made.”212

206

Compl. ¶ 251.

207

CPC Mikawaya Hldgs., LLC v. MyMo Intermediate, Inc., 2022 WL 2348080, at *17 (Del. Ch. June 29, 2022).

208

Winner Acceptance Corp. v. Return on Cap. Corp., 2008 WL 5352063, at *9 (Del. Ch. Dec. 23, 2008).

209

Outdoor Techs., Inc. v. Allfirst Fin., Inc., 2001 WL 541472, at *4 (Del. Super. Apr. 12, 2001) (citations omitted).

210

CPC Mikawaya Hldgs., 2022 WL 2348080, at *17 (quoting MicroStrategy Inc. v. Acacia Rsch. Corp., 2010 WL 5550455, at *15 (Del. Ch. Dec. 30, 2010)). 211

Winner Acceptance, 2008 WL 5352063, at *10.

212

Berdel, Inc. v. Berman Real Est. Mgmt., Inc., 1997 WL 793088, at *8 (Del. Ch. Dec. 15, 1997).

40

World Energy’s promissory fraud allegations lack “a proper pleading of

intent.”213 It does not plead particularized facts suggesting Air Products “intended

to renege at the time it made the promise.”214 It pleads only that Air Products

promised an updated forbearance agreement if World Energy executed the Second

Amendment, and that Air Products subsequently refused to honor that promise.215

While World Energy quibbles with the “suspicious timing” of the refusal,216 the

Complaint itself pleads Air Products did not exercise its remedies until months after

the Second Amendment.217 World Energy offers no basis to infer from that

chronology that Air Products intended to renege at the time of its promise.

With no other specific facts to rely on, World Energy falls back on its

argument that Air Products simply “had no intention of providing World Energy

relief, as evidenced by its immediate refusal to honor the promise once the Second

Amendment was signed.”218 Again, “a party’s failure to keep a promise” is not

“evidence” of an intent to break that promise at the outset.219 World Energy has

failed to state a claim for promissory fraud. Count V is dismissed.

213

Dunn v. FastMed Urgent Care, P.C., 2019 WL 4131010, at *9 (Del. Ch. Aug. 30, 2019). 214

Berdel, 1997 WL 793088, at *8 (citations omitted).

215

See Compl. ¶¶ 156, 251–54.

216

D.I. 27 at 46 (citing Grunstein, 2009 WL 4698541, at *13).

217

See Compl. ¶ 173.

218

Id. ¶ 254.

219

See Berdel, 1997 WL 793088, at *8.

41

B. Irreparable Harm and Balance of the Equities

At oral argument, I told the parties there were several reasons I would not

order the mandatory injunction World Energy requested. This case must be

dismissed for failure to state a claim; further ruminations on why final relief is not

granted stray into dicta. But for the sake of explaining my reasoning for denying the

preliminary injunction when I did, I will note that World Energy also failed to

demonstrate the sine qua non of injunctive relief: irreparable harm.

“A mandatory injunction will only issue if the plaintiff demonstrates it is

necessary to prevent irreparable harm.”220 While not dispositive, the availability of

a remedy at law in the form of compensatory damages tips against a finding of

irreparable harm.221

World Energy sees irreparable harm from the 12-D Rack’s current condition

in the potential loss of customer relationships, the potential loss of its “first-mover

and industry-leader status” in the sustainable aviation fuel market, and damage to

both the Paramount Facility and the city’s economy.222 But by World Energy’s own

220

DeMarco v. Christiana Care Health Servs., Inc., 263 A.3d 423, 437 (Del. Ch. 2021) (citing Richard Paul, Inc. v. Union Improvement Co., 86 A.2d 744, 747–48 (Del. Ch. 1952)).

221

See AM Gen. Hldgs. LLC v. Renco Gp., Inc., 2012 WL 6681994, at *4 (Del. Ch. Dec. 21, 2012); Gray v. Council of Town of Newark, 79 A. 735, 737 (Del. Ch. 1911) (“A clear case of prospective injury for which the plaintiff will have no adequate remedy at law is indispensable.”).

222

Compl. ¶¶ 216–17.

42

admission, it does not need the requested mandatory relief to avoid those harms:

World Energy could “engage another entity” to make the 12-D Rack repairs and

complete the work.223 Indeed, according to World Energy, “the 12-D Rack is not a

complex piece of machinery” that only Air Products can repair.224

Oral argument injected some question as to whether World Energy can hire

somebody else to repair the 12-D Rack and seek to shift the costs to Air Products.

There, World Energy asserted that engaging another entity would be infeasible given

Air Products’ ownership of the land, structures, and equipment at issue.225 It argued

Air Products has cut off access to the Paramount Facility.226 Counsel for Air

Products represented that is not true, referencing a letter it sent World Energy on

July 8, 2025.227 That letter makes clear “the access offer remains open.”228 I cannot

conclude World Energy will suffer irreparable harm absent the requested relief.

223

Id. at Prayer for Relief.

224

D.I. 27 at 27.

225

Hr’g Tr. 55; see also D.I. 27 at 23; Compl. ¶ 192.

226

Hr’g Tr. 55.

227

Id. at 124–25 (referencing a letter dated July 8, 2025, stating that “the access offer remains open. If World Energy wishes to access the Paramount refinery to conduct remediation activities, it is welcome to do so with appropriate supervision as long as it pays for those activities and confirms that allowing access will not prejudice Air Products’ legal rights . . . .”). World Energy did not dispute receiving this letter. 228

Id.

43

In the absence of irreparable harm, the balance of the equities weighs against

World Energy. Granting the requested mandatory relief would require Air Products

to perform services under a contract that it terminated months ago, as it was entitled

to do. World Energy can solve the problem its defaults created by hiring somebody

else to fix the 12-D Rack. Under these circumstances, World Energy has not shown

that denying the mandatory injunction would cause it “greater harm than granting

the injunction will cause [Air Products].”229

III. CONCLUSION

World Energy is not entitled to the mandatory injunctive relief it seeks, and

Air Products’ motion to dismiss is GRANTED.

229

DeMarco, 263 A.3d at 437 (citing Cantor Fitzgerald, L.P. v. Cantor, 724 A.2d 571, 587 (Del. Ch. 1998)).

44