Snipes Concrete & Hauling, LLC v. BC Constr. Grp., Inc.

2026-08-19

Summary

Holding. The Court of Appeals reversed the trial court's order compelling arbitration in North Carolina and remanded the case. The FAA applies to the parties' contract because it evidences a transaction involving interstate commerce, thus preempting North Carolina General Statute Section 22B-2 and requiring the arbitration to proceed in Michigan as specified in the contract.

Snipes Concrete entered into a subcontract with BC Construction Group (BCCG), a Michigan-based general contractor, to perform concrete work on a school building project in Durham, North Carolina. The subcontract contained an arbitration clause requiring disputes to be resolved through binding arbitration in Brighton, Michigan. When Snipes sued BCCG for nonpayment, BCCG moved to compel arbitration in Michigan. The trial court agreed to compel arbitration but relocated the venue to North Carolina, citing North Carolina law that voids forum-selection clauses requiring out-of-state proceedings for real property improvement contracts.

BCCG appealed, arguing that the Federal Arbitration Act (FAA) applied to the interstate commercial transaction and preempted the North Carolina statute. The appellate court agreed, finding that BCCG's status as a Michigan corporation, combined with the requirement that payment applications be submitted to Michigan and administrative functions be performed there, established that the contract involved interstate commerce. Under the FAA, the court explained that BCCG was entitled to enforce the arbitration agreement as written, including the Michigan forum-selection clause.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether the FAA applies to an arbitration clause in a construction subcontract involving an out-of-state general contractor and in-state subcontractor
  • What evidence and connections suffice to show a contract involves interstate commerce under the FAA
  • Whether North Carolina's forum-selection statute is preempted by the FAA when the underlying contract involves interstate commerce
  • Whether a state court may relocate arbitration based on judicial economy and efficiency concerns when the FAA applies

Procedural posture

BCCG appealed as of right an interlocutory order from the trial court that compelled arbitration but relocated the venue from Michigan to North Carolina.

Authorities cited

Opinion

majority opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA25-234

Filed 19 August 2026

Durham County, No. 23CVS003271-310

SNIPES CONCRETE AND HAULING, LLC, Plaintiff,

v.

BC CONSTRUCTION GROUP, INC., and TRAVELERS CASUALTY AND SURETY

COMPANY OF AMERICA, Defendants.

Appeal by defendant from order entered 23 May 2024 by Judge L. Lamont

Wiggins in Superior Court, Durham County. Heard in the Court of Appeals 9

September 2025.

Anderson Jones, PLLC, by Lindsey E. Powell and Todd A. Jones, for plaintiffappellee.

Conner Gwyn Schenck PLLC, by Andrew L. Chapin and Daniel C. Watts, for

defendant-appellant.

STROUD, Judge.

Defendant BC Construction Group, Inc. (BCCG) appeals an order compelling

arbitration in North Carolina rather than in Michigan, the forum the parties’ contract

designates. Because the contract involves interstate commerce, the Federal

Arbitration Act (FAA) applies and preempts North Carolina General Statute Section

22B-2. BCCG was therefore entitled to enforce the arbitration agreement as written,

including its forum-selection clause. We reverse and remand.

SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

I. Background

On 11 December 2023, Plaintiff Snipes Concrete and Hauling, LLC (Snipes), a

North Carolina limited liability company, filed an amended complaint against BCCG;

Kestrel Heights Facilities, LLC (Kestrel); and Corporation for Effective Schooling

(CES).1 BCCG is a “foreign corporation organized and existing under the laws of the

State of Michigan” and is “authorized to do business in North Carolina.” Snipes

alleged that Defendants Kestrel and CES (collectively, Owners) owned real property

in Durham, North Carolina known as Kestrel Heights Charter School (Property or

Project). BCCG, a construction company, entered into a contract with Owners to

“serve as the general contractor for” the Property’s “construction or improvement.”

Snipes entered into a subcontract (Contract) with BCCG to “provide labor,

equipment, and materials” for concrete work on the Project, which included the

installation of footings, floor slabs, and walls.

Snipes alleged that it performed its duties under the Contract but that BCCG

failed to pay in full for the work, despite Snipes’s “repeated payment demands.” It

further claimed that BCCG owed over $108,000 under the Contract. Snipes asserted

claims of breach of contract and, in the alternative, unjust enrichment or quantum

meruit against all Defendants. It also sought interest from BCCG at the rate of 1%

1 Snipes simultaneously filed a dismissal of Defendants Kestrel and CES.

BCCG consented to the

amendment of the complaint. The amended complaint added Travelers Casualty and Surety Company of America as a Defendant.

-2-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

per month under the North Carolina Prompt Pay Act, see N.C. Gen. Stat. § 22C-5

(2025), and asserted a claim on the lien discharge bond and a claim for attorney’s fees

against BCCG and Defendant Travelers Casualty and Surety Company of America

(Travelers).

On 5 February 2024, BCCG filed a motion to dismiss or, in the alternative, a

motion to stay litigation and compel arbitration. BCCG alleged that the Contract

between it and Snipes included the following arbitration provision:

Arbitration. The parties agree that all claims, disputes,

and other matters arising out of or relating to this

Subcontract shall be decided by binding arbitration

pursuant to the Construction Industry Arbitration Rules of

the American Arbitration Association. The arbitration

shall be conducted in Brighton: Livingston County,

Michigan. The arbitrator shall have the right to award

reasonable attorney’s fees to the prevailing party as well as

taxation of the costs of the arbitration as part of the award.

However, in the event of any dispute between

Subcontractor and Contractor arising under or relating to

this Subcontract, or the breach thereof, which in

Contractor’s judgment involves the correlative rights and

duties of Owner or its agents, the dispute shall be decided

in accordance with the Contract Documents, and

Subcontractor and its sureties shall be bound to any

decisions or determination made by an authorized person,

board, court, or other tribunal. In Contractor’s sole

discretion, any arbitration or litigation between Contractor

and Subcontractor under this Subcontract may be joined

with and consolidated into any arbitration or litigation

between the Owner and Contractor, and such arbitration

or litigation shall bind Contractor and Subcontractor.

-3-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

BCCG alleged that Snipes’s claims were subject to binding arbitration under

the Contract and requested that Snipes’s complaint be dismissed or, in the

alternative, stayed under Title 9 United States Code Section 4—i.e., the FAA—and

North Carolina General Statutes Sections 1-569.5 and 1-569.7, with arbitration

compelled in accord with the Contract.

On 10 May 2024, Snipes filed the affidavit of Jordan Snipes—its vice

president—in opposition to BCCG’s motion. Mr. Snipes averred that the Project was

located entirely in North Carolina and that one of the Project’s Owners, Kestrel, was

a limited liability company organized in North Carolina. His affidavit also stated

that Snipes had (1) “received, reviewed, and executed” the Contract in North

Carolina, (2) “performed all labor exclusively in North Carolina,” (3) “supplied all

equipment” and “materials exclusively” in North Carolina, and (4) “sourced” all the

materials it supplied from North Carolina entities. He further averred that all the

laborers Snipes hired or contracted were residents of North Carolina, and they were

hired to work on the Project site. No materials or personnel on the Project ever left

North Carolina, and every permit, inspection, and other compliance activity was done

or obtained in North Carolina. Mr. Snipes also averred that BCCG “holds itself out

as having” offices in Raleigh and Charlotte, North Carolina. And he stated that

Snipes “never contemplated that the performance of the [Contract] would involve

multiple states.” A copy of the Contract was attached to the affidavit.

On 13 May 2024, BCCG filed the affidavit of Heather Watkins, its Director of

-4-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Accounting. Her affidavit stated that BCCG is a Michigan corporation with its

primary office in Brighton, Michigan. Ms. Watkins averred that BCCG is a licensed

general contractor in several states, including North Carolina, and it served as the

general contractor for the Project in Durham, North Carolina. She further asserted

that “[m]uch of the preconstruction and design work” occurred outside of North

Carolina, including in Michigan, and that “[a]ll bookkeeping and accounting records”

for the project were kept in Michigan. And she stated that Snipes submitted its

payment applications and invoices to BCCG in Michigan. Attached to the affidavit

were the Contract, which BCCG’s vice-president executed in Michigan, and a

Certificate of Insurance for the Project, which was provided to BCCG at its Michigan

address.

On 14 May 2024, the trial court held a hearing on BCCG’s motion to dismiss

or, in the alternative, to stay litigation and compel arbitration. The trial court

considered the affidavits submitted by Snipes and BCCG. At the hearing, the parties

stipulated that there was “an enforceable arbitration agreement between the parties

and the scope of the disputes is covered by the arbitration agreement.” The parties

also agreed that the issue in dispute was “the venue of that arbitration.” BCCG

argued that the arbitration provision was binding and enforceable as written, and

that the FAA applied because “the contract in question evidences a transaction

involving interstate commerce.” Snipes argued that the Contract was performed

entirely in North Carolina, so (1) the FAA would not preempt North Carolina General

-5-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Statute Section 22B-2, see N.C. Gen. Stat. § 22B-2 (2025) (Contracts to improve real

property), and (2) the arbitration should be held in North Carolina instead of

Michigan. In short, the only disputed issue at the hearing was whether the Contract

“involved interstate commerce” as contemplated by the FAA.

On 28 May 2024, the trial court entered an Amended Order Staying Litigation

and Compelling Arbitration (Order).2 In the Order, the trial court did not separate

its findings of fact from its conclusions of law. Instead, the findings, conclusions, and

decree appear under a single section beginning: “Now, therefore, the court finds and

orders as follows.” (Capitalization altered.) The Order granted BCCG’s motion to stay

litigation and compel arbitration but required the arbitration to be held in North

Carolina instead of Michigan.

The trial court made findings of fact about the Contract and the Project

generally consistent with Mr. Snipes’s affidavit. Although BCCG is a Michigan

company, it specifically found that it was “adopt[ing] the recital of . . . Snipes that the

project that is the subject of th[e] action is wholly contained within North Carolina

2 The trial court entered an initial Order Staying Litigation and Compelling Arbitration on 21 May

2024. The reason for the Amended Order Staying Litigation and Compelling Arbitration is not apparent in our record, but the initial order and the amended order are identical except for the filing dates. The notice of appeal is timely as to either order. See Assoc. Behav. Servs., Inc. v. Smith, 264 N.C. App. 277, 279, 826 S.E.2d 214, 216 (2019) (noting that our Rules of Appellate Procedure “require[ ] that parties to a civil action file and serve a notice of appeal within thirty days after entry of a final judgment” (citation omitted)). Trial courts generally have jurisdiction to make non-substantive corrections to orders before entry of a notice of appeal, and because the two orders are identical, the trial court had jurisdiction to enter the amended order. See generally In re A.R.B., 289 N.C. App. 119, 124, 888 S.E.2d 402, 405 (2023) (allowing amendment for correction of clerical errors).

-6-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

and the subcontract between BCCG and Snipes was wholly performed within North

Carolina.” The court also found that there were “no issues of federal control that

would invoke federal activity or interstate commerce.” And based on the arguments

of counsel rather than the record or evidence, it found:

[O]ther subcontractors to BCCG have claims on the project

that are subject to arbitration in North Carolina, and the

[c]ourt, in the exercise of its legal and equitable

jurisdiction, and for the purposes of judicial economy and

efficiency, determines that all subcontractor arbitrations

should take place in North Carolina.

The trial court ordered BCCG and Snipes to “submit all issues between them

to binding arbitration,” and it ruled that the “venue for such arbitration shall be [in]

North Carolina.” And the arbitration was to be completed no later than 25 February

2024. The court proceedings were “stayed pending (a) the conclusion of the

arbitration ordered herein or (b) a joint stipulation of voluntary dismissal filed herein

by BCCG and Snipes.”

BCCG filed a notice of appeal from the Order on 13 June 2024.

II. Appellate Jurisdiction

BCCG acknowledges that this is “an interlocutory appeal from the trial court’s

order denying [its] motion to compel arbitration.” Under North Carolina General

Statute Section 7A-27(b)(3)a, an interlocutory order may be appealed as of right if it

“[a]ffects a substantial right.” N.C. Gen. Stat. § 7A-27(b)(3)a (2025). The “denial of

a motion to compel arbitration, although interlocutory, is . . . immediately

-7-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

appealable,” because “it affects a substantial right.” King v. Bryant, 225 N.C. App.

340, 343, 737 S.E.2d 802, 805 (2013) (citation and quotation marks omitted). But the

Order does not deny arbitration; it compels arbitration. And it moves the arbitration

from Michigan, the forum the Contract specifies, to North Carolina.

Still, this Court has determined that an order “addressing the validity of a

forum-selection clause also affect[s] a substantial right.” Earnhardt Plumbing, LLC

v. Thomas Builders, Inc., 291 N.C. App. 1, 4, 893 S.E.2d 564, 567 (2023) (citation

omitted). The Contract designates Michigan as the arbitration’s venue; the Order

overrides that designation. Thus, citing Jeffreys v. Raleigh Oaks Joint Venture, 115

N.C. App. 377, 380, 444 S.E.2d 252, 254 (1994), BCCG contends that it would lose its

“substantial right to arbitrate in Michigan ‘absent a review prior to a final

determination on the merits.’ ” BCCG is correct. Because the Order affects a

substantial right, we have appellate jurisdiction under Section 7A-27(b)(3)a. See

Earnhardt Plumbing, 291 N.C. App. at 4, 893 S.E.2d at 567.

III. Standard of Review

“Whether a particular dispute is subject to arbitration is a conclusion of law,”

which this Court reviews de novo on appeal. Id. (citation omitted). We likewise

review de novo “issues relating to the interpretation of terms in an arbitration

clause.” Id. (citations, quotation marks, and brackets omitted). As noted above, the

Order did not separately set out its findings of fact, conclusions of law, and decree

provisions. We consider each finding and conclusion based on its substance and

-8-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

review them accordingly. See In re K.J.M., 288 N.C. App. 332, 339, 886 S.E.2d 589,

595 (2023) (“As a general rule, the labels ‘findings of fact’ and ‘conclusions of law’

employed by the lower tribunal in a written order do not determine the nature of our

standard of review because if the lower tribunal labels as a finding of fact what is in

substance a conclusion of law, we review that ‘finding’ as a conclusion de novo.”

(citation and quotation marks omitted)).

IV. The FAA’s Application

BCCG argues that “the trial court erred by failing to determine whether the

[FAA] applied to the arbitration provision at issue and preempted state law.” In its

view, the FAA applies and preempts Section 22B-2, which provides that

[a] provision in any contract, subcontract, or purchase

order for the improvement of real property in this State, or

the providing of materials therefor, is void and against

public policy if it makes the contract, subcontract, or

purchase order subject to the laws of another state, or

provides that the exclusive forum for any litigation,

arbitration, or other dispute resolution process is located in

another state.

N.C. Gen. Stat. § 22B-2.

BCCG notes that the trial court “failed to directly address the FAA, either in

the hearing itself or in its subsequent orders.” (Capitalization altered.) And BCCG

asserts that the court applied the “wrong test” to determine whether interstate

commerce was affected.

The trial court found, based on Mr. Snipes’s affidavit, that the Project was

-9-SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

performed in North Carolina. In so doing, it essentially ignored the undisputed fact

that BCCG is a Michigan corporation and that the Contract requires certain financial

and administrative matters to be handled in Michigan. In fact, the court found that

there were “no issues of federal control that would invoke federal activity or interstate

commerce.” At the hearing, however, the parties had agreed that the only issue in

dispute was whether the Contract involved interstate commerce, such that the FAA

applies and preempts North Carolina law.

Snipes responds that

[i]t is well-established that the determination of whether a

transaction involves interstate commerce such that the

FAA will apply is a question of fact for the trial court.

Eddings v. S. Orthopedic & Musculoskeletal Assocs., P.A.,

147 N.C. App. 375 385, 555 S.E.2d 649, 656 (2001) (Greene,

J., dissenting), rev’d per curiam for reasons stated in the

dissent, 356 N.C. 285, 286, 569 S.E.2d 645, 645 (2002);

Sillins v. Ness, 164 N.C. App. 755, 758, 596 S.E.2d 874, 876

(2004); King v. Bryant, 225 N.C. App. 340, 344, 737 S.E.2d

802, 806 (2013): Earnhardt Plumbing v. Thomas Builders,

291 N.C. App. 1, 5, 893 S.E.2d 564, 568 (2023).

As Snipes notes, the trial court has the initial responsibility to make findings

of fact, and if the findings are supported by the record, the appellate court is bound

by them. Despite finding that “there are no issues of federal control that would invoke

federal activity or interstate commerce,” the court granted BCCG’s motion to compel

arbitration, which explicitly relied on “the [FAA], 9 [United States Code Section] 1 et

seq., and the North Carolina Revised Uniform Arbitration Act, [North Carolina

General Statute Section] 1-569.1 et seq.” Because the trial court granted BCCG’s

- 10 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

motion to compel arbitration under the FAA, the Order is (in fact) based on the FAA,

even if it does not mention it.

The FAA provides:

If any suit or proceeding be brought in any of the courts of

the United States upon any issue referable to arbitration

under an agreement in writing for such arbitration, the

court in which such suit is pending, upon being satisfied

that the issue involved in such suit or proceeding is

referable to arbitration under such an agreement, shall on

application of one of the parties stay the trial of the action

until such arbitration has been had in accordance with the

terms of the agreement, providing the applicant for the

stay is not in default in proceeding with such arbitration.

9 U.S.C. § 3.

No one disputes that BCCG is a Michigan corporation. Snipes’s amended

complaint alleges as much, and the attached Contract lists BCCG’s Michigan address

in several places. And the parties’ affidavits do not contradict each other; they

address different facts. Mr. Snipes’s affidavit focuses on the physical work performed

under the Contract—concrete work to construct a school building—in North Carolina.

BCCG’s affidavit addresses its status as a Michigan corporation and the planning,

administrative, and financial tasks done in Michigan. Neither party disputes the

other’s facts. At the hearing, Snipes argued only that BCCG’s Michigan presence and

business were irrelevant because the Project was in North Carolina and Section 22B2 voided the arbitration clause, at least in part.

At the hearing, Snipes argued that it was “not [t]here opposing arbitration

- 11 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

itself” but was “opposing the venue or the forum selection of [arbitration] pursuant to

both common law in North Carolina and [Section] 22B-2.” Citing North Carolina

law,3 it contended that the Contract’s arbitration provision—“The arbitration shall

be conducted in Brighton, Livingston County, Michigan”—was not mandatory. In

Snipes’s view, then, the trial court could enforce the arbitration provision while

relocating the arbitration under North Carolina law.

This Court has twice addressed an arbitration provision under similar facts.4

See Earnhardt Plumbing, LLC v. Thomas Builders, Inc., 291 N.C. App. at 1, 893

S.E.2d at 564 (Earnhardt I); see also Earnhardt Plumbing, LLC v. Thomas Builders,

Inc., 301 N.C. App. 586, 924 S.E.2d 844 (2025) (Earnhardt II).

Earnhardt Plumbing, LLC, a North Carolina limited liability company,

subcontracted to install plumbing and gas line systems for a hotel under construction

in Fayetteville, North Carolina. Earnhardt I, 291 N.C. App. at 2, 893 S.E.2d at 566.

3 The Contract also includes a choice-of-law provision, which states that it “shall be interpreted under

the laws of the State of Michigan without consideration of conflicts of laws rules.” Neither party has cited any Michigan law, and neither has raised any argument on appeal about the Contract’s interpretation.

4 We note that Snipes invokes Section 22B-2 rather than Section 22B-3, the statute at issue in Earnhardt. Section 22B-2 voids a provision in a contract “for the improvement of real property in this State” that “provides that the exclusive forum for any litigation, arbitration, or other dispute resolution process is located in another state.” N.C. Gen. Stat. § 22B-2. The Contract’s Michigan designation falls within those terms. As we explain below, Section 2 of the FAA preserves only state grounds “for the revocation of any contract”—defenses like fraud or duress, which ask whether a party should be held to the agreement at all. 9 U.S.C. § 2. Section 22B-2 supplies no defense of that kind. It leaves a construction contract wholly enforceable and strikes a single term, the one selecting the forum. That is the defect that doomed Section 22B-3, which, we said, “applies to one type of provision only.” Earnhardt Plumbing, LLC v. Thomas Builders, Inc., 301 N.C. App. 586, 595, 924 S.E.2d 844, 852 (2025). The FAA thus preempts Section 22B-2 as applied to the Contract’s forum-selection clause.

- 12 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Thomas Builders, Inc., the general contractor, was a Tennessee corporation with a

registered office in Wake County. Id. As here, an in-state subcontractor—Earnhardt

Plumbing—sued an out-of-state general contractor—Thomas Builders—to collect

payment for work performed in North Carolina. Id.

The contract required arbitration of claims arising “out of or related to this

Subcontract” and provided that “[t]he Arbitration shall be held at the discretion of

the Contractor either at Contractor’s principle [sic] place of business or where the

Project is located.” Id. Thomas Builders wanted arbitration to “take place in

Tennessee”—its principal place of business. And as here, the parties did not dispute

that the claims were arbitrable—only whether the arbitration would occur in a

different state or in North Carolina. Id. at 3, 893 S.E.2d at 566.

The trial court stayed the proceedings and compelled arbitration. Id. at 3, 893

S.E.2d at 566–67. It concluded that the provision allowing Thomas Builders “to

require Tennessee be the forum for arbitration was unenforceable” under North

Carolina General Statute Section 22B-3, and it ordered that arbitration be conducted

in North Carolina. Id. at 3, 893 S.E.2d at 567; see also N.C. Gen. Stat. § 22B-3 (2023)

(“[A]ny provision in a contract entered into in North Carolina that requires the

prosecution of any action or the arbitration of any dispute that arises from the

contract to be instituted or heard in another state is against public policy and is void

and unenforceable.”). It also ruled that the FAA did not preempt Section 22B-3.

Earnhardt I, 291 N.C. App. at 4, 893 S.E.2d at 567.

- 13 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

On appeal, this Court vacated and remanded. We explained that the FAA

applies “if the contract evidences a transaction involving interstate commerce,” and

whether it does is a question of fact an appellate court should not decide in the first

instance. Id. at 5, 893 S.E.2d at 568 (quoting Hobbs Staffing Servs., Inc. v.

Lumbermens Mut. Cas. Co., 168 N.C. App. 223, 226, 606 S.E.2d 708, 711 (2005)). The

Court also noted that where a contract does “involve[ ] commerce among the States,”

the FAA preempts North Carolina’s statute and public policy on forum selection. Id.

(citing Goldstein v. Am. Steel Span, Inc., 181 N.C. App. 534, 538, 640 S.E.2d 740, 743

(2007)). The trial court had found only that a valid arbitration agreement existed

and that the dispute fell within its scope. See id. It made no findings “as to whether

the parties’ [c]ontract evidence[d] a transaction involving interstate commerce,” and

without such findings, we could not evaluate whether the FAA applied. Id. at 5–6,

893 S.E.2d at 568.

On remand, the trial court found that the contract involved interstate

commerce and concluded that the FAA preempted Section 22B-3 as applied to the

forum-selection clause. Earnhardt II, 301 N.C. App. at 588, 924 S.E.2d at 848. It

nonetheless determined the clause was permissive rather than mandatory, held it

unenforceable under North Carolina law, and again directed arbitration in North

Carolina. Id. Thomas Builders appealed, and this Court reversed in Earnhardt II.

Id.

- 14 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Our analysis began with whether the FAA applied at all. Earnhardt Plumbing

claimed that the trial court had to “find there was ‘substantial’ interstate commerce.”

Id. at 590, 924 S.E.2d at 849. This Court rejected that argument as resting on

“preempted precedent.” Id. The FAA, we said, applies if the transaction “in fact

involve[s] interstate commerce, even if the parties did not contemplate an interstate

commerce connection.” Id. (quoting Allied-Bruce Terminix Cos. v. Dobson, 513 U.S.

265, 270, 281 (1995)). Indeed, the United States Supreme Court interprets the FAA’s

reach “to the limits of Congress’ Commerce Clause power.” Id. So we determined

that the trial court needed only to “find facts supporting [the] conclusion the

transaction involved interstate commerce.” Id.

We also agreed with Earnhardt Plumbing that the “mere diversity of [the]

parties” did not establish “that [the] agreement involved interstate commerce.” Id.

at 591, 924 S.E.2d at 849. The trial court, however, had also found that payment

requests crossed state lines and that Thomas Builders’ employees traveled across

state lines in connection with the contract. Id. Those findings sufficed, and they

matched the connections our state courts and the federal courts had held sufficient

elsewhere. Id. at 591, 924 S.E.2d at 849–50 (citations omitted).

We then addressed who bears the burden on the interstate-commerce question.

The FAA, we noted, does not “require proof by affidavit or other specific evidence of

the nexus to interstate commerce.” Id. at 591, 924 S.E.2d at 849 (citation omitted).

Where the party seeking arbitration alleges the transaction falls within the FAA’s

- 15 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

scope and the opposing party offers no evidence rebutting jurisdiction under the

federal statute, the FAA demands nothing further. Id. Thomas Builders had alleged

that the contract involved interstate commerce, and Earnhardt Plumbing identified

no contrary evidence,

except that [Earnhardt] used only materials from North

Carolina and the labor of North Carolina employees.

Th[at] evidence d[id] not rebut [Thomas Builders’]

allegation because the origins of material and labor

involved are not the only factors by which interstate

commerce may be evidenced.

Id.

With the FAA in play, the Court turned to whether Section 22B-3 could still

void the forum-selection clause. It could not. Id. at 595, 924 S.E.2d at 852. The FAA

does not “completely preempt state contract law because it does not ‘reflect a

congressional intent to occupy the entire filed of arbitration.’ ” Id. at 592, 924 S.E.2d

at 850 (citation omitted). But where federal and state law conflict, we observed, the

Supremacy Clause requires that “we give effect to federal law.” Id. Section 2 of the

FAA makes arbitration agreements enforceable save “upon such grounds as exist at

law or in equity for the revocation of any contract.” 9 U.S.C. § 2. That provision

preserves “generally applicable contract defenses, such as fraud, duress, or

unconscionability,” but not “defenses that apply only to arbitration or that derive

their meaning from the fact that an agreement to arbitrate is at issue.” Earnhardt

II, 301 N.C. App. at 594, 924 S.E.2d at 852 (citation omitted).

- 16 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Earnhardt Plumbing claimed that Section 22B-3 was such a general defense

because it reaches every contract formed in North Carolina and voids litigation and

arbitration forum clauses alike. Id. at 595, 924 S.E.2d at 852. This Court rejected

that claim. While Section 22B-3 “explicitly applies to all contracts, it applies to one

type of provision only, forum-selection provisions,” and so is “not a general contract

defense like ‘fraud, coercion, lack of consideration’ or lack of meeting of the minds.”

Id. at 595, 924 S.E.2d at 852 (citation omitted). Reading it otherwise, we said, would

sit “directly at odds” with the Supreme Court’s holding that the FAA “preempts state

laws” requiring “a judicial forum for the resolution of claims which the contracting

parties agreed to resolve by arbitration.” Id. (quoting Southland Corp. v. Keating,

465 U.S. 1, 10 (1984)). This Court’s decision in Goldstein had held as much already,

and that holding bound the panel. Id. at 593, 924 S.E.2d at 851 (citing Goldstein, 181

N.C. App. at 538, 640 S.E.2d at 743; In re Civil Penalty, 324 N.C. 373, 384, 379 S.E.2d

30, 37 (1989)).

Finally, the Court assessed whether the trial court erring in ruling that the

arbitration clause was permissive and thus unenforceable. As a reminder, that clause

let Thomas Builders choose between two forums: “either” its principal place of

business “or” the Project site. See id. at 587, 924 S.E.2d at 847. A forum-selection

clause is mandatory when it contains words “which indicate that the contracting

parties intended to make jurisdiction exclusive,” and no particular modifier—“only,”

“solely,” “exclusively”—is required. Id. at 598, 924 S.E.2d at 854 (quoting Cable Tel

- 17 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

Servs., Inc. v. Overland Cont., Inc., 154 N.C. App. 639, 644, 574 S.E.2d 31, 34–35

(2002)). We held that the disjunctive “either . . . or” construction marked the

designated fora as the only available ones, and that the grant of discretion to one

party to choose between them made the parties’ intent plain.5 Id. at 597–98, 924

S.E.2d at 853–54.

The facts here closely track Earnhardt I and II, but as we explain below, the

trial court erred differently. BCCG’s arguments focus on both the findings of fact and

the conclusions of law, but the substance of its position is that the trial court acted

under a misapprehension of law. BCCG contends that “[w]hile the trial court made

findings consistent with the parties’ stipulations, it failed to make any [sic] findings

to support any conclusion of law that would permit it to [ ] ignore the uncontroverted

evidence contained in” Ms. Watkins’s affidavit “that corroborates the existence and

validity of the [Contract] and its effects on interstate commerce.”

The trial court made no findings about BCCG’s status as a Michigan

corporation or Snipes’s submission of payment requests to Michigan. It found instead

5 The provision at issue here names a single forum—Michigan—with no alternative and no discretion

in either party. And Snipes has not argued that it is permissive. Still, the Contract does provide that “In Contractor’s sole discretion, any arbitration or litigation between Contractor and Subcontractor under this Subcontract may be joined with and consolidated into any arbitration or litigation between the Owner and Contractor, and such arbitration or litigation shall bind Contractor and Subcontractor.” But even this portion of the provision does not address changing the arbitration’s venue. The Contract states that the arbitration “shall” be held in Michigan. Under basic rules of contract interpretation in both North Carolina and Michigan, the term “shall” is mandatory. See Internet E., Inc. v. Duro Commc’ns, Inc., 146 N.C. App. 401, 405–06, 553 S.E.2d 84, 87 (2001); Oakland-Macomb Interceptor Drain Drainage Dist. v. Ric-Man Const., Inc., 304 Mich. App. 46, 56, 850 N.W.2d 498, 504 (2014).

- 18 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

that “[t]here are no issues of federal control that would invoke federal activity or

interstate commerce.” This finding is confusing, because the parties agreed that the

existence of “interstate commerce” was the sole issue. And the parties agreed that

the dispute must go to binding arbitration—again, Snipes argued only that the

arbitration should occur in North Carolina under Section 22B-2.

The trial court appears to have treated BCCG’s status as a Michigan

corporation and the administrative and financial matters handled in Michigan as

irrelevant to the FAA’s application. Under Earnhardt II, they are not. BCCG invoked

the FAA and alleged that the Contract involved interstate commerce. That allegation

shifted to Snipes—“the party opposing [the FAA’s] application”—the burden of

producing “evidence to rebut jurisdiction under the federal statute.” Id. at 591, 924

S.E.2d at 849.

Snipes did not carry that burden. Its affidavit spoke only to the location of the

Project and the origins of the material and labor—the exact showing Earnhardt II

held insufficient to rebut an allegation of interstate commerce. Id. The facts as found

by the trial court are not entirely irrelevant, but the trial court simply did not address

the undisputed facts regarding BCCG’s status as a Michigan corporation and the

administrative and financial matters conducted in Michigan by BCCG.6 To the extent

6 The trial court implicitly addressed BCCG’s presence in Michigan in two findings: “BCCG has sufficient contacts with North Carolina and is doing business in North Carolina, with offices in Charlotte and Raleigh. Additionally, BCCG has applied for and has been granted a Certificate of

- 19 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

the trial court overlooked these facts, it was acting under a misapprehension of the

law. As stated earlier, those facts have been held to require a conclusion that a

contract “involv[es] interstate commerce” for purposes of the FAA. Hobbs, 168 N.C.

App. at 226, 606 S.E.2d at 711.

That leaves the question of remedy. Earnhardt I remanded for findings, and

we consider whether this case calls for the same course. It does not—and the line of

authority behind Earnhardt I explains why.

In Earnhardt I, the Court drew its remand instruction from Hobbs. See

Earnhardt I, 291 N.C. App. at 5, 893 S.E.2d at 568. In Hobbs, the question presented

was whether the dispute fell within the parties’ arbitration agreement; this Court

affirmed the trial court’s ruling that it did. Hobbs, 168 N.C. App. at 226–27, 606

S.E.2d at 711. In their briefs to this Court, the parties tried to raise an additional

question the trial court had never taken up—whether the agreement fell under the

North Carolina Uniform Arbitration Act or the FAA. Id. at 226, 606 S.E.2d at 711.

This Court declined to examine those arguments. We held that whether a contract

evidences a transaction involving interstate commerce “is a question of fact, which an

appellate court should not initially decide.” Id. at 226–27, 606 S.E.2d at 711 (relying

Authority to transact business in North Carolina by the Secretary of State and maintains a registered agent and office in North Carolina.” There would be no reason to address BCCG’s contacts with North Carolina if BCCG was in North Carolina. And the purpose of this finding is not clear because there was no question of personal jurisdiction over BCCG. The trial court also found that “BCCG has diversity of citizenship and substantial contacts in North Carolina, Michigan, and other states.” But again, BCCG’s “substantial contacts” in North Carolina are irrelevant to the arbitration question.

- 20 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

on Eddings v. S. Orthopedic & Musculoskeletal Assocs. Inc., 356 N.C. 285, 569 S.E.2d

645 (2002) (per curiam)). The question therefore belonged to the trial court on

remand. Id. at 227, 606 S.E.2d at 711.

Hobbs took that principle from Eddings, where our Supreme Court had applied

it the year before. See id. The plaintiff in Eddings was a physician who had been

practicing in Chattanooga. Eddings v. S. Orthopedic & Musculoskeletal Assocs., P.A.,

147 N.C. App. 375, 376, 555 S.E.2d 649, 650 (2001), rev’d per curiam, 356 N.C. at 285,

569 S.E.2d at 645 (adopting dissenting opinion in the Court of Appeals). He came to

North Carolina to interview with a medical practice, entered negotiations over

possible employment, and signed an employment agreement. Id. This Court

concluded that the agreement memorialized “a transaction . . . by which [the] plaintiff

[had] left his practice in Chattanooga and crossed state lines to begin practicing in

North Carolina,” and that “[s]uch a transaction clearly involve[d] interstate

commerce.” Id. at 382–83, 555 S.E.2d at 654. Judge Greene dissented. Id. at 385,

555 S.E.2d at 656 (Greene, J., dissenting).

On appeal, our Supreme Court reversed, adopting Judge Greene’s dissent. See

Eddings, 356 N.C. at 286, 569 S.E.2d at 645 (“For the reasons stated in the dissenting

opinion, the decision of the Court of Appeals is reversed.”). Judge Greene did not

doubt that the agreement might fall under the FAA. Eddings, 147 N.C. App. at 385,

555 S.E.2d at 656 (Greene, J., dissenting). His objection centered on the record. Id.

(Greene, J., dissenting). Neither party, he observed, had argued the FAA applied or

- 21 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

that the agreement evidenced a transaction involving commerce. Id. (Greene, J.,

dissenting). Beyond the single fact that the plaintiff had lived in Tennessee before

moving to North Carolina, the record held “no evidence . . . that the transaction

involved multiple states”—indeed, it was “devoid of any evidence” that the

“[e]mployment [a]greement or [the] plaintiff’s employment” involved interstate

commerce within the FAA’s scope. Id. at 385–86, 555 S.E.2d at 656 (Greene, J.,

dissenting). An appellate court “may speculate on what may have been the nature of

the performance required by the contract,” he wrote, but on such a record he thought

it “impossible for us to determine on appeal whether the [FAA] applies.” Id. at 386,

555 S.E.2d at 656 (Greene, J., dissenting). So he thought the Court should have

remanded for the trial court to make that determination first. Id. (Greene, J.,

dissenting).

One feature unites Eddings, Hobbs, and Earnhardt I: in each, the facts bearing

on interstate commerce remained unsettled. In Eddings, no party had argued the

FAA applied, so no one developed the record on it, and the only interstate fact before

the Court was where the plaintiff had lived before. Id. at 385–86, 555 S.E.2d at 656

(Greene, J., dissenting). In Hobbs, the parties raised the FAA for the first time on

appeal, leaving the trial court no occasion to hear any evidence on the question.

Hobbs, 168 N.C. App. at 226, 606 S.E.2d at 711. And in Earnhardt I, the parties did

litigate the FAA, but the trial court ruled without finding the facts its ruling required.

Earnhardt I, 291 N.C. App. at 5, 893 S.E.2d at 568. In none of the three could an

- 22 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

appellate court resolve the question without supplying facts the record did not

contain.

Here, the facts are settled. BCCG raised the FAA in the trial court, the parties

agreed that its applicability was the only issue at the hearing, and the operative facts

appear on the face of the Contract and its attachments. Snipes has never contested

BCCG’s Michigan incorporation, the Contract’s requirement that payment

applications go to Michigan, or BCCG’s administrative and financial duties there.

Simply put, nothing requires us to speculate about whether “the contract in question

involve[es] interstate commerce.” Eddings, 147 N.C. App. at 386, 555 S.E.2d at 656

(Greene, J., dissenting).

Moreover, the United States Supreme Court has interpreted the FAA’s

“involving commerce” language broadly. See Allied-Bruce, 513 U.S. at 273–77. It

reads that language to reach as far as the Commerce Clause itself—that is, to the full

extent of Congress’s power. Id. at 273–74. A narrower reading, the Court has

warned, would strand courts in a “no man’s land” between “in commerce” and

“affecting commerce,” complicating the law and breeding the very litigation the FAA

seeks to avoid. Id. at 275.

The Contract here clears that standard. BCCG is a Michigan corporation. The

Contract required Snipes to submit its payment applications and invoices to BCCG

in Michigan, and it assigned certain administrative and financial duties to BCCG

there. Snipes disputes none of this. That the Project was built in North Carolina

- 23 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

with North Carolina labor and materials does not resolve the question, because the

origins of material and labor are not the only indicia of interstate commerce.

Earnhardt II, 301 N.C. App. at 590, 924 S.E.2d at 849. And beyond the parties’

obvious diversity, the cross-border payment requests and BCCG’s Michigan

obligations under the Contract are precisely the connections Earnhardt II found

sufficient. Id. at 591, 924 S.E.2d at 849–50. The Contract thus evidences a

transaction involving interstate commerce, and the FAA applies.

In sum, our standard of review is de novo. Goldstein, 181 N.C. App. at 536,

640 S.E.2d at 742. Under the findings of fact and the undisputed facts included in

Snipes’s complaint and BCCG’s motion, both of which include the Contract and its

attachments, the Contract “involv[es] interstate commerce.” Hobbs, 168 N.C. App. at

226, 606 S.E.2d at 711. Because the FAA preempts Section 22B-2, the arbitration

provision requires the parties to arbitrate in Michigan, not North Carolina.

Goldstein, 181 N.C. App. at 538, 640 S.E.2d at 743.

V. Alternative Basis for Ruling

We have already held that the trial court erred by failing to apply the FAA

when it ordered arbitration in North Carolina. But paragraph 12 of the Order sets

out what appears to be an independent basis for the same result. And BCCG argues

that the trial court erred by ordering arbitration based on that paragraph. Paragraph

12 provides:

- 24 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

The [c]ourt further finds that other subcontractors to

BCCG have claims on the project that are subject to

arbitration in North Carolina, and the [c]ourt, in the

exercise of its legal and equitable jurisdiction, and for the

purposes of judicial economy and efficiency, determines

that all subcontractor arbitrations should take place in

North Carolina.

According to BCCG, in this paragraph, the trial court “improperly consider[ed] other

subcontracts” and “interpos[ed] its own standard of ‘judicial economy and efficiency’

into the analysis of interstate commerce.”

Paragraph 12 contains a finding of fact followed by what appears to be an

alternative legal basis for the Order. We start with the supposed “finding” that other

subcontractors have claims on the Project subject to arbitration in North Carolina.

BCCG correctly asserts that there is simply no evidence to support it: the pleadings

say nothing about other subcontractors or other disputes arising from the Project,

and neither affidavit mentions them. At the hearing, counsel did refer to other

pending disputes that would be arbitrated here. But “it is axiomatic that arguments

of counsel are not evidence.” Reynolds v. Burks, 295 N.C. App. 515, 521, 906 S.E.2d

508, 512 (2024). Snipes does not contest the absence of evidence. It argues instead

that “[e]ven assuming that particular finding was not supported by competent

evidence, the finding is inapplicable to and not determinative of the issue,” and that

the trial court’s remaining findings support the Order. They do not, for the reasons

already given.

- 25 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

The remainder of paragraph 12 rests on the trial court’s “legal and equitable

jurisdiction” and “the purposes of judicial economy and efficiency.” No party argued

about any such authority below; the argument focused on Section 22B-2 alone. And

on appeal, neither party identifies a statute or decision supporting this “legal and

equitable jurisdiction,” and we have found none.

Nor could such authority survive the FAA. As we explained in Earnhardt II:

In enacting [Section] 2 of the [FAA], Congress declared a

national policy favoring arbitration and withdrew the

power of the states to require a judicial forum for the

resolution of claims which the contracting parties agreed

to resolve by arbitration. This preemption is in accord with

the purpose of the FAA. Congress enacted the FAA in 1925

in response to widespread judicial hostility to arbitration

agreements. The Supreme Court of the United States has

described the Act as reflecting a liberal federal policy

favoring arbitration, and the fundamental principle that

arbitration is a matter of contract. The principal purpose

of the FAA is to ensure that private arbitration agreements

are enforced according to their terms.

301 N.C. App. at 592–93, 924 S.E.2d at 850–51 (internal citations, quotation marks,

and brackets omitted). A state court’s equitable interest in consolidating related

arbitrations is not among the grounds on which the FAA permits a forum-selection

clause to be set aside.

We appreciate the trial court’s concern for judicial economy. Arbitrating all

Project disputes in one state may well be more efficient. But efficiency was not the

issue before the court. BCCG and Snipes agreed to arbitrate in Michigan, and under

the FAA, that agreement governs.

- 26 -SNIPES CONCRETE & HAULING, LLC V. BC CONSTR. GRP., INC.

Opinion of the Court

VI. Conclusion

For the reasons discussed above, we reverse the trial court’s Order and remand

“for entry of an order allowing the parties to pursue arbitration in accordance with

the terms of the Contract, including the forum-selection clause.” Id. at 598, 924

S.E.2d at 854.

REVERSED AND REMANDED.

Judges ARROWOOD and STADING concur.

- 27 -