United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued March 24, 2026 Decided August 25, 2026
No. 24-1291
FOR A BETTER BAYOU, ET AL.,
PETITIONERS
v.
FEDERAL ENERGY REGULATORY COMMISSION,
RESPONDENT
VENTURE GLOBAL CP EXPRESS, LLC AND VENTURE GLOBAL
CP2 LNG, LLC,
INTERVENORS
Consolidated with 24-1292, 25-1157
On Petitions for Review of Orders of the
Federal Energy Regulatory Commission
Nathan Matthews argued the cause for petitioners. With
him on the joint briefs were Megan Gibson, Spencer T. Gall,
Clara Derby, Caroline Reiser, Thomas Zimpleman, Gillian
Giannetti, and Rebecca McCreary.
2
Scott R. Ediger, Attorney Advisor, Federal Energy
Regulatory Commission, argued the cause for respondent.
With him on the brief was Robert H. Solomon, Solicitor.
Susanna Y. Chu, Senior Attorney, entered an appearance.
Eric Konopka argued the cause for intervenors in support
of respondent. With him on the brief were Gregory G. Garre,
Joel P. Nevins, Peter Prindiville, Halle H. Edwards, and
Sandra Snyder.
Before: HENDERSON and MILLETT, Circuit Judges, and
GINSBURG, Senior Circuit Judge.
Opinion for the Court filed by Senior Circuit Judge
GINSBURG.
3
I. Background ...................................................................... 4
A. Relevant Statutes ...................................................... 4
B. Commission Proceedings ......................................... 9 II. Analysis ......................................................................... 11
A. Challenges under the NGA ..................................... 12
1. The Commission’s interpretation of the
NGA ................................................................ 13
2. The Commission’s application of the NGA .... 17
a. The project’s harms .................................. 17
b. The Terminal’s benefits ........................... 19
c. The authorization of the Pipeline ............. 20
B. Challenges under the NEPA ................................... 23
1. The Terminal’s cumulative effects .................. 23
a. New model ............................................... 24
b. Magnolia Terminal. .................................. 25
c. Marine vessels serving other terminals
.................................................................. 27
2. The Commission’s use of NAAQS in the
cumulative effects analysis.............................. 30
3. The Moss Lake Compressor Station’s
cumulative effects ........................................... 33
4. The harm to the commercial fishing
industry ............................................................ 37
a. Temporary harm................................... 37
b. Localized harm..................................... 38
III. Conclusion ..................................................................... 41
4
GINSBURG, Senior Circuit Judge: In December 2021
Venture Global CP2 LNG and Venture Global CP Express, the
Intervenors here, sought authorization from the Federal Energy
Regulatory Commission for the siting, construction, and operation of a terminal and pipeline for the exportation of liquefied natural gas (LNG). A long review process followed, resulting
in two environmental impact statements, an initial authorization order, three rehearing orders and, in 2025, the FERC’s
approval of the project.
The petitioners are individuals and advocacy groups seeking review of those orders. Leaving no stone unturned, they
improbably allege the Commission committed no fewer than
eleven errors under the Natural Gas Act (NGA) and the
National Environmental Policy Act (NEPA). Because these
arguments lack merit, we deny the petitions for review.
I. Background
This appeal implicates not only the NGA and the NEPA,
but also the Clean Air Act (CAA). We begin by discussing the
relevant provisions of these laws before turning to the procedural history of the case.
A. Relevant Statutes
The NGA regulates “the business of transporting and
selling natural gas for ultimate distribution to the public.”
15 U.S.C. § 717(a). It prohibits the export of natural gas by any entity “without first having secured an order of the
Commission authorizing it to do so.” § 717b(a). A party must
also obtain prior authorization before constructing a natural gas terminal or a pipeline. See Big Bend Conservation All. v.
FERC, 896 F.3d 418, 420 (D.C. Cir. 2018).
5
The United States Department of Energy (DOE) has delegated authority to the FERC to “[a]pprove or disapprove” the
siting, construction, and operation of particular facilities used to export natural gas, including LNG terminals. DOE,
Delegation Order No. S1-DEL-FERC-2006, § 1.21A (2006);
see § 717b(e)(1); see also § 717a(11) (defining “LNG
terminal”). 1 The Congress has laid down different standards for
the approval of an LNG export terminal than it has for the
approval of a pipeline used to transport natural gas. Under
Section 3 of the NGA the FERC “shall issue” an order authorizing an LNG export terminal “unless” it finds the terminal
“will not be consistent with the public interest.” § 717b(a). By
contrast, under Section 7 the FERC may not authorize the construction and operation of a pipeline unless it determines the
pipeline “is or will be required by the present or future public
convenience and necessity.” § 717f(e).
Although the FERC exercises authority over the approval
of LNG terminals, the DOE has “retained for itself the
authority to authorize exports . . . of natural gas.” Sierra Club v. DOE (Alaska Gasline), 134 F.4th 568, 570 n.2 (D.C. Cir.
2025). Any exportation of gas to a country with which the
United States has “a free trade agreement requiring national
treatment for trade in natural gas[] shall be deemed to be
consistent with the public interest, and applications for
such . . . exportation shall be granted without modification or
delay.” § 717b(c).
The FERC follows its longstanding Certificate Policy
Statement when it reviews an application for the construction
1
“Commission” as used in the NGA refers to the Federal Power
Commission, § 717a(9), the predecessor to the FERC. In 1977 the
Congress “transferred to” the Secretary of Energy “the function of the Federal Power Commission.” 42 U.S.C. § 7151(b), who as just
mentioned, has delegated some of those functions to the FERC.
6
of a pipeline. See Certification of New Interstate Nat. Gas
Pipeline Facilities, 88 FERC 61227 (1999), clarified, 90 FERC
61128 (2000), further clarified, 92 FERC 61094 (2000). The
Commission first considers whether there is a “market need”
for the project by asking whether it can proceed without subsidies from the applicant’s existing customers. Env’t Def. Fund
v. FERC, 2 F.4th 953, 961 (D.C. Cir. 2021). If it finds there is
a market need for the pipeline, then the FERC determines
whether the pipeline will have an adverse effect on the applicant’s existing customers, pipelines in the same market and
their captive customers, or landowners and communities surrounding the project. Id. If the pipeline will cause an adverse
effect, then the FERC balances that effect against the pipeline’s public benefits. Id. In doing so, the Commission will “consider
all relevant factors reflecting on the need for the project.” Id.
Under the NEPA, the FERC must prepare an
environmental impact statement (EIS) if it determines that the
approval of a terminal or pipeline would constitute a “major
federal action[] significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C); see § 4336(b)(1). The
NEPA, however, “imposes no substantive environmental
obligations or restrictions.” Seven Cnty. Infrastructure Coal. v. Eagle Cnty., 605 U.S. 168, 173 (2025). It is “a purely
procedural statute that, as relevant here, simply requires an
agency to prepare an EIS — in essence, a report.” Id. The
NEPA does not require the Commission “to weigh
environmental consequences in any particular way. Rather, an
agency may weigh environmental consequences as the agency
reasonably sees fit under its governing statute and any relevant
substantive environmental laws.” Id. “The goal of the law is to
inform agency decisionmaking, not to paralyze it.” Id.
Still, the FERC must “look hard at the environmental
effects” of the action. Sierra Club v. FERC (Cumberland),
7
153 F.4th 1295, 1303 (D.C. Cir. 2025). Accordingly, an EIS
must consider the “reasonably foreseeable environmental
effects of the proposed agency action,” including any adverse
effects “which cannot be avoided should the proposal be
implemented.” § 4332(2)(C)(i)-(ii).
Under regulations in effect at the time of the proceedings
here under review, the FERC would consider the cumulative
environmental effects of a proposed project as part of its NEPA
analysis. See 40 C.F.R. § 1508.1(g)(3) (2023); see also 90 Fed.
Reg. 10610, 10611 (2025) (final rule promulgated by the
Council on Environmental Quality repealing the regulations
implementing the NEPA, including § 1508). The FERC
defined cumulative effects as “the incremental effects of the
action when added to the effects of other past, present, and
reasonably foreseeable actions.” § 1508.1(g)(3).
Two standards set by the Environmental Protection
Agency are relevant to the FERC’s analysis of cumulative
effects on air quality. First, the EPA has identified significant impact levels (SILs) for certain air pollutants, “below which
the EPA considers [the] source to have an insignificant effect
on ambient air quality.” Sierra Club v. EPA, 705 F.3d 458, 461
(D.C. Cir. 2013); see May 2025 Rehearing Order, 191 FERC
61153, ¶ 5 n.25 (discussing EPA guidance documents on the
SILs for, as relevant here, NO2 and PM2.5). Second, the CAA
requires the EPA to set national ambient air quality standards
(NAAQS) for each air pollutant for which the EPA has issued
air quality criteria. See 42 U.S.C. § 7409(a). The EPA must set
primary NAAQS at a level “requisite to protect the public
health” with “an adequate margin of safety.” § 7409(b). The
CAA prohibits the construction of a “major emitting facility”
unless the applicant demonstrates the facility “will not cause,
or contribute to, air pollution in excess of” any NAAQS.
§ 7475(a)(3). The EPA has delegated authority to enforce this
8
provision to state agencies, here the Louisiana Department of
Environmental Quality (the LDEQ).
When analyzing the cumulative effects of a proposed project on air quality, the FERC applied a three-step framework in
accordance with EPA guidelines for evaluating a project’s
emissions:
1. Preliminary screening: The FERC first
compares the project’s predicted emissions to the SILs for those emissions. If
the FERC predicts the emissions will
fall below the SILs, then the emissions
are “insignificant” and the FERC’s
analysis is at an end.
2. Cumulative effects: If the FERC
predicts the emissions will exceed a
relevant SIL, then the FERC adds the
emissions from the source under review
to those from sources already existing in
the area and compares the cumulative
emissions to the NAAQS. In doing so,
the FERC may rely upon an emissions
inventory maintained by a state agency
such as the LDEQ. If the cumulative
effects of the emissions do not exceed
the NAAQS, then the FERC ends its
analysis.
3. Cause and contribution: If the
predicted cumulative emissions will
exceed a NAAQS, then the FERC considers whether the predicted SIL
exceedance and the predicted NAAQS
exceedance will occur simultaneously at
9
the same receptor. If it will not, then the
project is deemed to “not cause or
contribute to the potential NAAQS
exceedance.”
May 2025 Rehearing Order, 191 FERC ¶¶ 5-6 (citing 40 C.F.R.
pt. 51, app. W).
B. Commission Proceedings
In December 2021 the Intervenors sought the FERC’s
authorization for the siting, construction, and operation of a
new LNG terminal on the Calcasieu Ship Channel in Cameron
Parish, Louisiana and of a natural gas pipeline running 85 miles
from East Texas to the Terminal. The Pipeline will also include
the Moss Lake Compressor Station.
In July 2023 FERC staff completed the EIS, which ran
more than 600 pages plus appendices. 2 The EIS predicted the
project would cause some adverse environmental effects and
recommended more than 100 measures to reduce those effects.
As for the cumulative effects analysis of the Terminal and the
Compressor Station, the EIS predicted there would be exceedances of the SILs and NAAQS for PM2.5 and NO2, but it
concluded that those exceedances would not occur
simultaneously and the project therefore would not cause or
contribute to any NAAQS exceedances. The EIS also concluded that the project would not cause significant harm to the
commercial fishing industry.
In June 2024 the FERC issued an order authorizing the
Terminal and the Pipeline. 187 FERC 61199, ¶¶ 199-200. For
2
The Congress has since imposed a general 150-page limit for an
EIS and a 300-page limit for an EIS “for a proposed agency action of extraordinary complexity.” 42 U.S.C. § 4336a(e)(1).
10
a Better Bayou, other advocacy groups, and several individuals
(together, Bayou), filed a request for rehearing, which the
FERC granted in part. November 2024 Rehearing Order, 189
FERC 61148, ¶ 2. Out of concern that our decisions in Healthy
Gulf v. FERC, 107 F.4th 1033 (2024), and City of Port Isabel
v. FERC, 111 F.4th 1198 (2024), may have undermined part of
its cumulative effects analysis, the FERC set aside its analysis
of the project’s NO2 and PM2.5 emissions and ordered an additional environmental review. Id. ¶ 185. The FERC also said it
would address “other air quality issues raised by” Bayou in a
future order; it otherwise rejected Bayou’s arguments. Id.
In May 2025 FERC staff issued the Supplemental EIS
(SEIS). Unlike the original EIS, which had predicted SIL and
NAAQS exceedances for the Terminal and the Compressor
Station, the SEIS predicted no NAAQS exceedances for the
Terminal and no SIL exceedances for the Compressor Station.
The SEIS accordingly ended its cumulative effects analysis at
step one for the Compressor Station and at step two for the
Terminal, concluding that “there would be no significant
cumulative air quality impacts.”
Two weeks later the FERC issued an order again authorizing the Terminal and the Pipeline, based upon the conclusions
in the EIS and the SEIS. May 2025 Rehearing Order, 191
FERC ¶¶ 92-93. Bayou filed another request for rehearing,
which the Commission denied. August 2025 Rehearing Order,
192 FERC 61157, ¶ 2.
After the Initial Authorization Order issued in June 2024,
the FERC had authorized limited construction activities. Bayou
sought a stay of those activities, which was twice denied by the
FERC and by this court.
11
II. Analysis
We have jurisdiction over Bayou’s petitions for review
under 15 U.S.C. § 717r(b). 3 Insofar as Bayou’s challenges raise
questions of statutory interpretation, our review is de novo. See Loper Bright Enters. v. Raimondo, 603 U.S. 369, 412-13
3
Bayou filed its first petition for review in September 2024 — after its request for rehearing had been denied by operation of law but before the Commission set aside part of its order in the November 2024 Rehearing Order. A request for rehearing will be denied by
operation of law if the Commission does not act on it within thirty days, but the Commission may still modify or set aside the initial order until “the record in [the] proceeding shall have been filed in a court of appeals.” § 717r(a). One month after the Commission issued the November 2024 Rehearing Order, Bayou filed a motion to clarify whether the November 2024 Rehearing Order was encompassed by
its existing petition for review and, if necessary, to amend its petition to seek review of that order.
We dismiss that motion as moot. After Bayou filed the motion, the FERC issued the May 2025 Rehearing Order that modified the
Commission’s discussion in the first two orders and addressed
Bayou’s “original claims on rehearing of the Authorization order
regarding air quality.” 189 FERC ¶ 2. After the Commission denied Bayou’s request for rehearing of the May 2025 Rehearing Order,
Bayou filed a petition seeking review of the November 2024 and the May 2025 Rehearing Orders. Based upon those subsequent events,
we have no reason to decide precisely which orders were covered by Bayou’s initial petition for review.
We have Article III jurisdiction. Bayou has associational standing on behalf of its members who reside and fish near the project. Because “at least one [petitioner] has standing,” we “may proceed” to the merits of its petitions. Biden v. Nebraska, 600 U.S. 477, 489 (2023); see also Horne v. Flores, 557 U.S. 433, 446-47 (2009); Woodhull
Freedom Found. v. United States, 948 F.3d 363, 371 (D.C. Cir.
2020).
12
(2024). We review the FERC’s exercise of its discretion under
the NGA and its NEPA analysis under the familiar arbitraryand-capricious standard of the Administrative Procedure Act.
See Vecinos para el Bienestar de la Comunidad Costera v.
FERC, 6 F.4th 1321, 1327, 1331 (D.C. Cir. 2021). We will set
aside the Commission’s action if it “has relied on factors which
Congress has not intended it to consider, entirely failed to
consider an important aspect of the problem, offered an
explanation for its decision that runs counter to the evidence
before [it],” or has reached a result that “is so implausible that it could not be ascribed to a difference in view or the product
of agency expertise.” Motor Vehicle Mfrs. Ass’n of U.S., Inc. v.
State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983); see
Cumberland, 153 F.4th at 1305 (“We review FERC’s public
convenience and necessity determination for whether it was
based on a consideration of the relevant factors and whether
there has been a clear error of judgment” (cleaned up)). Under
the NGA, “the finding of the Commission as to the facts, if
supported by substantial evidence, shall be conclusive.”
§ 717r(b).
A. Challenges under the NGA
Bayou first challenges the FERC’s authorization of the
Terminal and the Pipeline under the NGA. To reiterate: Under
Section 3 of that Act, the Commission “shall” authorize a terminal “unless” it finds the terminal “will not be consistent with the public interest.” § 717b(a); under Section 7, the
Commission will authorize a pipeline only if it determines the
pipeline “is or will be required by the present or future public
convenience and necessity.” § 717f(e). “Section 3 is in this
respect the reverse of [Section 7].” Panhandle Producers &
Royalty Owners Ass’n v. Econ. Regul. Admin., 822 F.2d 1105,
1111 (D.C. Cir. 1987). Whereas Section 3 “requires an
affirmative showing of inconsistency with the public interest to
13
deny an application,” Section 7 “requires an affirmative
showing of public convenience and necessity to grant one.” Id.;
see also Vecinos, 6 F.4th at 1326 (similar).
Bayou argues that the Commission’s interpretation of
Section 3 was arbitrary and unlawful and that its application of
both Section 3 and Section 7 was arbitrary and capricious.
These arguments all lack merit.
1. The Commission’s interpretation of the NGA
In its first rehearing request, Bayou argued that the
Commission had failed to explain how it balanced the
Terminal’s benefits against its harms to determine whether the
Terminal would be inconsistent with the public interest. The
Commission responded in the November 2024 Rehearing
Order that Bayou’s balancing argument was “misplaced”
because “section 3 of the NGA does not charge the
Commission with demonstrating that the benefits of a proposal
outweigh its potential harms.” 189 FERC ¶ 41 (quoting Alaska
Gasline Dev. Corp., 172 FERC 61214, ¶ 16 (2020)). Later in
that order the Commission reiterated that it “does not weigh the
public benefits against potential harms in its NGA section 3
public interest determination.” Id. ¶ 158 n.647.
Bayou says this was wrong for several reasons. First, the
Commission’s position is not the “best” interpretation of
Section 3. Second, the Commission offered no explanation as
to the standard it applies under Section 3. Third, the
Commission had previously engaged in balancing under
Section 3, but it departed from its precedents without any
explanation. The Commission responds that these arguments
are foreclosed by our precedent or not properly before us. We
agree with the Commission.
14
We start, as usual, with the text of the statute: As we have
said, the Commission “shall” authorize the construction and
operation of a terminal “unless” doing so “will not be
consistent with the public interest.” § 717b(a). This statute is
“not neutral” but rather demonstrates a clear congressional
preference for authorization. Alaska Gasline, 134 F.4th at 572.
Consequently, we have long held that Section 3 establishes a
“presumption” in favor of authorization. See, e.g., Sierra Club
v. FERC (Saguaro), 145 F.4th 74, 87 (2025); Alaska Gasline,
134 F.4th at 572-73; Ctr. for Biological Diversity v. FERC, 67
F.4th 1176, 1188 (2023); Sierra Club v. DOE (Freeport), 867
F.3d 189, 203 (2017); EarthReports, Inc. v. FERC, 828 F.3d
949, 953 (2016); W. Va. Pub. Servs. Comm’n v. DOE, 681 F.2d
847, 856 (1982).
This long-standing presumption conflicts with Bayou’s
attempt to read Section 3 as imposing a balancing requirement
on the Commission. As the Intervenors explain, an ordinary
balancing test would require the Commission to start its review
from “equipoise,” with “the scales tip[ping] in favor of a
particular outcome” based upon the evidence presented. Not so
here. The Commission begins its review from the position that
it will — indeed, that it must — authorize a terminal unless the
presumption is rebutted.
Bayou acknowledges this presumption but says it rebutted
it by producing some evidence of harm, at which point the
Commission needed to balance that evidence against the
Terminal’s benefits. If the presumption were that easy to dispel, then it is hard to imagine a case in which an opponent
would fail to do so. Unsurprisingly then, our case law provides
a different answer: The petitioner must “show, affirmatively,
that approving the [terminal] is inconsistent with the public
interest.” Saguaro, 145 F.4th at 87. Satisfying that standard
requires a petitioner to do more than simply produce some
15
evidence of harm. See, e.g., Freeport, 867 F.3d at 203 (holding
the petitioner “fail[ed] to overcome the presumption in favor of
exports” even assuming the environmental effects of the
exports were “significant”); Saguaro, 145 F.4th at 87 (rejecting
argument that the Commission “treated adverse impacts versus
benefits inconsistently” and reaffirming its reliance upon the
presumption in favor of authorization). 4
Bayou next argues the Commission did not offer an
adequate explanation of what Section 3 requires. It characterizes the Commission’s approach to reviewing a terminal for
inconsistency with the public interest as meaning “we’ll know
it when we see it.” We disagree. Relying upon our precedent,
the Commission cited the presumption in favor of authorization
and explained that Bayou bore the burden of making an
“affirmative showing” that the Terminal would be inconsistent
with the public interest. Initial Authorization Order, 187 FERC
¶ 23; November 2024 Rehearing Order, 189 FERC ¶ 36. It then
4
After entirely ignoring Saguaro in its opening brief, Bayou argues in its reply brief that requiring it “not only to produce evidence of harm, but to prove themselves that the Terminal was inconsistent
with the public interest” is “unsupported.” To make that argument Bayou attempts to rewrite our precedent, claiming Saguaro did not establish that a petitioner’s burden “entails anything more than
producing evidence of harm” because the petitioners in that case did not produce any evidence of direct harm. Saguaro did not, however, even mention a lack of evidence of direct harm when discussing the petitioners’ burden. The petitioners argued that the Commission had “asymmetrically considered benefits downstream of the [proposed
facility] while dismissing adverse impacts upstream.” 145 F.4th at 87. In response, we said the petitioner needed to make “an
affirmative showing of inconsistency with the public interest” and affirmed the Commission’s reliance upon the presumption in favor
of authorization. Id. To the same effect, see Freeport, 867 F.3d at 203. Bayou makes no attempt to distinguish our discussion of this burden in Freeport.
16
discussed specific benefits and harms it had considered and
concluded that Bayou had not satisfied its burden. See below at
18-20; Initial Authorization Order, 187 FERC ¶¶ 23-32;
November 2024 Rehearing Order, 189 FERC ¶¶ 37-46.
Insofar as Bayou seeks something akin to a bright-line rule
for when a terminal will be inconsistent with the public interest, it is out of luck. Whether a terminal will be inconsistent with
the public interest is a fact-bound inquiry that does not easily
lend itself to bright-line rules. This does not mean the
Commission’s discretion is limitless; as relevant here, its
orders must still be “reasonable and reasonably explained, and
its factual findings must be supported by substantial evidence.”
Saguaro, 145 F.4th at 80 (cleaned up); see § 717r(b). Those
requirements have been applied by this court on many occasions and provide a sufficient standard against which to review
the Commission’s orders. See, e.g., Vecinos, 6 F.4th at 1331;
Wash. Gas Light Co. v. FERC, 532 F.3d 928, 932-33 (2008).
The FERC was required to provide an explanation that was
“clear enough that its path may reasonably be discerned,”
Encino Motorcars, LLC v. Navarro, 579 U.S. 211, 221 (2016)
(cleaned up), which it did here.
That leaves Bayou with its argument that the Commission
departed from its own precedent without explaining its decision
to do so. We do not reach this argument because, as the
Commission and the Intervenors point out, Bayou did not raise
this argument to the Commission. See § 717r(b) (“No objection
to the order of the Commission shall be considered by the court
unless such objection shall have been urged before the
Commission in the application for rehearing unless there is
reasonable ground for [the] failure so to do”). Although Bayou
argued the Commission was required to engage in balancing, it
did not argue that the Commission’s own precedent required it
to do so. See Port Isabel, 111 F.4th at 1217-18 (holding that
17
§ 717r(b) prevents courts from considering “specific arguments” that were not raised to the Commission on rehearing).
Bayou argues it had a reasonable ground for not raising
this argument earlier, namely, that the Commission had not disclaimed a balancing approach under Section 3 until the
November 2024 Rehearing Order. But that is not correct. In an
order issued nearly four years before the Initial Authorization
Order in this case, the Commission stated that “section 3 of the
NGA does not charge the Commission with demonstrating that
the benefits of a proposal outweigh its potential harms.” Alaska
Gasline Dev. Corp., 172 FERC ¶ 16. Although Bayou contends
other sections of that order suggest the Commission did in fact
engage in balancing, the order nonetheless put Bayou on notice
that the Commission took a contrary position as to what Section
3 required.
In sum, the Commission’s interpretation of Section 3 was
neither unlawful nor arbitrary.
2. The Commission’s application of the NGA
Bayou next argues that the Commission’s application of
the NGA was unlawful and arbitrary in three ways: The
Commission incorrectly dismissed the project’s harms as insignificant or inconsequential; failed to explain how the
Terminal’s benefits would outweigh its harms; and did not
meaningfully balance the Pipeline’s benefits and harms
because it placed undue weight on a precedent agreement
between the Intervenors.
a. The project’s harms
Bayou claims the Commission failed to give proper weight
to the evidence of the Terminal’s harms or to explain its reasons for discounting them. In Bayou’s view, the FERC did not
18
take a “hard look” at the project’s effects on air quality, commercial fishing, or climate change.
Bayou’s arguments regarding air quality and commercial
fishing overlap substantially with its NEPA claims, to the merits of which we turn below. Because its NEPA claims fail, so
too do these arguments. See Ctr. for Biological Diversity,
67 F.4th at 1188 (holding that a petitioners’ meritless NEPA
challenges “fare[d] no better when framed as NGA
challenges”).
Bayou’s argument that the Commission simply dismissed
the project’s contributions to climate change is without merit.
The Commission cited the project’s estimated greenhouse gas
emissions and the social cost of those emissions, Initial
Authorization Order, 187 FERC ¶¶ 165, 168; compared the
project’s greenhouse gas emissions to the existing national and
state levels, id. ¶¶ 171-73; and approved mitigation measures
proposed by the Intervenors, which responded to recommendations made by the EPA, id. ¶¶ 176-77. The Commission also
explained that it would not characterize the project’s emissions
as significant or insignificant because “there currently are no
accepted tools or methods for [it] to use to determine
significance,” but it had still “taken the required ‘hard look’”
at the evidence. Id. ¶¶ 179-80; see also November 2024
Rehearing Order, 189 FERC ¶¶ 90-99. Although Bayou says
the Commission should have done more to explain why the
project’s greenhouse gas emissions did not warrant the denial
of the project, we have previously approved similar analyses
by the Commission. See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 240-42 (2025); Food & Water Watch
v. FERC, 104 F.4th 336, 346-47 (2024); Ala. Mun. Distribs.
Grp. v. FERC, 100 F.4th 207, 214-15 (2024); Ctr. for
Biological Diversity, 67 F.4th at 1183-84. Bayou has not
provided any reason we should not do the same here.
19
b. The Terminal’s benefits
Insofar as the Commission attempted to balance the
Terminal’s benefits against its harms, Bayou argues the record
does not support the Commission’s decision to authorize the
Terminal. For the reasons discussed above at 14-15, the
Commission did not bear that burden; it was Bayou that needed
to make an affirmative showing that the Terminal would be
inconsistent with the public interest. See Saguaro, 145 F.4th at
87.
In any event, the Commission explained why the Terminal
would not be inconsistent with the public interest. In addition
to invoking the presumption in favor of authorization, the
Commission cited § 717b(c), which provides that the exportation of gas to any country with which the United States has
entered into a free trade agreement “shall be deemed to be
consistent with the public interest.” Initial Authorization Order, 187 FERC ¶ 23; November 2024 Rehearing Order, 189 FERC
¶¶ 39, 46. Here the DOE had authorized the Terminal to export
LNG to such countries. Initial Authorization Order, 187 FERC
¶ 8. Bayou attempts to minimize the significance of these considerations, but the Commission was obligated to consider
them. See Saguaro, 145 F.4th at 87; § 717b(c).
The Commission also acknowledged the potential adverse
effects of the Terminal, but it found that those effects “would
not be significant or would be reduced to less-than-significant
levels with the implementation of avoidance, minimization,
and mitigation measures recommended in the EIS and adopted
by the [Commission].” Initial Authorization Order, 187 FERC
¶ 29. The Commission therefore concluded that Bayou had not
made “the affirmative showing of inconsistency with the public
interest that [was] necessary to overcome the presumption in
section 3.” Id.; see November 2024 Rehearing Order, 189
20
FERC ¶ 37. That conclusion was reasonable, reasonably
explained, and supported by substantial evidence.
c. The authorization of the Pipeline
As we have said, the Commission will issue a certificate
for the construction of a pipeline only if the pipeline “is or will be required by the present or future public convenience and
necessity.” § 717f(e). Recall that the Commission follows a
three-step approach under Section 7, asking whether there is a
“market need” for the pipeline; whether the project will cause
certain adverse effects; and if so, whether the pipeline’s benefits are greater than its adverse effects. Env’t Def. Fund, 2 F.4th at 961.
Bayou primarily takes issue with the Commission’s
analysis at the first and third steps. In Bayou’s telling, the
Commission relied “almost exclusively on a single precedent
agreement between two Venture Global subsidiaries” to take
the Pipeline’s full capacity. A precedent agreement is a
“preconstruction contract[] . . . for the natural gas the pipeline would transport.” Id. at 959. Bayou argues the Commission’s
reliance upon the precedent agreement was arbitrary because
the benefits of the Pipeline identified by the Commission
depended upon the Terminal, the approval of which was itself
arbitrary, and the Commission did not explain why those benefits outweighed the harms caused by the Pipeline.
We can easily dispose of Bayou’s first argument. For the
reasons explained above at 13-20, the Commission’s approval
of the Terminal complied with the NGA. Consequently, it
could consider the benefits stemming from the Terminal when
considering the application for the Pipeline.
As for Bayou’s second argument, we see no error in the
Commission’s weighing of the Pipeline’s benefits and harms.
21
At the first step — identifying a “market need” — the
Commission cited the long-term precedent agreement between
the Venture Global subsidiaries to take the Pipeline’s full
capacity. See Initial Authorization Order, 187 FERC ¶¶ 37-38;
November 2024 Rehearing Order, 189 FERC ¶¶ 48-51. “As a
general rule,” we have held that the “FERC may find market
need by relying solely on a precedent agreement.”
Cumberland, 153 F.4th at 1309. True, as Bayou notes, we had
previously said that a precedent agreement is not “always
sufficient” to show market need. Env’t Def. Fund, 2 F.4th at
972. As we have since clarified, however, that decision provided only a narrow exception to the general rule “when an
agreement involves affiliated entities and there is plausible
evidence of self-dealing.” Cumberland, 153 F.4th at 1309
(cleaned up). As the Commission found below and the
Intervenors note on appeal, Bayou has not presented evidence
of — or even alleged — self-dealing by the Intervenors. See
November 2024 Rehearing Order, 189 FERC ¶ 48 (“Here,
there is no evidence of impropriety or self-dealing to indicate
anti-competitive behavior or affiliate abuse”). “[A]bsent selfdealing, FERC was entitled to rely on the precedent agreement
without considering additional evidence.” Cumberland,
153 F.4th at 1310.
Bayou also argues the Commission used the precedent
agreement as “a proxy for the foreign sales the Terminal would
enable,” which was inappropriate because the DOE exercises
exclusive authority over those exports. The Congress has
already settled this issue by declaring that exports to countries with which the United States has a free trade agreement are
“consistent with the public interest.” § 717b(c). Accepting
Bayou’s position would “thwart Congress’ directive and intent,
as expressed in Section 3.” City of Oberlin v. FERC, 39 F.4th
719, 727 (D.C. Cir. 2022) (cleaned up). Accordingly, we have
held “[n]othing in Section 7 prohibits considering export
22
precedent agreements in the public convenience and necessity
analysis.” Id. at 726. In Oberlin we upheld the Commission’s
approval of a pipeline precisely because the Commission had
relied upon a precedent agreement for the exportation of gas to
a free-trade-agreement country. See id. at 726-27. “We would
be hard pressed,” we explained, “to conclude that FERC’s
reliance on [the] clear statutory directive [in § 717b(c)] was
unjustified.” Id. at 727. So too here. It was reasonable for the
Commission, when determining whether to approve the
Pipeline, to consider how the Pipeline would support the
Terminal and, hence, the exports authorized by the DOE. See
November 2024 Rehearing Order, 189 FERC ¶ 58; above at 19.
At the third step, Bayou claims the Commission did not
adequately explain how the benefits of the Pipeline outweighed
the adverse effects. We find the Commission’s explanation sufficiently clear. In the November 2024 Rehearing Order the
FERC addressed Bayou’s argument about the Pipeline’s
adverse effects on landowners, noting that Venture Global CP
Express had already taken steps to mitigate those effects, such
as by revising the route of the Pipeline. 189 FERC ¶ 63. As for
the Pipeline’s benefits, the Commission cited not only the precedent agreement; it also found the project would “provide
domestic public benefits, including: adding new transportation
options for producers and shippers; boosting the domestic
economy and the balance of international trade; and supporting
domestic jobs in gas production and transportation.” Id. ¶ 68;
see also id. ¶ 69 (citing “an increase in the local population,
increased employment opportunities, increased demand for
housing and public services, and an increase in state and local
government revenues” as other benefits associated with the
Pipeline). The Commission also cited “minor positive
economic impacts” that would occur during the construction of
the project, including increased employment and spending. Id.
¶ 69 & n.299. That the Commission considered some of these
23
benefits to be “minor” compared to the precedent agreement is
of no moment because it was obligated to consider “all relevant
factors.” Env’t Def. Fund, 2 F.4th at 959; see Atl. Refin. Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378, 391 (1959) (Section
7 “requires the Commission to evaluate all factors bearing on
the public interest”).
The Commission therefore concluded that the “net positive
benefit to the domestic economy . . . . in addition to the
significant evidence of need as demonstrated by the long-term,
binding precedent agreement,” demonstrated that the Pipeline
was required by public convenience and necessity. November
2024 Rehearing Order, 189 FERC ¶ 69. Bayou may disagree
with the result of the Commission’s balancing, but its decision
was reasonably explained and supported by substantial
evidence. We therefore reject Bayou’s challenge to the authorization of the Pipeline.
B. Challenges under the NEPA
Bayou raises several challenges under the NEPA. As the
Supreme Court recently explained, “The bedrock principle of
judicial review in NEPA cases can be stated in a word:
Deference.” Seven Cnty., 605 U.S. at 185.
Bayou’s challenges ultimately ask us to engage in a more
searching review than precedent allows. See Cumberland,
153 F.4th at 1311 (“After Seven County, the era of searching
NEPA review is over”). Considering the “substantial judicial
deference required in NEPA cases,” Seven Cnty., 605 U.S. at
174, we must reject Bayou’s NEPA challenges.
1. The Terminal’s cumulative effects
Bayou first takes issue with the FERC’s analysis of the
Terminal’s cumulative effects on air quality. At step two of the
24
analysis, the EIS predicted exceedances of the 1-hour NAAQS
for NO2. The SEIS, however, did not predict any exceedances
of the NAAQS for NO2 or PM2.5. The FERC adopted the findings of the SEIS in the May 2025 Rehearing Order. 191 FERC
¶ 55.
Bayou asserts this was arbitrary for three reasons. First, the
Commission relied upon a new model in the SEIS “without
demonstrating awareness of why it reached a different
conclusion” than it had in prior analyses, referring to the EIS
for this project and to its review of other nearby terminals.
Second, the FERC did not account for emissions from the
Magnolia LNG Terminal in the SEIS, a project which was
included in the cumulative effects analysis in the EIS. Third,
the FERC did not account for emissions from marine vessels
serving other nearby terminals.
a. New model
The record squarely contradicts Bayou’s first argument.
The SEIS explained that the updated air quality modeling submitted by Venture Global CP2 LNG “used the most recent
validated air quality monitor data and the most recent
emissions inventory revisions provided by the LDEQ.” The
FERC then showed its awareness of that update in both its May
and August 2025 Rehearing Orders. The FERC noted that the
updated air quality modeling relied upon the “most recent
emissions inventory” data from the LDEQ, which had changed
since the EIS and which “largely” accounted for the differences
between the modeling in the EIS and the SEIS. August 2025
Rehearing Order, 192 FERC ¶ 13; May 2025 Rehearing Order,
191 FERC ¶¶ 55 n.204, 63. The FERC also explained that it
reached a different conclusion in the SEIS than it had in its
analyses of other nearby terminals because of differences in the
air dispersion modeling, “including differences in emission
25
rates, stack heights, variability in terrain near each facility, and other terminal-specific factors.” August 2025 Rehearing Order,
192 FERC ¶ 13; May 2025 Rehearing Order, 191 FERC ¶ 65.
The FERC did not detail every particular change to the inventory, but it was not required to do so; “all we may demand” is
“a reasonable level of detail.” Save the Sound, Inc. v. FAA, No.
24-1028, 2026 WL 2093931, at *5 (D.C. Cir. July 26, 2026)
(citing Seven Cnty., 605 U.S. at 180-81).
b. Magnolia Terminal
Bayou next challenges the FERC’s omission of the
Magnolia Terminal from the cumulative effects analysis in the
SEIS. The FERC had authorized the Magnolia Terminal, which
was also located on the Calcasieu Ship Channel, in 2016.
Before the FERC completed the SEIS for this terminal,
however, the Magnolia Terminal’s LDEQ-issued air permits
had expired, and the LDEQ had accordingly omitted the
Magnolia Terminal from its emissions inventory. See August
2025 Rehearing Order, 192 FERC ¶ 14. This was one of several
changes the LDEQ had made to its emissions inventory. 5
According to Bayou, the Magnolia Terminal nonetheless
remained a “reasonably foreseeable” source of emissions
because the loss of its permits did not invalidate the FERC’s
authorization of the terminal, so the FERC needed to include it
in the cumulative effects analysis.
The FERC reasonably explained its reasons for omitting
the Magnolia Terminal. The Commission considered the
LDEQ’s emissions inventory “the most reliable data input for
the cumulative [effects] analysis,” and that agency had omitted
the Magnolia Terminal because its air permits had expired.
August 2025 Rehearing Order, 192 FERC ¶ 15. Bayou argues
5
See LDEQ, Public Notice, at 261-65 (Jan. 31, 2025),
https://edms.deq.louisiana.gov/app/doc/view?doc=14632557.
26
that the Commission still should have included the Magnolia
Terminal because it did not say that terminal was no longer a
“reasonably foreseeable” source of emissions. But that is, as a
practical matter, just what the Commission concluded. The
FERC noted that the Magnolia Terminal’s authorization under
§ 717b remained in effect, but finding “no record evidence
explaining why Magnolia LNG’s air permits ha[d] allegedly
expired,” declined to “speculate as to the reasons why.” Id.
Instead, it “grant[ed] the LDEQ — the state agency tasked with
implementing the CAA — a presumption of regularity formed
by general principles of administrative law.” Id.
This was consistent with the Commission’s longstanding
practice of relying upon “other agencies’ expertise in carrying
out its NEPA responsibilities.” May 2025 Rehearing Order,
191 FERC ¶ 61. It was neither unreasonable nor arbitrary for
the FERC to rely upon the LDEQ’s most recent emissions
inventory, to grant that inventory a presumption of regularity,
and to omit the effects of a terminal the future of which was not foreseeable. Cf. Appalachian Voices v. FERC, 139 F.4th 903,
927 (D.C. Cir. 2025) (Henderson, J., concurring) (“[C]ourts
cannot demand that agencies run down every rabbit hole”).
Bayou also argues the FERC needed to consider the
Magnolia Terminal because the Magnolia Terminal’s authorization under § 717b remained in effect, so the Commission
would not have another opportunity to consider the cumulative
effects of the proposed Terminal and the Magnolia Terminal if
the latter were to obtain new air permits. Under the NEPA,
however, an agency is supposed to focus upon “the project at
hand.” Seven Cnty., 605 U.S. at 186-87. That is what the FERC
27
did by excluding the speculative re-emergence of a different
project. 6
c. Marine vessels serving other terminals
When considering the cumulative effects of the Terminal,
the FERC limited its consideration of mobile source emissions
to those attributable to the proposed Terminal and to Global
Venture’s Calcasieu Pass LNG Terminal. Initial Authorization
Order, 187 FERC ¶ 185; May 2025 Rehearing Order, 191
FERC ¶ 61. Bayou claims the FERC should have also considered emissions from ship traffic related to six other terminals.
The FERC included the mobile source emissions attributable to the Terminal and to the Calcasieu Pass LNG Terminal
principally because of their proximity to each other and
because the Commission had updated emissions data for the
Calcasieu Pass LNG Terminal. May 2025 Rehearing Order,
191 FERC ¶ 61 & n.229. In order to account for their emissions, the FERC treated these mobile sources as stationary
6
Bayou also alleges the FERC included the Magnolia Terminal in
the cumulative effects analysis of an SEIS issued one week after it issued the SEIS in this proceeding. In both instances the FERC relied upon the emissions inventory from the LDEQ. In the other SEIS,
however, the FERC explained in response to comments that the
emissions inventory used in the initial EIS “was not the subject of the court proceeding and remand” in Healthy Gulf and thus was
“outside the scope of th[e] supplemental final EIS.” Commonwealth LNG SEIS, No. CP19-502-001, Accession No. 20250516-3002, app.
D at 5 (May 16, 2025). The timing of the inventory used in the
proceedings may therefore explain the Commission’s treatment of
the Magnolia Terminal. We express no view on the Commission’s
decision not to update the emissions inventory in the other
proceeding. Here we conclude only that it was reasonable for the
FERC to rely upon the most recent emissions inventory from the
LDEQ in preparing the SEIS.
28
sources. Id. ¶ 58. This approach involved a “large number of
assumptions,” including “calculating emissions based on the
upper limit of ships that the applicant can utilize.” Id. ¶ 58 &
n.220.
The FERC then explained why applying that approach to
mobile sources related to the six terminals would have been too
speculative. Specifically, the FERC addressed the EPA’s preferred air-dispersion model (AERMOD), which Bayou says the
FERC should have used to model mobile source emissions.
Given the large number of assumptions the FERC needed to
make in order to model the mobile source emissions related to
the two Venture Global terminals, the FERC concluded that
extending this approach to other mobile sources “would not
provide accurate” information. Id. ¶ 60. Emissions from those
other mobile sources were therefore not “reasonably
foreseeable.” Id.; see Del. Riverkeeper Network v. FERC,
753 F.3d 1304, 1310 (D.C. Cir. 2014) (stating the NEPA “does
not demand forecasting that is not meaningfully possible”
(cleaned up)).
Bayou did not point to any methodology other than
AERMOD the FERC could have used to measure the emissions
from additional mobile sources. In insisting the FERC could
have used the AERMOD tool to measure mobile source emissions, Bayou cites one case in which the FERC did that. The
FERC persuasively distinguished that case in the May 2025
Rehearing Order: The cumulative effects modeling in that case
“reflected unique situational circumstances” because “all three
[relevant] LNG terminals were simultaneously undergoing
initial environmental review at the time.” 191 FERC ¶ 59. The
FERC therefore included mobile emissions from those terminals because it “possessed current, facility-specific mobile
source emissions data for each individual project.” Id. In this
case the FERC was not currently reviewing all the other termi29
nals, id., and those terminals “may have undergone changes”
since the FERC had completed its NEPA analysis of them several years earlier, August 2025 Rehearing Order, 192 FERC
¶ 20; see J.A. 786 (Bayou’s Request for Rehearing of the Initial
Authorization Order citing EIS’s completed between 2015 and
2022 for other terminals). So much for Bayou’s claim that the
Commission “offer[ed] no facts distinguishing the scenario
here from [the] other scenario[] in which AERMOD was
successfully used to model the impact of ship emissions.”
The FERC also explained that its decision to omit mobile
source emissions from the other six terminals was consistent
with both EPA regulations and with the LDEQ’s emissions
inventory. See May 2025 Rehearing Order, 191 FERC ¶ 61
(citing 40 C.F.R. pt. 51, App. W). The FERC consulted with
both agencies when preparing the SEIS, and “neither suggested
that the Commission should analyze mobile source emissions
more than it had already done.” Id. ¶ 58 n.219. For the reasons
already explained above at 25-26, and those discussed below at
31-33, the FERC was entitled to rely upon the expertise of
those agencies.
In order to comply with its NEPA obligations, “an agency
will invariably make a series of fact-dependent, contextspecific, and policy-laden choices about the depth and breadth
of its inquiry.” Seven Cnty., 605 U.S. at 182-83. We will affirm
those choices “so long as they fall within a broad zone of
reasonableness.” Id. at 183. The FERC provided its reasons for
excluding the disputed emissions sources in its cumulative
effects analysis. Under our deferential standard of review, we
may not set aside that well-reasoned decision.
30
2. The Commission’s use of NAAQS in the
cumulative effects analysis
Even accepting the FERC’s conclusion that the Terminal’s
emissions would not cause exceedances of the NAAQS for
NO2 and PM2.5, Bayou says the Terminal’s emissions would
still cause harms such as “premature deaths, asthma, and lost
days of school and work.” Bayou claims it was arbitrary and
capricious for the FERC to rely upon the NAAQS rather than
the EPA’s CO-Benefits Risk Assessment Health Impacts
Screening and Mapping Tool (COBRA), which Bayou says
would have more accurately accounted for the health effects of
the Terminal’s emissions. We disagree.
As an initial matter, the FERC and the Intervenors argue
that Bayou forfeited this argument by failing to raise it in its
first request for rehearing. We will not ordinarily consider an
objection that was not “urged before the Commission in the
application for rehearing,” unless, that is, there is a “reasonable ground for [the] failure so to do.” § 717r(b). Bayou acknowledges that it did not challenge the Commission’s reliance upon
the NAAQS until its second rehearing request but argues its
delay should be excused because only the “SEIS and
subsequent rehearing orders . . . made relevant the question of
whether air pollution below the NAAQS was safe.” But it
seems Bayou was on notice of, and aggrieved by, the
Commission’s reliance upon the NAAQS long before it raised
its challenge; the EIS predicted that the O3 emissions from both
the Terminal and the Compressor Station would exceed the
SILs but not the relevant NAAQS. As for the NO2 and PM2.5
emissions, the EIS predicted no exceedances of the annual
NAAQS for NO2 or of the annual and 24-hour NAAQS for
PM2.5 with respect to the Terminal. In short, the Commission’s
use of the NAAQS as a threshold in the cumulative effects
analysis was clear before Bayou filed its first rehearing request.
31
In any event, even assuming Bayou had reasonable ground
for not raising this argument earlier, it fails on the merits. The EPA sets NAAQS at a level “requisite to protect the public
health” with “an adequate margin of safety.” 42 U.S.C.
§ 7409(b)(1). We have previously held the FERC
“appropriately relied on [NAAQS] as a standard of comparison
for air-quality impacts” because that approach “enabled
decisionmakers and the public to meaningfully evaluate the
project’s air-pollution effects by reference to a generally
accepted standard.” Sierra Club v. FERC (Sabal Trail),
867 F.3d 1357, 1370 n.7 (2017), abrogated on other grounds
by Seven Cnty., 605 U.S. 168. Other circuits have similarly held
that federal agencies may rely upon the NAAQS in making
their own health-related determinations consistent with the
NEPA. See, e.g., Diné Citizens Against Ruining Our Env’t v.
Haaland, 59 F.4th 1016, 1045-46 (10th Cir. 2023) (Bureau of
Land Management’s review of applications for permits to drill
for oil and gas); Lowman v. FAA, 83 F.4th 1345, 1364-66 (11th
Cir. 2023) (Federal Aviation Administration’s review of proposed airport expansion); Coal. for Advancement of Reg’l
Transp. v. Fed. Highway Admin., 576 F. App’x 477, 491-92 &
n.1 (6th Cir. 2014) (Federal Highway Administration’s review
of the proposed construction of bridges).
As the FERC notes, Bayou has not pointed us to a single
case in which a court has overturned an agency’s reliance upon
the NAAQS as part of its NEPA analysis. Bayou instead argues
our decision in Sabal Trail, upholding the FERC’s use of
NAAQS in its cumulative effects analysis, does not apply here
because the petitioners in that case did not present evidence
“directly forecasting the health impacts that the specific
project’s pollution would cause.” Our reasoning in Sabal Trail,
however, did not rest upon a lack of evidence. We specifically
approved the Commission’s reliance on NAAQS because they
provided a “generally accepted standard” against which
32
interested parties could “meaningfully evaluate” the proposed
project. 867 F.3d at 1370 n.7.
Bayou also disputes the FERC’s assertion that the NAAQS
are “designated as safe by [the] EPA.” Bayou again argues that
NAAQS-compliant emissions are not completely harmless and
points to the benefits of achieving an emissions level below the
NAAQS. We do not doubt that achieving an emissions level
below the NAAQS may result in additional benefits, but that
does not mean the NAAQS are not set at a “safe” level. Again,
federal law mandates that the EPA set primary NAAQS at a
level “requisite to protect the public health” with an “adequate
margin of safety.” 42 U.S.C. § 7409(b)(1). Therefore, “the
Agency’s establishment of . . . NAAQS demonstrates that it
did reach a conclusion regarding ‘safe’ . . . levels.” Am.
Trucking Ass’ns v. EPA, 283 F.3d 355, 368 (D.C. Cir. 2002).
Finally, Bayou touts the utility of the COBRA, but the
FERC explained its reasons for choosing instead to rely upon
the NAAQS: The EPA is “the air quality authority with the
expertise to establish air quality thresholds/limits to protect
public health required by the CAA.” August 2025 Rehearing
Order, 192 FERC ¶ 29 (quoting May 2025 Rehearing Order,
191 FERC ¶ 49). According to the EPA, the NAAQS are
“designed to ensure public safety by setting acceptable
concentration limits that minimize health risks and to protect
sensitive populations.” Id. And the EPA must “periodically
review the NAAQS and the data used to develop the
standards,” ensuring that the standards remain up to date. May
2025 Rehearing Order, 191 FERC ¶ 72. In contrast, the EPA
had described the COBRA as a “screening tool” used primarily
at “the state or county level” that was not yet appropriate for
the modeling of “project-specific analyses” because of remaining uncertainties regarding “key components” of the model.
August 2025 Rehearing Order, 192 FERC ¶ 29 & n.116.
33
The FERC thus did not blindly defer to the NAAQS but
rather made an independent judgment that using them as part
of its cumulative effects analysis was more appropriate than
using the COBRA. Bayou may disagree with the FERC’s decision, but the FERC’s “choice among reasonable analytical
methodologies is entitled to deference.” Sabal Trail, 867 F.3d
at 1370 n.7 (quoting Cmtys. Against Runway Expansion, Inc. v.
FAA, 355 F.3d 678, 689 (D.C. Cir. 2004)); cf. Ala. Mun.
Distribs., 100 F.4th at 214 (holding the FERC was not required
to use the “social cost of carbon tool” when it had not yet
determined how to “render that tool useful for project-level
analyses”).
3. The Moss Lake Compressor Station’s cumulative
effects
The SEIS concluded at step one of its cumulative effects
analysis that the Compressor Station’s emissions would not
exceed any SILs for any criteria pollutant. Bayou argues the
FERC’s decision to end its analysis there is inconsistent with
our decision in Healthy Gulf.
In Healthy Gulf, the petitioners argued the FERC’s
cumulative effects analysis of a project’s NO2 emissions was
arbitrary because of the way the FERC relied upon the SILs.
107 F.4th at 1043. After the FERC determined the project’s
NO2 emissions would not exceed the relevant SIL, the FERC
“then redeployed the SIL to determine whether the Project’s
cumulative effects were significant.” Id. The FERC concluded
the project’s cumulative effects were insignificant because its
incremental NO2 emissions did not exceed the relevant SIL at
each NAAQS exceedance location. Id. “In other words, the
Commission said that because the project’s incremental effects
were insignificant, its cumulative effects were, too.” Id. at
1044. This “non sequitur” made the FERC’s decision arbitrary:
34
NEPA requires the Commission to assess the
Project’s cumulative effects, which are the
effects on the environment that result from the
incremental effects of the action when added
to the effects of other past, present, and reasonably foreseeable actions. Simply measuring the
Project’s own emissions against the SIL fails to
satisfy that requirement. Indeed, on the
Commission’s view, the cumulative effect of a
Project’s emissions would never be deemed significant unless the Project’s incremental
emissions were already significant on their own.
That approach would eviscerate the purpose
behind requiring a distinct cumulative effects
analysis in the first place, which is to account
for collectively significant environmental
impacts that may result from individually minor
actions.
Id. (cleaned up). We remanded the matter for the Commission
either to explain how its use of the SILs was “consistent with a
proper cumulative effects analysis” or to use a different
methodology. Id.
Bayou argues this reasoning also applies to the
Commission’s analysis of the cumulative effects of the
Compressor Station. For its part, the FERC reads Healthy Gulf
as a case about the third step of the cumulative effects
analysis — i.e., whether a project’s predicted SIL exceedance
and its NAAQS exceedance will occur simultaneously. On that
reading of Healthy Gulf, the FERC says it can still end its
analysis at step one if it determines that a project’s emissions
will not exceed the relevant SIL. See August 2025 Rehearing
Order, 192 FERC ¶ 23 (concluding that “Healthy Gulf disa35
greed with the Commission’s re-use of the SIL” at step three
but not with its initial use at step one).
Healthy Gulf is not applicable only to the third step of the
FERC’s cumulative effects analysis. In that case the FERC’s
error occurred at the third step, but nothing in the opinion suggests our reasoning turned on that. Rather, we explained
without regard to the step that the Commission’s approach
“would eviscerate the purpose behind requiring a distinct
cumulative effects analysis.” 107 F.4th at 1044.
Still, nothing in Healthy Gulf requires us to remand this
matter. After all, we did not hold the FERC could never end its
analysis of cumulative effects after finding that a project’s
emissions would not exceed the relevant SIL, that is, at step
one. On the contrary, we left open the possibility that the FERC
could explain on remand “how its use of the . . . SIL [was]
consistent with a proper cumulative effects analysis.” Id.
The FERC provided that explanation in this case. The
SEIS reported that “the maximum emission impacts for all criteria pollutants” from the Compressor Station were “effectively
insignificant,” so the emissions did not “add any meaningful
amount when combined with past, present, and reasonably
foreseeable emissions within the regional air environment.” In
reaching this conclusion, the SEIS also looked at “facilities in
the vicinity of the Moss Lake Compressor Station” and
determined that the cumulative effects of the NO2 and PM2.5
emissions were not significant based upon four considerations:
(1) the magnitude of the emissions and the distance between
the Compressor Station and other emitting facilities; (2) that
the facilities were subject to permitting programs under the
CAA that ensured they would not cause or contribute to any
NAAQS exceedances; (3) that local monitors showed ambient
levels below the NAAQS; and (4) that the magnitude of the
36
effects of the Compression Station were below the SILs. See
May 2025 Rehearing Order, 191 FERC ¶¶ 51-52.
“Black-letter administrative law instructs that when an
agency makes those kinds of . . . predictive or scientific
judgments, and decides what qualifies as significant or feasible
or the like, a reviewing court must be at its ‘most deferential.’” Seven Cnty., 605 U.S. at 182 (quoting Balt. Gas & Elec. Co. v.
NRDC, 462 U.S. 87, 103 (1983)); see also Save the Sound,
2026 WL 2093931, at *5 (collecting cases demonstrating our
long history of deference to agency decisions requiring
“technical expertise”). This is particularly appropriate here,
because “requiring extensive air modeling for every source is
costly and overly burdensome, especially where the source is
projected to emit insignificant amounts of pollution.” Sierra
Club v. LDEQ, 100 F.4th 555, 565 (5th Cir. 2024).
In sum, the Commission reasonably explained why, in the
context of this proceeding, the Compressor Station’s emissions
did not warrant further analysis. 7 Given the deference we owe
the Commission on this point, we reject Bayou’s argument to
the contrary.
7
Bayou also questions whether it was appropriate for the FERC to
use the SILs as a statistical threshold because they also reflect policy considerations. We do not share this concern. As mentioned above at 7, we have described SILs as a numerical value “below which the
EPA considers a source to have an insignificant effect on ambient air quality.” Sierra Club, 705 F.3d at 461. We have no reason to think that does not hold true here considering the FERC consulted with the EPA on the final SEIS “regarding the methodologies for various
impact analyses.” May 2025 Rehearing Order, 191 FERC ¶ 58 n.219.
37
4. The harm to the commercial fishing industry
Finally, Bayou argues the FERC failed to take a hard look
at the Terminal’s effects on the commercial fishing industry in
Cameron Parish. According to Bayou, the FERC “downplayed
the harm” to the commercial fishing industry by describing it
as “temporary” and erroneously concluding that the Terminal’s
effects would be “localized.”
a. Temporary harm
Bayou argues the FERC failed to consider whether the
adverse effects on the aquatic ecosystem would have a longterm effect on the commercial fishing industry, namely, that a
single season with a reduced catch could force commercial
fishers out of business permanently. But the FERC did not
ignore this potential effect.
In the Initial Authorization Order the FERC acknowledged
comments claiming the Terminal would “threaten[] the
viability of the fishing and shrimping industries . . . in the
project area.” 187 FERC ¶ 107. The Commission also noted
that the EIS analyzed the “potential socioeconomic impacts on
commercial fisheries and shrimping, impacts to commercial
fisheries and fishermen in environmental justice communities,
and cumulative temporary and permanent impacts on
commercial fishing.” Id. ¶ 110 (cleaned up). For example, the
Commission observed that construction would occur “during
peak fishing and recreational seasons,” id. ¶ 111, and cited
potential effects such as increased vessel traffic, obstructed
access to certain fishing locations, and changes to the population of shrimp, fish, and crab, id. ¶ 112. The FERC even
acknowledged that “[p]ermanent impacts on recreational and
commercial fisheries in the ship channel may occur due to the
loss of available fishing areas from operation of the LNG
terminal’s marine facilities and LNG carrier traffic.” Id. ¶ 111.
38
The FERC went on, however, to consider efforts to mitigate these potential harms as recommended in the EIS. Those
efforts included project-specific procedures designed to minimize the effects on wildlife and habitats, a training program to
inform workers about wildlife and endangerment factors, and
an engagement plan to allow local fishers and residents to communicate problems directly to Venture Global. Id. ¶¶ 109, 113.
The Commission also concluded the “overall size of the
waterway and access to and maneuverability within the
Calcasieu Ship Channel” would minimize the effects of the
“proposed use of barges” on fishing activities. Id. ¶ 111.
The FERC again considered Bayou’s argument in the
November 2024 Rehearing Order,189 FERC ¶ 101, once more
acknowledged the “serious and potentially long-term impacts”
identified in the EIS, id. ¶ 102, and again emphasized the mitigation efforts recommended in the EIS and adopted by the
Commission, id.; see also id. ¶¶ 106-08. Based upon these
orders, we readily conclude that the FERC considered the
potential long-term effects on the commercial fishing industry
and provided a reasoned explanation for approving the
Terminal despite those potential effects.
b. Localized harm
Bayou next disputes the FERC’s conclusion that the
Terminal’s effects “would be localized.” Id. ¶ 112.
Specifically, Bayou argues the FERC erroneously concluded
that the area near the Terminal does not have any “unique
features” not found in other parts of the Calcasieu Ship
Channel. Id. ¶ 114.
The EIS explained that the waters near the terminal are
divided by what is referred to as the “Firing Line.” In waters
north of the Firing Line, shrimp harvesting season varies by
year; south of the line, where the Terminal is located, shrimp
39
harvesting occurs year-round. According to Bayou, this means
the area near the Terminal is “prime real estate” because it is
“the only portion of the Calcasieu Ship Channel that is open for
commercial shrimp harvesting year-round.” Bayou further
claims the Terminal will cover part of the area through which
shrimp migrate to and from Calcasieu Lake.
Citing the EIS, the FERC recognized that “impacts on
shrimping vessels would be greatest near the Terminal.” Id.
¶ 109. It further explained, however, that the waters around the
Terminal do not have any “unique features or habitat
characteristics” not found in “other locations within the
Calcasieu Ship Channel” and that the Terminal would “leav[e]
approximately 25 river miles upstream” available with “the
same fish common to the lower estuarine area.” Id. ¶¶ 109, 114.
Bayou says this was erroneous, again emphasizing the distinction between waters north and south of the Firing Line. As the
Intervenors note, however — and as shown on the map
below — the Terminal (outlined in green) covers only a small
portion of the area south of the Firing Line (outlined in white). Even accepting Bayou’s characterization of waters south of the
Firing Line as “prime real estate,” the Terminal leaves most of
those waters available to commercial fishers.
40
The Commission also explained that commercial fishing
vessels would still have access to those waters. “[D]ue to the
overall size of the waterway and access to and maneuverability
within the Calcasieu Ship Channel,” fishing activities “would
not be significantly affected by the proposed use of barges”
during the construction of the Terminal. Id. ¶ 106. The FERC
acknowledged that once the Terminal becomes operational,
“LNG carriers in transit could impact commercial and
recreational fishing vessels” in the Channel insofar as those
vessels would have to give way until the LNG carrier passed,
but they could then resume their activities throughout the
Channel. Id. ¶ 107. This meant the Terminal “would have a
moderate, but not significant impact on commercial fishing.”
Id. ¶¶ 107-08. Bayou gives us no reason to disturb the FERC’s
conclusion on this point.
41
III. Conclusion
For the reasons stated, the petitions for review are
Denied.