LAW.coLAW.co

West Dev. v. Town of W. Yellowstone

2026-08-25

Summary

Holding. The Montana Supreme Court affirmed the District Court's grant of summary judgment in favor of the Town, holding that the 2007 Will Serve Letter did not constitute an enforceable contract or vested right because West Development failed to perform within a reasonable time—over thirteen years elapsed with the project dormant and permits expired—and that West Development's negligence claim failed under the public duty doctrine.

West Development purchased property in West Yellowstone in 2006 and obtained a building permit in 2007 to construct 48 condominium units. The Town's engineer issued a Will Serve Letter in August 2007, confirming the Town could provide water and sewer services to the project. West Development began construction in 2007 but ceased work in 2011 and allowed its permits to expire. The project remained inactive for nine years until West Development attempted to sell the property in 2020. The Town refused to guarantee immediate sewer connections because its system lacked capacity, citing a 2019 moratorium on new connections pending infrastructure upgrades. West Development then sued, claiming breach of contract, negligence, and seeking a declaration that the Will Serve Letter was an enforceable vested right.

The District Court granted summary judgment for the Town, holding that the Will Serve Letter did not constitute an enforceable contract because West Development failed to perform within a reasonable time. Over thirteen years had elapsed between issuance of the letter and West Development's demand for service, during which the project was dormant and its permits expired. Montana's Supreme Court affirmed, concluding that while the policy arguments supporting developer reliance on will-serve letters have merit, a contract requiring performance within reasonable time cannot extend indefinitely. Additionally, the court rejected the negligence claim under the public duty doctrine, finding no special relationship exception warranted imposition of a specific duty on the Town given the extreme passage of time and lack of active development.

Summary generated by law.co from the public-domain opinion. The opinion text itself is public domain.

Key issues

  • Whether a will-serve letter stating a municipality's capacity to provide water and sewer services creates an enforceable contract indefinitely
  • Whether a contract lacking an express time for performance must be performed within a reasonable time despite years of project inactivity
  • Whether a 2019 moratorium on sewer connections was the subject of West Development's claims or whether the claims were time-barred
  • Whether the public duty doctrine applies to a municipality's allocation of wastewater infrastructure capacity

Procedural posture

West Development appealed the District Court's grant of summary judgment to the Town on claims of breach of contract, negligence, and declaratory relief, and the Town cross-appealed on the ground that West Development's claims were time-barred.

Authorities cited

Opinion

majority opinion

08/25/2026

DA 25-0324

Case Number: DA 25-0324

IN THE SUPREME COURT OF THE STATE OF MONTANA

2026 MT 203

WEST DEVELOPMENT, LLC,

Plaintiff, Appellant, and

Cross-Appellee,

v.

TOWN OF WEST YELLOWSTONE,

MONTANA,

Defendant, Appellee, and

Cross-Appellant.

APPEAL FROM: District Court of the Eighteenth Judicial District,

In and For the County of Gallatin, Cause No. DV-20-1189A

Honorable Peter B. Ohman, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Kelsey Bunkers, Matthew Hibbs, Crowley Fleck PLLP, Bozeman,

Montana

For Appellee:

Bridget W. leFeber, Berg Lilly, PC, Bozeman, Montana

Submitted on Briefs: February 25, 2026

Decided: August 25, 2026

Filed:

Clerk

Justice Jim Rice delivered the Opinion of the Court.

¶1 West Development, LLC (West Development) appeals the order entered by the

Eighteenth Judicial District Court, Gallatin County, granting summary judgment to the

Town of West Yellowstone (Town) on West Development’s claims of breach of contract,

negligence, and declaratory relief. We first consider the Town’s cross-appeal:

1. Whether the District Court erred by holding West Development’s claims were

not time-barred under §§ 27-2-209 and 2-3-114(1), MCA.

On appeal, we consider:

2. Whether the District Court erred by granting summary judgment to the Town on

the merits of West Development’s claims.

We affirm all issues.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 Mitchell Simon (Simon), a developer, formed West Development in 2006 to invest,

renovate, and develop properties. In 2006, West Development purchased real property

located in the Town, Gallatin County, Montana, known as Tract 4C of the Madison

Addition, or simply “Tract 4C.”

¶3 West Development applied to the Town for a building permit (Permit) to construct

four condominium buildings, each housing 12 units, or 48 total units on Tract 4C. The

condominium development was to be called Yellowstone Trails Condominiums (YTC).

The Town issued the Permit to West Development for the project on January 2, 2007, the

fee schedule for which consisted of $22,934 for the Permit, $18,375 for sewer, $2,388 for

water meter, $1,225 for water, and $700 for driveway bonds. In a section titled

“Agreement,” the Permit contained the following language:

2

This permit becomes null and void if work or construction authorized is not

commenced within 180 days, or if work is suspended or abandoned for a

period of 180 days at any time after work is commenced.

The undersigned agrees that the proposed work shall be in accordance with

the plans and specifications submitted and in accordance with the provisions

of the Town of West Yellowstone Zoning pertaining to building construction.

¶4 In August 2007, Town Engineer, Winston Dyer, sent a letter to YTC’s engineer

regarding the Town’s provision of services to the property (Will Serve Letter or Letter).

The Letter stated, “I am authorized to certify that the Town of West Yellowstone has the

capacity and will provide requested service to the Yellowstone Trails Condominiums for

water, sewer, and storm drainage,” and clarified that no construction may begin until YTC

also had obtained appropriate permits for building and underground construction from the

Town. The Will Serve Letter did not provide an expiration date or deadline by which

connection to the Town’s system had to be accomplished. West Development also

petitioned and received a Certificate of Subdivision Plat Approval from the Montana

Department of Environmental Quality (DEQ), a later extension of which would continue

the Certificate through 2012.

¶5 West Development began work on Tract 4C in 2007, constructing foundation

footings and walls for two of the buildings and a ramp for a subterranean parking area.

West Development obtained extensions of the Permit from Bill Fogarty (Fogarty), the

Town’s Public Works Superintendent, when weather and other delays were expected to

suspend work for more than 180 days. During times of active construction, Fogarty

inspected the property regularly to ensure ongoing progress. Fogarty’s employment with

the Town terminated in 2011, and the process for permitting commercial building projects

3

in the Town was transferred to the State in September 2011, whereafter applicants for

commercial permits were required to apply to the State.

¶6 Due to the economy and project priorities, West Development ceased construction

activity on the project in 2011. The Permit expired because of 180 days of inactivity with

no request for extension. At that point, for construction to continue on Tract 4C, West

Development needed to reapply to the State for a new permit. In 2011, Simon met with

Mr. Green, then-Town manager, and Mr. Arnado, an employee of the Town. Mr. Arnado

was becoming certified to handle commercial building permits, and when that occurred,

West Development could renew its Permit through the Town and resume work. Simon

preferred to have the Permit reissued by the Town, rather than applying with the State. In

his deposition, Simon stated that he inquired about the status of Arnado’s qualifications

“maybe a couple times a year, couple three times a year, whenever I was down there and

saw him,” through 2016 but, apparently, this certification never occurred. West

Development did not apply to the State for a permit. Thus, the Permit remained expired

since 2011 and construction never resumed. Likewise, DEQ’s approval of the Subdivision

Plat expired in 2012, which would have required a re-application.

¶7 In May 2019, about eight years after construction work ceased, the Town Council

considered and adopted Resolution No. 727 (Resolution). Citing the “dire” need for repair

and upgrades to the wastewater treatment facility, including the necessity of increasing

capacity for the Town’s future needs that may require replacement of the wastewater

system, the Resolution approved what was called a “Moratorium.” The measure limited

new connections to the system. The Resolution stated:

4

The Town Council . . . believes that it is necessary and proper for the Town

to limit the number of new uses or connections to the waste water treatment

system. Complete applications will be evaluated in the order they are

received. Applications must meet all criteria required for a zoning permit

and be evaluated by the Town Engineer according to the current available

capacity in the system. The Town shall have the authority to deny

applications once full capacity in the system has been reached.

(Emphasis added.) New applications advised commercial applicants they were required to

secure other agency approvals, including from DEQ, State Building, and the fire

department, to obtain review of their application, which started with a system capacity

assessment by the Town Engineer, followed by four stages of review that ended with

consideration by the Town Council.

¶8 Before enactment of the Moratorium, then-Town Manager Dan Sabolsky advised

Simon that the Town was adopting a new site approval and permitting process and sent

him documents that would be used in the new application process. West Development was

not directed to file a new application, but took no action in response to these

communications or to the Moratorium, and initiated no further action on Tract 4C,

including obtaining a new building permit from the State.

¶9 However, in April 2020, West Development entered into an agreement (Buy-Sell

Agreement) with Copa Counselling, LLC (Copa) for the sale of Tract 4C. The Buy-Sell

Agreement stated that Copa would pay West Development $1.6 million for Tract 4C,

contingent on West Development “providing evidence that water and sewer fees have been

paid for 48 units and the Town [] will allow [Copa] to hook up to water and sewer upon

completion of construction.” To secure this evidence, Jaymie Bowditch, attorney for West

5

Development, mailed a letter and followed with an email to Town Manager Sabolsky,

about the validity of the 2007 Will Serve Letter, stating that he was

requesting that you confirm in writing, that the rights the Town provided to

[West Development] allowing 48 units to connect the Town’s water and

sewer systems remains valid and vested in [West Development] and that such

rights will be honored upon [West Development’s] transfer of Lot 4C and

that the buyer of Lot 4C, will be allowed to connect 48 units to the Town’s

water and sewer systems upon the completion of the buyer’s project.

Jane Mersen, attorney for the Town, responded to Bowditch’s email, stating:

[T]he Town will agree that Lot 4C paid to hook up 48 units. The “will serve”

letter is 14 years old and clearly no longer effective given the growth in West

and the problems with the current Wastewater system. Further, the hook-up

fees have increased substantially since 2007. However, the Town will allow

Lot 4C to hook up to 48 units when the Town’s wastewater system has

capacity. We expect that date to be 2023. We hope it is sooner but we cannot

guarantee it.

Please note that once Lot 4C is given the authority to hook up, that authority

will only be good for one year, unless an extension is requested by the Lot

owner and granted by the Town before the end of the one year time period.

The Town will no longer allows permits or will serve letters to linger

indefinitely.

¶10 Because the Town would not presently guarantee 48 sewer hookups for Tract 4C,

Copa terminated the Buy-Sell Agreement on June 30, 2020. West Development filed the

complaint against the Town in October 2020, alleging: breach of contract to connect the

project to Town services; negligent breach of duty in the management of its wastewater

system by failing to maintain a sufficient number of connections to accommodate West

Development’s Will Serve Letter; and entitlement to a declaratory judgment that the Will

Serve Letter was an enforceable promise to which the Town impermissibly applied the law

retroactively and the taking of a vested right. Denying all of the claims, the Town framed

6

the claims as challenging the validity of the Moratorium and thus were untimely filed either

under the 30-day period in § 2-3-114(1), MCA, governing public participation, or the

six-month period in § 27-2-209(5), MCA, governing actions against a municipality

concerning a land use or development project, and that the claims were barred by laches,

given that West Development had waited nine years after construction ceased before

bringing the suit.

¶11 After discovery, both parties moved for summary judgment. The District Court first

concluded that the claims were not time-barred, reasoning that West Development was “not

challenging the Town’s issuance of the Resolution itself,” and therefore the statutory

periods of limitation raised by the Town were inapplicable. It further concluded the

doctrine of laches did not apply because West Development’s claims did not accrue until

2020, when the Town first indicated its refusal to provide current wastewater connections

pending completion of system improvements, and that West Development had proceeded

to file suit by October 2020.1 However, the District Court granted summary judgment in

favor of the Town on the merits of the claims. The court “conclude[d] that the language of

the Will Serve Letter was insufficient to create a valid and enforceable contract” or an

enforceable promise, noting that the Town has not refused to provide services, but merely

delayed the connections until facility upgrades are completed. For that same reason, the

court concluded that no vested had right been taken. Regarding the negligence claim, the

District Court reasoned that the Will Serve Letter provided no express assurance and it was

1

The District Court’s laches ruling is not challenged on appeal by the Town.

7

not reasonable to expect the Will Serve Letter “would be available in perpetuity,” such that

the Town had breached a duty, and that, in any event, the Town did not owe a duty to West

Development under the special relationship exception to the public duty doctrine.

¶12 West Development appeals the denial of its claims, and the Town cross-appeals the

denial of its defense that the claims were statutorily time-barred.

STANDARD OF REVIEW

¶13 “We review a district court’s ruling on motions for summary judgment de novo,

using the same M. R. Civ. P. 56 (Rule 56) criteria used by the district court.” Chapman v.

Maxwell, 2014 MT 35, ¶ 7, 374 Mont. 12, 322 P.3d 1029 (citation omitted).

¶14 “Both the existence of a contract and its interpretation are questions of law which

we review for correctness.” Hurly v. Lake Cabin Dev., LLC, 2012 MT 77, ¶ 14, 364 Mont.

425, 276 P.3d 854 (citation omitted). “Our standard of review pertaining to a declaratory

judgment is to determine if the court’s interpretation of law is correct.” Roe v. City of

Missoula, 2009 MT 417, ¶ 15, 354 Mont. 1, 221 P.3d 1200 (citation omitted).

DISCUSSION

¶15 1. Whether the District Court erred by holding West Development’s claims were

not time-barred under §§ 27-2-209 and 2-3-114(1), MCA.

¶16 We first take up the Town’s cross-appeal, presenting the threshold issue of whether

West Development’s claims are time-barred. The Town argues the claims are untimely

under § 2-3-114(1), MCA, and § 27-2-209(5), MCA, “[b]ecause West Development’s

claims distill down to a challenge of the Resolution imposing the Moratorium.” The Town

contends that “at the core of each of West Development’s claims is the contention that the

8

Town should have specifically ‘reserved’ the ‘48’ water and sewer connections for it as

part of the Resolution/Moratorium and not made West Development subject to the

Moratorium,” and that, “if the Town had not passed the Resolution/Moratorium there

would be no reason the Town would need to ‘reserve 48 connections’ from the ‘remaining

sewer capacity.’” West Development answers that its Complaint did not ask for the

Resolution or Moratorium to be set aside, particularly on the ground “it was denied notice

or participation in a public meeting or other agency operation,” under the public

participation statutes. See § 2-3-114(1), MCA (a person “whose rights have been

prejudiced[]” by an agency’s decision made without opportunity for public participation

has 30 days after learning of the decision to file an action in the district court). West

Development further argues it “had no reason to challenge Resolution 727” in this action,

because the Resolution did not mandate that West Development “re-apply for the sewer

connections it had already purchased” for the project, and that its contention was that “the

Town was required to reserve sewer capacity for the [YTC] in 2007, years before the

passage of Resolution 727.” (Emphasis in original.)

¶17 We agree with West Development’s arguments. Its Complaint did not challenge the

Resolution on the ground that West Development’s right to participate in the public process

was violated, such that § 2-3-114(1), MCA, would be applicable. Nor did West

Development otherwise challenge the legality of the Resolution or the Moratorium and

seek a declaration of invalidity. To the extent West Development’s arguments could

implicate the Resolution, such as by explaining the Town’s new approach to service

connections, it is clear the claims went beyond the Resolution’s passage, asserting

9

entitlement to rights West Development held since 2007, regardless of the Resolution. The

Town argues that if the Resolution had not been passed, there would be no reason to

“reserve” 48 hookups, but in that event West Development would still be claiming

entitlement to 48 hookups that the Town contended it lacked capacity to presently provide.

We conclude the District Court correctly held West Development’s claims were timely

filed.

¶18 2. Whether the District Court erred by granting summary judgment to the Town on

the merits of West Development’s claims.

¶19 At the factual center of this dispute, and of each of West Development’s claims, is

the undisputed fact of the extraordinary amount of time that passed after the Town issued

the Will Serve Letter to West Development in August 2007, until this dispute arose in 2020.

West Development’s policy arguments, that “developers must be able to rely on and

enforce the promises made by municipalities in will-serve letters when investing time and

resources in development projects,” and that “[w]ill-serve letters cannot relate only to a

municipality’s current ability to provide sewer services if they are to serve their intended

purpose; will-serve letters must relate to a municipality’s future ability to provide sewer

services with the recipients of the letters finish their projects and are ready to connect to

the sewer system, which a municipality ensures by reserving capacity . . . ” (emphasis in

original), are well-founded in theory, but they fail to capture the record here, and to address

the consequence of a developer who receives a will-serve letter, starts a project, but then

ceases all work and permitting efforts on the project for many years. Based on the Will

Serve Letter, West Development started construction in 2007, then ceased work in 2011,

10

and has done nothing on the property since. The import of West Development’s argument

is that it was entitled to sit on the Will Serve Letter indefinitely, if not infinitely. The

District Court described West Development’s view of the Letter as a “guarantee of eternal

availability” and “available in perpetuity.”

¶20 The parties argue about whether the Will Serve Letter was sufficient to constitute a

contract, but even assuming arguendo that it did, a contract that does not provide a time of

performance is allotted a reasonable time. See § 28-3-601, MCA (“If no time is specified

for the performance of an act required to be performed, a reasonable time is allowed,”

unless the act is one that must be performed immediately.). We have held that “[a]

reasonable time usually allows as much time as necessary, under the circumstances, to do

conveniently what the contract requires.” Summer Night Oil Co., LLC v. Munoz, 2011 MT

202, ¶ 26, 361 Mont. 424, 259 P.3d 778 (citing Dambrowski v. Champion Int’l. Corp.,

2003 MT 233, ¶ 13, 317 Mont. 218, 76 P.3d 1080). Whether a time is reasonable, “hinges

upon the underlying factual circumstances, which, in turn vary from case to case.”

Dambrowski, ¶ 14.

¶21 We conclude that the 13 years which elapsed from issuance of the Will Serve Letter

until the attempted sale of the property to Copa, encompassing the 9 years that passed after

West Development ceased construction and allowed its related building permits to expire,

exceeded “a reasonable time” in which to perform its obligations. Summer Night Oil Co.,

¶ 26. The Will Serve Letter required the owner to obtain appropriate permits for the project,

but here, those project conditions expired and were not being met, as West Development

allowed the building permits to expire in 2011, and have been expired ever since. Under

11

these circumstances, it would be unreasonable to require the Town to guarantee on-demand

service for a project’s 48 hookups after the years of inactivity and the continuous lack of

permitting for the project.2

¶22 The District Court reasoned that failure of the breach of contract claim also

undermined the claim that the Letter was an “enforceable promise” for which West

Development had obtained vested rights, but that, in any event, West Development’s

argument that “the Town’s refusal to provide services is an impermissible retroactive

application of the law and taking of a vested right” was not supported by the record because

“the Town has not refused to provide the services at issue.”

¶23 While the District Court was technically correct that the Town did not permanently

refuse to provide the service connections, the Town did refuse in 2020 to guarantee a

current connection as stated by the 2013 Will Serve Letter. Mersen acknowledged that

West Development had paid to hook up 48 units and advised that “the Town will allow Lot

4C to hook up 48 units when the Town’s wastewater system has capacity,” which the Town

expected to be sooner rather than later, and thus was noncommittal about the timing.

Nonetheless, as explained above, by 2020 any project-specific commitment by the Town

had expired as exceeding a reasonable time.

¶24 Regarding its negligence claim, West Development argues the District Court erred

by failing to apply the “specific duty” exception to the public duty doctrine because of the

2

Counsel Mersen’s June 2020 letter advised that, going forward, the Town’s will-serve letters would be valid for one year, subject to extensions, and that they would not be allowed “to linger indefinitely.”

12

“special relationship” that existed between the parties, as there had been express assurances

made by local officials upon which West Development justifiably relied. Kent v. City of

Columbia Falls, 2015 MT 139, ¶ 24, 379 Mont. 190, 350 P.3d 9. We recently explained

that the public duty doctrine “serves the important interest of preventing the court’s

interference with the exercise and administration of governmental processes that benefit

the community as a whole.” Sara Da’ v. City of Bozeman, 2026 MT 164, ¶ 15, ___ Mont.

___, ___ P.3d ___ (citing Kent, ¶ 23). The public duty doctrine “is properly applied to

cases in which the governmental defendant owed no duty to the individual plaintiff because

the duty is owed to the public generally.” Sara Da’, ¶ 15 (citation omitted).

¶25 When the public duty doctrine applies, “the government defendant owes no duty to

a claimant unless a ‘special duty’ arises under one of four circumstances . . . ,” including

that the government’s actions “have induced a detrimental reliance by a member of the

public.” Sara Da’, ¶ 16. The District Court summarized West Development’s position on

this issue as follows:

West Development asserts it was reasonably induced to rely on the Will

Serve Letter issued by the Town which then created a special duty on the part

of the Town to maintain its sewer system, track the capacity remaining in the

system and properly allocate the remaining sewer capacity, apparently for as

long as Tract C potentially could be developed as planned . . . without regard

to whether West Development was actively working on the construction, had

the necessary permits for the project in place, or the amount of time which

elapsed between issuance of the Letter and West Development’s inquiry into

whether the 48 connections would be available.

¶26 West Development’s claimed economic injury arises from the Town’s alleged

failure to reserve and allocate municipal wastewater capacity among development projects,

which involve the administration and allocation of public infrastructure for the community

13

generally. Even so, the question returns to how long the duty would remain. Notably, the

Will Serve Letter stated in 2007 that the Town “has the capacity and will provide requested

service” to the project but, as reasoned by the District Court, the Letter “contained no

express assurances regarding the length of its validity” or that “connections would be

available in perpetuity,” or, in this case, after passage of 13 years, during which the project

went completely dormant, with West Development discontinuing construction efforts after

2011 and allowing its permits to expire.

¶27 We concur with the District Court’s summary judgment in favor of the Town on the

merits of West Development’s claims.

¶28 Affirmed.

/S/ JIM RICE

We Concur:

/S/ LAURIE McKINNON

/S/ KATHERINE M. BIDEGARAY

/S/ JAMES JEREMIAH SHEA

/S/ INGRID GUSTAFSON

14